Disconnected cables from CARME motors and turbo. The turbo has to go to allow Carme to slide out. Crane may be required to lift because it's in a very hard spot to access.
Dolly mostly built. See attached. Left side doesn't quite fit right by 1-2 mm. Might be okay anyway but will put some shims to avoid any shaking during sliding.
Waiting for the rails to arrive due to GSI procurement issues.
Plan to mount new feet and bellow support tomorrow.
Also plan to split CARME at the smaller flange towards the interaction chamber, after the bellows and before the bellows towards the magnet on the downstream side. |