Message ID: 32     Entry time: Thu Oct 19 10:55:54 2017
Author: Claudia 
Subject: Meeting 19.10. 

CERN-Edinburgh Liaison

  • FC at end of SEC: manual
  • Network access: port free.
  • N2 gas ? 
  • -date for connection of SEC to our chamber: week 30. October, 2nd November alignment. 
  • collimator in front of chamber ?? contact Jorge Alberto about beam tuning in general (maybe add contingency high energy point) ? cc Karl

look for 4 deliveries: 2 bags gain resistors, 1 box luvac, 1 box farnell


2) Parts to be prepared in Edinburgh

  • Iris: no news should be done today
  • spare feedthrough for cooling, to be done.
  • Al degrader: we have 2x10, 2x15 um (hole in center and light checked). 6 um still to prepare, 20 um maybe. mounts to be delivered.  
  • Photo diodes x2 along with degrader foil: PCB & photodiodes here. extra holes for ladder.  drawings there. making degrader foil holder.  target ladder remade.  Preamps, amps? ask Tom. Cocknell preamp tested. 20 mv/MeV (250 MeV max). maybe borrow some more amps from miniball. 
  • Faraday cup SHV to SMA converter: needs to be glued together
  • Window port for front of chamber? Peter to manufacture
  • Extra ribbon cables are needed? need to check with calibration. Also need long ribbon cables. will be done today/tomorrow
  • Photographs and diagrams of experimental setup -- organized clearly for beam operators during tuning: add technical drawing on elog Peter will make it coherent. Safety Folder/Risk Assessment. Safety Datasheets (Ethanol).
  • Alignment -- 2 end caps and one target ladder mount for optics reflector (8 mm diameter?) For survey people. Peter: two ends are done, drawings for S2 and target ladder mount points are at workshop
  • Adjustable feet to be produced for radial alignment: Toby, almost done
  • degrading of 12C - on elog. 

3)Decisions / Analysis

  • Alpha analysis: dE and HI detectors seem ok, We need spare cables for Detector to preamplifier. 
  • Sort Routine — Ruchi +Alex+Tom
  • Target ladder config finalization: 2 photodiodes, collimator (what size, we have 3 mm and 10mm), Beam viewer, 3 CH2 and 2 Carbon.
  • Calibration of Target ladder positions. Peter / Daid
  • CH2 and C sample choice. So far CH2 Target 1: 30+25 (480ug/cm2); CH2 Target 2: 16 (400 ug/cm2). Check combination 33+1+10. New Ch2 from Paul - all will be sent here

4) CERN Presence:

  • Ruchi: 22 Oct - ~20 Nov
  • Mirco: 22-27 Oct, 5- ~20 Nov ?
  • Claudia: 22-27 Oct, 5- ~20 Nov
  • Daid: from 30 Oct
  • Peter: from ~1 Nov
  • Toby: from 30 Oct 
  • Alex 6-11 Nov
  • Tom 8- ?? Nov

Sarah: 8 - ?? Nov

    


    


     


    