Fri Jun 16 10:42:38 2023 |
Lucia B, Federico F | Powercut during long run on LNL9 - end of shift | On 15/06/2023 morning, around 6:32 am,
a powercut caused failure in the Compresed
Air Pressure system. Faraday cup was closed |
 |
29
|
Thu Jun 15 10:13:56 2023 |
Lucia B | 23Na target location | Used and new 23Na targets are in a
box in LAB7, next to the other targets |
|
28
|
Wed Jun 14 11:30:42 2023 |
Lucia B, Carlo B | LNL6-LNL2-LNL9 | On 13/06/2023 afternoon we dismounted LNL6
sputtered target and mounted LNL2 (identical
to LNL1, one Cr layer). We performed a scan |
7x |
27
|
Tue Jun 13 12:44:05 2023 |
Lucia B, Carlo B | LNL4 dismounted - LNL6 mounted | On 12/06/2023 we dismounted LNL4 after
approximately 12 C were deposited.
We then mounted LNL6 (sputtered, |
 |
26
|
Sun Jun 11 09:18:23 2023 |
Lucia B, Carlo B | LNL4 | When opening LNL4 target jar, the
valve did not sound as if air was entering
it: we suspect the target was actually not |
  |
25
|
Fri Jun 9 13:47:24 2023 |
Lucia B, Carlo B | LNL1 | We performed the scan on the LNL1 23Na
target (details in the excel sheets in previous
entry) for the E_p=309 keV resonance. The |
   |
24
|
Thu Jun 8 10:36:26 2023 |
Lucia B, Carlo B | Start of the measurements | We have started the pumping system and
reached ~10^-6 mbar vacuum. We have then
filled the cold trap reaching ~10^-7 mbar. |
|
23
|
Tue Jun 6 11:15:31 2023 |
Lucia B,David R | Work on DAQ for 23Na target test | Attached a picture of the germanium baseline
in the morning 6/6/23.
----------------------- |
|
22
|
Mon Jun 5 15:48:47 2023 |
Lucia B,David R | Work on DAQ for 23Na target test | We started the acquisition via CoMPASS
with one CeBr (90) and the HPGe. The