Message ID: 421
Entry time: Fri Nov 4 04:35:03 2016
|
Author: |
TD, CG, DK |
Subject: |
Friday 4 November part 2 |
|
|
13.35 Swapped HDMI cables from master MACB to MACB #3 & #7
for HDMI cables from MACB #7 ports 1 & 2 to MACB modules #8 & #9
ReSYNC and stsrem wide test failures - see attachments 1-5
15.00 Swap HDMI cable from MACB #2 port 1 to MACB #3 next
ReSYNC and system wide test fails - see attachments 6-10
*Conclusion* all of HDMI cables between HDMI cable from nnaida6 and master MACB
have now been swapped for other HDMI cables between MACB # 7 and MACB # 8, 9, 10
but we still observe ReSYNC and clock issues
16.05 CG points out that I have misinterpreted Elog 258 - switch back MAC
mode settings to the following
MACB # 1 2 3 4 5 6 7 8 9 10 11 spare 1 spare 2
Mode 5 2 2 3 3 3 3 3 3 3 3
Rev B y y 50MHz? y
FEE64 power cycle
ReSYNC and system wide fails - see attachments 11-16
16,50 Re-considering options
Install MACB #11 (rev B) mode 0
Will attempt to use 25MHz correlation scaler clock NIM output from master MACB to BRIKEN+RIBFDAQ
Power cycle FEE64s
ReSYNC OK
System wide checks OK but some issues remain - see attachments 17-25
17.10 DAQ starts
Writing to disk file R115, merge rate 0.9M data items/, TapeServer ~7Mb/s
17.20 Analysis of R115_1 confirms ADC data synchronised - see attachment 26
17.25 MERGE stats look OK - see attachments 27-29
17.35 System wide tests SYNC errors & SYNC pulses OK
17.38 DAQ stalled - manual start of ORNL clover LN2 fill cycle by Nishimura-san
Most recent file R115_5 last accessed 17.38
DAQ stop OK
Disable histogram and data transfer #1
DAQ RESET
DAQ SETUP
Restart merger and TapeServer
Enable histogram and data transfer #1
17.47 DAQ start (R116)
17.58 DAQ stopped again at end of fill cycle.
1. Disable histogram and data transfer #1
2. DAQ RESET
3. DAQ SETUP
4. Restart merger and TapeServer
5. Enable histogram and data transfer #1
Had to repeat 1-5 multiple times to get all links working with the merger. R117 created during this (empty).
18.08 Run R118 started.
18.45 TD changing things for runs R119-R120.
18.50 Run R121 started.
First few minutes are pulser run 30-10,000 @ 250Hz on coarse dial.
18.54 Beam ON.
Continuing R121. Pb shield immediately after final MUSIC detector.
21.35 DAQ continues OK
Most recent file R121_30
All system-wide tests OK *but* note nnaida5 now fails clock status test in addition to combinations of
nnaida7/8/15/16
Merge/Tapeserver desktop, Merge statistics
- see attachments 30-36
21.45 R121_32 ADC data synchronised
Overnight
Phong Vi completed the pulser walkthrough interrupted earlier this evening.
BNC PB-4 amplitude settings 30,000 - 20,000 @ 10,000 step, 8,000-2,000 @ 2,000 step
The data is in files R121_62, _63 and _64 (which have been copied to d05 for further analysis). |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|