  146   Tue Nov 9 15:03:29 2021 RSS + OGBurnt cables issuesUpper part of the frame was mounted. In
order to do so, the valve was closed, turbo
wire and hose were disconnected and then
 7x 
  151   Thu Nov 11 11:44:58 2021 RSS + ML OG + CB (remotely)CARME baking startedWith the help of OG, the baking tent was
built. MG started baking around 11:30 am
with a rate of 0.2 K/minute.
 IMG_5535.JPGIMG_5537.JPGIMG_5531.JPGIMG_5534.JPGIMG_5539.JPG 
  149   Wed Nov 10 18:24:12 2021 RSSThermocouple labelling1. Detector

2. Chamber back

3. Strain relief
 labeling.JPG.svgLabelling.svgIMG_5512.JPG 
  428   Tue Jul 25 09:12:15 2023 RSSBuilding tent
10:10  IE514 2.0e-08mbar

Upstream
part of the CARME is covered.
 BD01C0C8-5181-49B8-8751-AD4C99A459CC.jpeg7B3836F1-8A7E-491B-AFDC-46033BF84760.jpeg 
  429   Wed Jul 26 08:28:09 2023 RSSBuilding tent
09:26  IE514 1.96e-08mbar
 IMG_9897.jpgIMG_9899.jpgIMG_9901.jpgIMG_9902.jpg 
  430   Thu Jul 27 09:43:56 2023 RSSThermocouples connected -2
10:30  IE514 1.80e-08mbar

Most
of the CARME is covered by the baking tent.
The tent needs to be closed and a bit covered
 IMG_9920.jpgIMG_9919.jpg 
  639   Sun Jun 16 06:02:31 2024 RSSRun 77Run 77 started at 06:48

Cooler voltage setpoint 247.0 V.

 
 20x 
  717   Tue Jun 3 14:54:29 2025 PMH, STRun 48Run 48 started. Everything is running again.
We started at 3E13 at/cm2

D+ beam deuterium target. D+ beam
 6x 
  351   Tue Mar 1 17:36:04 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  352   Tue Mar 1 18:43:41 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  353   Tue Mar 1 19:40:28 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 12x 
  354   Tue Mar 1 19:41:24 2022 PM, LVtarget temperature walkthroughA target temperature walkthrough has been
initiated at 20:41 since the target density
at S1 had slightly decreased (with ~0.1-0.2)
  
  355   Tue Mar 1 20:41:28 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  356   Tue Mar 1 21:34:06 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  384   Thu Dec 8 14:41:19 2022 PJCSResults of tests on AIDA PSU in DL T9We opened one up and soldered a co-ax cable
to one of the +6v power contacts at the output
of the filter board.
 8x 
  385   Wed Jan 18 13:32:36 2023 PJCSMACB settings with either Emulator or VETARWhen using the VITAR connected
to the HDMI port of the root MACB the settings
for all the MACB in the system 0x3.
 macb_apr20.jedmacb_apr20.vhdzybo.jpgMACB.jpg 
  478   Sat Jan 27 20:38:15 2024 PJCS[INFO] Steps to diagnose White Rabbit problemsThis is a suggested sequence of actions
to help with the current problem with the
White Rabbit timestamp distribution. Test
  
  263   Wed Feb 23 22:29:50 2022 PE, EM, CB (remotely)check - 23:30Motor position ok

Data rate: 1030kbytes/s

T ok
  
  109   Wed Oct 6 09:39:59 2021 PB CBOriginal dirty assembly of CARME internalsPB found pictures of the original dirty assembly,
before screws and components were shipped
to DL.
 7x 
  182   Mon Jan 31 08:58:38 2022 OH, TD, JMcentos server configurationSteps taken:
- MIDAS_Releases, Embedded and Exports files
brought across from the previously working
 8x 