Entry  Fri Jun 6 16:49:59 2025, CB, AY, ST, Beam overlap results for 200keV and 250keV 2025_06_06_17_46_56_Greenshot.png
For 200keV the optimal horizontal position is -5mm.
For 250keV the optimal horizontal position is -2mm.

Both values are already given to the operators, so tomorrow we can just switch to 200keV and go on :)
Entry  Thu Jun 5 16:54:18 2025, EW, ST, CB, Run 52 - 0.3 MeV/A 14x
Run 52 started at 17:53. Everything is running again. We started at 3E12 at/cm2

D+ beam deuterium target. D+ beam energy is now 0.3 MeV/u. (beam calc calculation is 0.3067 MeV/u).

All four detectors positioned fully out and stationary and also detector #4 is running again.
Entry  Thu Jun 5 08:50:00 2025, JM, CF, CB, EW, Run 51 - background Screenshot_from_2025-06-05_09-38-05.pngScreenshot_from_2025-06-05_09-46-08.pngScreenshot_from_2025-06-05_09-51-43.png
09:49

DSSD4 has been biased to 100V in steps of 5V from 60V. It was previously stable overnight at 60V - attachment 1

Will keep an eye on it but looks OK at the moment. Current bias and leakage current - attachment 2
Entry  Wed Jun 4 10:44:36 2025, EW, CB, JM, OF, JG, ST, Run 50 - 0.35 MeV/A 13x
11:30

Run 50 started.

D+ beam deuterium target. D+ beam energy is 0.35 MeV/u. (beam calc calculation is 0.3577 MeV/u)
Entry  Wed Jun 4 00:10:39 2025, JM, Run 49 - beam only 6x
01:10

Gas target turned off via the shutter valve.

Run 49 started beam only background run.
Entry  Tue Jun 3 14:54:29 2025, PMH, ST, Run 48 6x
Run 48 started. Everything is running again. We started at 3E13 at/cm2

D+ beam deuterium target. D+ beam energy is still 0.5 MeV/u. (beam calc calculation is 0.5143 MeV/u). See previous entry for beamcalc.

All four detectors positioned fully out and stationary, however we switched off detector #4.
Entry  Tue Jun 3 11:16:07 2025, EW, EM, JM, Run 47, beam only background Screenshot_from_2025-06-03_12-20-25.pngScreenshot_from_2025-06-03_12-19-36.png
Run 47 started. Target cooling down after water cooler failure, beam only background

D+ beam deuterium target. D+ beam energy is 0.5 MeV/u. (beam calc calculation is 0.5143 MeV/u). See previous entry for beamcalc.

All four detectors positioned fully out and stationary.
Entry  Mon Jun 2 20:03:43 2025, JG, AG, CB, EW, EM, Run 45/46, 0.5 MeV/A 13x
Run 45 started.

D+ beam deuterium target. D+ beam energy is 0.5 MeV/u. (beam calc calculation is 0.5143 MeV/u). See attachment for beamCalc

Target density is about 2e12 at/cm2
Entry  Mon Jun 2 17:48:07 2025, JG, AG, Run 44 scraper tests Screenshot_from_2025-06-02_18-51-24.pngScreenshot_from_2025-06-02_19-27-31.png
Same settings are Run 43 but with coasting beam and scrapers set to:  30 / - 30 mm.

 

all checks ok, but WR timestamp error, see attached
Entry  Mon Jun 2 17:25:31 2025, JG, AG, Run 43 scraper tests 
Same settings are Run 42 but bunched beam and scrapers set to:  30 / - 30 mm.

 
Entry  Mon Jun 2 16:35:35 2025, EW, AG, Run 42 and scraper tests Screenshot_from_2025-06-02_17-44-07.pngScreenshot_from_2025-06-02_17-44-50.png
17:00

Scraper tests conducted. We tried moving in the scrapers both at a fixed position throughout and also moving with the injection cycle.

We were unable to find a good position with the scrapers that did not produce significant scattering in the detectors.
Entry  Mon Jun 2 09:30:38 2025, JM, EW, ST, Run 41 6x
Run 41 started.

D+ beam deuterium target. D+ beam energy is 0.75 MeV/u. (beam calc calculation is 0.7619 MeV/u). See previous entry for beamcalc.

Beam calc - Attachment 1
Entry  Sun Jun 1 15:33:50 2025, EW, JM, CB, Run 40 10x
16:30

Run 40 started.

D+ beam deuterium target. D+ beam energy is 0.75 MeV/u. (beam calc calculation is 0.7619 MeV/u)
Entry  Sun Jun 1 07:46:34 2025, JM, EM, CB, Run 39 7x
08:45

Run 39 started.

D+ beam deuterium target. D+ beam energy is 1.0 MeV/u. (beam calc calculation is 1.0151 MeV/u)
Entry  Sat May 31 10:46:42 2025, TD, Run 38 - remote monitoring 21x

11.40 DAQ continues
      File G22-205/R38
Entry  Sat May 31 09:58:21 2025, JM, Run 38 10x
10:56

Run 38 started.

D+ beam deuterium target. D+ beam energy is 1.5 MeV/u. (beam calc calculation is 1.5160 MeV/u)
Entry  Fri May 30 21:49:08 2025, JM, NP, CB, Run 37 Screenshot_from_2025-05-31_00-56-32.pngScreenshot_from_2025-05-31_00-58-40.pngScreenshot_from_2025-05-31_06-16-50.png
22:49

Run 37 started.

D+ beam deuterium target. D+ beam energy is 2 MeV/u. (beam calc calculation is 1.9211 MeV/u)
Entry  Fri May 30 20:47:47 2025, JM, CB, NP, Run 36 Screenshot_from_2025-05-30_22-45-48.pngScreenshot_from_2025-05-30_22-46-48.png
21:47

Run 36 started.

D+ beam deuterium target. D+ beam energy is 2 MeV/u.
Entry  Fri May 30 20:06:48 2025, JM, CB, NP, Run35 8x
21:00

Run 35 started.

D+ beam deuterium target. D+ beam energy is 2 MeV/u. (beam calc calculation is 1.9211 MeV/u -> may be wrong cooler voltage, need to check
Entry  Fri May 30 07:27:41 2025, CB LB JM NP EM, Waiting for deuterium 8x
08:27

No run going.

Temperatures OK - attach
ELOG V3.1.4-unknown