| <p>27/05/24</p>
<p>The carme-gsi computer has been moved from the server room into the shifter control room.</p>
<p>Startup of the DAQ looks OK. Settings loaded 2024Apr24</p>
<p>System wide checks OK. Aida16 clock status fails. Aida16 ADC calibration fails. Rest OK.</p>
<p>All FEEs look OK, we again see high rates in aida15 ~ 12k data items/sec, rate in other FEEs is 0.</p>
<p>Testing of the pulser widths has been done. Pulser widths will be uploaded soon.</p>
<p>Background run started. No beam, no target. File G22-201 and R2. Data being written is ~128 kb/s. Run will be left overnight, no night shift.</p>
<p>28/05/24</p>
<p>DAQ continues with alpha background run.</p>
<p>System wide checks OK. Aida16 clock status fails. Aida16 ADC calibration fails. Rest OK. Temps OK</p>
<p>Data can be seen in the spectrum browser on MIDAS. CARME monitoring code was started incorrectly yesterday. It has now be restarted and a small number of events are seen</p> |