Chamber has been vented back to atmosphere.
Motor was able to be pulled back to insert bloacking pin once at atmosphere.
Thermocouple feedthrough constructed with 4 thermocuples attached. Internal thermocouples each ~200mm in length with external thermocouples each ~1m in length. All were tested by plugging into TC08 and using baking code. Feedthrough will be installed under the motors flange tomorrow.
Survey team come tomorrow morning, afterwhich ion pump and RGA will also be installed. |