... and sashimi (see photo)

The detectors (BRIKEN tubes, CLOVER, VETO detectors, AIDA) 
are mounted, tested and ready for November commissioning,
except beam detectors a Plastic TOF and a Si detector which
will be attached to the PE shielding.
DACQs (BRIKEN, AIDA) are running. The synchronization monitoring
program which was working in June, for some reason is not functioning
properly now and is being worked on (desirable but not required).
The data merger and near-line analysis programs are being worked on.