AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  DTAS, Page 1 of 8  ELOG logo
  ID Date Author Subjectdown
  12   Thu May 16 02:57:15 2019 Nacher, Algorathreshold dynode #13 increased
Threshold of dynode #13 changed from 500 to 700 because of a very high noise.
New configuration file: 20190516_Conf.xlsx (attached).
Attachment 1: 20190516_Conf.xlsx
  100   Fri Jun 7 02:50:40 2019 SN, AAtest of 24Na

Start: 10:49

Stopt: 11:04

Lmd: 201906071049_24Na_AIDA_242.dlt

Root: 201906071117_24Na_AIDA_in.root

Comment: After irradiation of approximately 7 days, we extracted one Alu plate. It shows 24Na activity and also probably some beta+ activity.

The sample was not irradiated in the last 10 hours or so. It is positioned roughly in the center of the detector side in front of AIDA, using the frame prepared in Valencia.

It is not in the geometrical centre of the DTAS

Rates: 4.5 kHz (Dynodes), 4.5 (Anodes)  (Background level was at approximately 1.6-1.7 in both Dynodes, Anodes)

We need to check the alignment properly with Cs, but it looks that after one week some of the detectors have moved.

Group 1,3,5,7  (all seem to move with respect to detector 1)

Group 2,4,6,8 (detector 6 moved)

Group 11,13,15,17 (11 and 1 seem aligned, detector 13 moved)

Group 12, 14,16, 18 (12 and 2 not aligned, they seem aligned)

 

Attachment 1: 201906071117_24Na_AIDA_in.root
Attachment 2: Screenshot_from_2019-06-07_11-22-06.png
Screenshot_from_2019-06-07_11-22-06.png
Attachment 3: Screenshot_from_2019-06-07_11-24-39.png
Screenshot_from_2019-06-07_11-24-39.png
Attachment 4: Screenshot_from_2019-06-07_11-27-49.png
Screenshot_from_2019-06-07_11-27-49.png
Attachment 5: Screenshot_from_2019-06-07_11-30-17.png
Screenshot_from_2019-06-07_11-30-17.png
Attachment 6: Screenshot_from_2019-06-07_11-35-31.png
Screenshot_from_2019-06-07_11-35-31.png
Attachment 7: Screenshot_from_2019-06-07_11-36-43.png
Screenshot_from_2019-06-07_11-36-43.png
  105   Sat Jun 8 04:38:30 2019 Nacher, Algora, Tain, Molinasource top and bottom

137Cs top and bottom test... to check differences we positiones the source at the top and bottom of AIDA respectively.

Furthermore, we have changed the LED rate. Source reference: Cs401 - 4763

Root files:

201906081252_137Cs_AIDA_in_top.root  (pulser 100 Hz) (Attachment 2)

201906081228_137Cs_AIDA_in_bottom.root (pulser 10 Hz) (Attachment 3)

For each detector (An & Dy), the peak is plotted when the source is at top & bottom (Attachment 1).

 

 

Attachment 1: testOfPositioning.tar
Attachment 2: 201906081252_137Cs_AIDA_in_top.root
Attachment 3: 201906081228_137Cs_AIDA_in_bottom.root
  106   Sun Jun 9 03:59:40 2019 Manysome cable changes

The cable of detector 8 was changed (long cable) to reduce the noise. The cable (long) of the reference detector was also changed.

  120   Sat Jun 15 18:15:08 2019 Pancho& Kikerun 9
Shifters: Pancho & Kike

Degrader: none
Comments :
Last configuration file: 190615_1935_Conf_DTAS.xlsx
########################################################

Date: 2019-06-16
Start: 00:35
DTAS run: 009
AIDA run: _26
BigRIPS run: 2006

Listmode DLT: 190616_0035_100Sn_009.dlt


########################################################
----> TODO LIST during shift (check it!)<----
CHECK HISTOGRAMS/ Time: xxxx
LSUMA (hist. 3), LSUMD (hist. 4), LCryA (hist. 7), LCryD (hist. 8) - OK
F11PLR (and *L) (hist. 65 and 66) - OK
AIDAPL (hist. 69) - OK
ERefAn (hist. 70) - OK
Group Dynodes, Anodes, Ancilliaries - OK
*****************

