<pre>
Header: 4.7 MeV/u and CH2_30+25.
Ender: STOP due to PSB fire.
====================================================
Run number : 74
Date : 09/11
Start time : 22:33
Stop time : 23:42
Trigger rate (MIDAS) :
Blocks written : 422
——————————————————————————————
Run Scalars (approx rates)
0- Ungated :
1- Gated :
2- dE :
3- E :
4- HI :
5- Pulser :
6- Clock :
——————————————————————————————
Beam energy : 4.7 MeV/u
Beam intensity : 1.5pA
Target : #6 CH2_33+35
Ladder position : 67.26
HI Degrader foil (um) : 15 um Al
——————————————————————————————
del_E voltage (V) : 32
del_E leakage (uA) : 0.75
E voltage (V) : 350
E leakage (uA) : 1.73
E_hi voltage (V) : 14
E_hi leakage (uA) : 0.85
——————————————————————————————
PA power (upstream, positive) : 1.55A
PA power (upstream, negative) : 0.55A
PA power (downstream, positive) : 0.8A
PA power (downstream, negative) : 0.28A
——————————————————————————————
Pressure (IMG1) : 7.0E-06
Pressure (old gauge) : 2.0E-05
Pressure (SEC) : 3.9E-06
——————————————————————————————
Temp (Chiller) : -10
Temp (chamber) : 5.4
——————————————————————————————
Comments:
ISOLDE: (PSB is 1 ring down - CCC operator to return 1st ring when fixed)
Fluctuations in intensity throughout run, as operator attempts to restart.
Final decision made to run with 3 rings and more runs per supercycle at 23:10.
====================================================</pre> |