CARME |
 |
|
Message ID: 51
Entry time: Wed Sep 1 17:14:16 2021
|
Author: |
CB RSS + DR ML |
Subject: |
CARME mounted on the CRYRING |
|
|
Lifted CARME with Al support on the
CRYRING. No issues during transportation.
Drilled new holes in the Al feet to fit
elephant feet. Unclear if the issue is
with the model, the frame or the feet
themselves. In any case this issue is
sorted.
CARME was designed to interface with the
CRYRING via the cross section with pumps
and sensors that we decided dismount. To
replace this section a length of xhv
tubing and a bellow will be employed.
Prepared today, to be mounted tomorrow.
Aligned CARME height with beam height.
This posed issues due to difficulty to
adjust bolts under the cross members used
to support the motors. See previous log
entry.
Bolts under those cross members are now
only finger tight. Unclear whether the
CARME section will drop slightly if
disconnected from main body. It's the
section housing the moving Dssds. May be
an issue for tightening it back. Will
investigate.
Gate valves and supports to be installed
tomorrow morning. |
|
|
|
|
|
|
|
|
|
|