Message ID: 468     Entry time: Mon Jan 15 18:51:28 2024
Author: JG, DR, TD 
Subject: Monday 15 January 
Cooling water manifolds


The manifolds were returned this afternoon.

Inflow manifold - blue hose, female Swagelok connectors

Attached to inflow hose and bled using bleed/drain valve.
Small leak observed at the 3/8" connection between the manifold and the bleed/drain valve - attachment tightened and leak fixed.
Inflow manifold installed.

Outflow manifold - red hose, male Swagelok connectors

Attached to outflow hose and bled using bleed/drain valve.
Small leak observed at the weld immediately *below* the weld that had been re-worked - this weld had not been re-worked.
Significant leak observed at one of the male Swagelok connectors in the lower half of the manifold - it does not seal correctly.


DR will return this manifold to the workshop for welding re-work Tuesday am.
The faulty male Swagelok will be replaced.


AIDA cabling


16x AIDA PSU, HDMI and RJ45 Cat 6 cables and 4x SHV-BNC cables required.

Available

8x AIDA PSU cables 
1x AIDA PSU cable ( in one of two white plastic storage boxs with 7x FEE64s returned from STFC DL ) now appears to be missing

16x AIDA HDMI cables 

8x RJ45 Cat 6 network cables
1x RJ45 Cat 6 network cable ( network switch to CRYRING network patch panel - to be replaced )
3x RJ45 Cat 6 network cables found in AIDA plastic box ( S4 Messehutte )

3x SHV-BNC 

Will check DESPEC store above ESR with NH tomorrow afternoon.