Tuesday 15 September

08:40
Rates started working again. Unclear what yesterday evening's bug was caused by. Will investigate eventually.
Temperature setpoint reach T=150 , however even at full power (heating constantly on) the RE72 appear unable to
reach past T = 135
See attached.

Perhaps better insulation would be required. 
However, this temperature is sufficient to bake CARME with the detectors inserted.


Day shift
Baking continues and will be left overnight to gather more data. Vessel temperatures are increasing by roughly 1.5 deg/hour with the vessel average temperature now 141.5 
deg.

Wire seals fully closed and tightened. Bolts were tightened first finger tight, then to 50 N.m and finally to 80 N.m in a pattern so that seal is closed evenly. Leak and 
pump cart are ready to be connected to the turbo for leak testing tomorrow. 


19:20
Baking continues OK. Temperatures seem to increase slowly. See attached.
Attachment 1: 20200915_0842_ctrl.png  60 kB  Uploaded Tue Sep 15 09:44:21 2020  | Hide | Hide all
20200915_0842_ctrl.png
Attachment 2: 20200915_0842_temp.png  156 kB  Uploaded Tue Sep 15 09:44:24 2020  | Hide | Hide all
20200915_0842_temp.png
Attachment 3: 20200915_152708.jpg  396 kB  Uploaded Tue Sep 15 16:54:13 2020  | Hide | Hide all
20200915_152708.jpg
Attachment 4: image007.jpg  40 kB  Uploaded Tue Sep 15 16:54:52 2020  | Hide | Hide all
image007.jpg
Attachment 5: 20200915_1920_temps.png  152 kB  Uploaded Tue Sep 15 20:24:53 2020  | Hide | Hide all
20200915_1920_temps.png
ELOG V3.1.4-unknown