DTAS Rate-dynodes: 3.8kHz
DTAS Rate-anodes: 3.3kHz
F11 Rate (hist. 27 or 28): 180 cps
AIDA Veto Plastic Rate (hist. 26): 13 cps

Beam current: 6965 enA (134 pnA, = enA/Zet(Xe), Zet(Xe)=52)

************************************************************************************

************************************************************************************



########################################################

Date: June-16th
Stop:
DTAS run:
AIDA run:
BigRIPS run:

Online ROOT file:

########################################################

Note:

Images:

Image entitled EDy01 corresponds to Energy of Crystal Dynod 01 (black) and 11 (red)
Image entitled EDy02 corresponds to Energy of Crystal Dynod 02 (black) and 12 (red)
Image entitled EDy03 corresponds to Energy of Crystal Dynod 03 (black) and 13 (red) .. and so on

Image entitled ECryA corresponnd to the sum of anode signal of all crystals (black) and the TAS sum (red)
Attachment 1: Screenshot_from_2019-06-16_01-50-05.png
Screenshot_from_2019-06-16_01-50-05.png
Attachment 2: Screenshot_from_2019-06-16_01-50-40.png
Screenshot_from_2019-06-16_01-50-40.png
Attachment 3: Screenshot_from_2019-06-16_01-51-11.png
Screenshot_from_2019-06-16_01-51-11.png
Attachment 4: Screenshot_from_2019-06-16_01-51-35.png
Screenshot_from_2019-06-16_01-51-35.png
Attachment 5: Screenshot_from_2019-06-16_01-52-10.png
Screenshot_from_2019-06-16_01-52-10.png
Attachment 6: Screenshot_from_2019-06-16_01-52-37.png
Screenshot_from_2019-06-16_01-52-37.png
Attachment 7: Screenshot_from_2019-06-16_01-53-01.png
Screenshot_from_2019-06-16_01-53-01.png
Attachment 8: Screenshot_from_2019-06-16_01-53-35.png
Screenshot_from_2019-06-16_01-53-35.png
Attachment 9: Screenshot_from_2019-06-16_01-47-11.png
Screenshot_from_2019-06-16_01-47-11.png
  121   Sat Jun 15 18:38:15 2019 Pancho & Kikerun 12
Shifters: Pancho & Kike

Degrader: none
Comments :
Last configuration file: 190615_1935_Conf_DTAS.xlsx
########################################################

Date: 2019-06-16
Start: 02:33
DTAS run: 012
AIDA run: 43
BigRIPS run: 2007

Listmode DLT: 190616_0233_100Sn_012.dlt



########################################################
----> TODO LIST during shift (check it!)<----
CHECK HISTOGRAMS/ Time: xxxx
LSUMA (hist. 3), LSUMD (hist. 4), LCryA (hist. 7), LCryD (hist. 8) - OK
F11PLR (and *L) (hist. 65 and 66) - OK
AIDAPL (hist. 69) - OK
ERefAn (hist. 70) - OK
Group Dynodes, Anodes, Ancilliaries - OK
*****************

DTAS Rate-dynodes: 4.0kHz
DTAS Rate-anodes: 3.3kHz
F11 Rate (hist. 27 or 28): 180 cps
AIDA Veto Plastic Rate (hist. 26): 12 cps

Beam current: 6886 enA (132 pnA, = enA/Zet(Xe), Zet(Xe)=52)

************************************************************************************

************************************************************************************



########################################################

Date: June-16th
Stop:
DTAS run:
AIDA run:
BigRIPS run:

