| <p>12:15 restarted measurement with target - Run 83</p>
<p>same settings as for runs 76, 77 etc</p>
<p>ROOT histograms NOT zeroed</p>
<p>Beam at 8e8, target density at 1.5e13, scintillator @ 0 deg. peak rate 5000</p>
<p>status screenshots attached</p>
<p>15:15: Checks all ok, peaks are peaky (attatchment 8)</p>
<p>16:45 Checks all ok.</p>
<p>17:45 Checks all ok. IMP Froze and has been restarted. Peaks good. Light turned off iin cave.</p>
<p>18:40: Checks all ok. Target great at 1e13.</p>
<p>22:20 Checks done - all okay except aida green-to-red was not working, but still writing data to disk. Carlo trying to figure it out now. All other checks were okay. Daedalus crashed, restarted and target still at 1e13. </p> |