Online ROOT file:
########################################################

Note:
  133   Sun Jun 16 19:18:15 2019 Ela, Victorroot files from run 30 to run 45
Attachment 1: 190617_0124_100Sn_045.root
Attachment 2: 190616_2316_100Sn_042.root
Attachment 3: 190616_2241_100Sn_041.root
Attachment 4: 190616_2041_100Sn_038.root
Attachment 5: 190616_1840_100Sn_035.root
Attachment 6: 190616_1641_100Sn_032.root
  122   Sat Jun 15 18:39:07 2019 Pancho & Kikeroot files
100Sn root files corresponding to runs 06,07,08 (190616_0030_100Sn_008.root) and runs 09,10,11 (190616_0230_100Sn_011.root) two hours each
Attachment 1: 190616_0030_100Sn_008.root
Attachment 2: 190616_0230_100Sn_011.root
  8   Wed May 15 09:57:54 2019 Nacherroot file with 60Co and 137Cs

For JL to play...

Attachment 1: 201905151432_137Cs60Co.root
  124   Sat Jun 15 22:43:20 2019 Pancho & Kikeroot file data 4:30 - 6:30
corresponding to runs .dlt 15-17


Images:

EAn01: All anodes energies overlay. EAn12 shows a bump between 50-100 keV and a peak between 100-120 keV


LAn01: all anodes lights overlayed. In LAn06 a peak is seen between 20-30 au (keV?); for LAn12 two bumps are seen between 80-120 au (keV?) and between 130-150 au (keV?)
Attachment 1: 190616_0630_100Sn_017.root
Attachment 2: Screenshot_from_2019-06-16_06-41-32.png
Screenshot_from_2019-06-16_06-41-32.png
Attachment 3: Screenshot_from_2019-06-16_06-42-55.png
Screenshot_from_2019-06-16_06-42-55.png
  123   Sat Jun 15 20:43:50 2019 Pancho & Kikeroot file data 2:30 - 4:30
corresponding to runs .dlt 12-14
Attachment 1: 190616_0430_100Sn_014.root
  128   Sun Jun 16 03:42:17 2019 Ela, Sonja, Victorroot file 8:30-10:30
Attachment 1: 190616_1032_100Sn_023.root
  125   Sun Jun 16 00:52:27 2019 Ela, Sonja, Victorroot file 6:30-8:30
Attachment 1: 190616_0833_100Sn_020.root
  139   Sun Jun 16 23:37:47 2019 Ela, Victorroot file 5:30-7:30
Attachment 1: 190617_0730_100Sn_054.root
  135   Sun Jun 16 21:44:38 2019 Ela, Victorroot file 3:30-5:30
Attachment 1: 190617_0528_100Sn_051.root
  138   Sun Jun 16 23:37:18 2019 Ela, Victorroot file 3:30-5:30
Attachment 1: 190617_0528_100Sn_051.root
  134   Sun Jun 16 21:43:36 2019 Ela, Victorroot file 1:30-3:30
Attachment 1: 190617_0325_100Sn_048.root
  130   Sun Jun 16 06:55:31 2019 Ela, Sonja, Victorroot file 12:30-14:30
Attachment 1: 190616_1435_100Sn_029.root
  129   Sun Jun 16 04:44:05 2019 Ela, Sonja, Victorroot file 10:30-12:30
The beam stopped a couple of times due to problems before RRC
Attachment 1: 190616_1233_100Sn_026.root
Attachment 2: Runs_24-26_breaks.png
Runs_24-26_breaks.png
  137   Sun Jun 16 22:56:41 2019 Victorrates modules in coincidence with F11
Module	Rate cps	Rate coin. F11 cps	Difference cps
1	36.8868		13.4045			23.4824
2	11.9046		1.16338			10.7412
3	35.5992		12.8111			22.7881
4	12.114		1.2723			10.8417
5	37.6139		13.2296			24.3843
6	12.793		1.33943			11.4536
7	37.7954		13.4383			24.3571
8	12.4813		1.3365			11.1448
11	29.6067		7.84707			21.7597
12	12.0162		0.859941		11.1563
13	28.9357		7.5685			21.3672
14	11.4407		0.825287		10.6154
15	29.7828		7.77872			22.0041
16	11.4512		0.847232		10.604
17	29.7826		8.0374			21.7452
18	11.3122		0.850505		10.4617
ELOG V3.1.4-unknown