AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  CARME, Page 21 of 34  ELOG logo
  ID Date Author Subject Text Attachments
  270   Thu Feb 24 14:31:25 2022 JM, ML, CNBeam Tuning Run 7615:30

1.5 MeV/u beam currently being
tuned
 6x 
  269   Thu Feb 24 09:43:16 2022 JG, MScheckBeam is still beeing tuned. Target is off.

 

- Motor on manual
 13x 
  268   Thu Feb 24 08:30:36 2022 JG, MSAIDA5 calibration test failed - solvedUPDATE: THE PROBLEM IS SOLVED FOR NOW:

Doing the calib for the 5th time
eventually worked.
 Screenshot_from_2022-02-24_09-09-36.pngScreenshot_from_2022-02-24_09-29-24.png 
  267   Thu Feb 24 08:15:23 2022 JG, MScheckBeam is still beeing tuned. Target is off.

There is a problem with ADC calibration
of aida5: see entry https://elog.ph.ed.ac.uk/CARME/268
 13x 
  266   Thu Feb 24 07:25:53 2022 OH (Remote)Recover of system after crash08:00 Woke up to message from Carlo explaining
the server had crashed.
      Anydesked into the machine.
  
  265   Thu Feb 24 05:09:47 2022 CB, PE, EMInlet valve at target closed + problems with turbopumpThe turbo pump E1 is continuing to draw
too much current and the rotation frequency
has steadily decreased from 817 Hz at the
  
  264   Thu Feb 24 04:17:35 2022 CB, TD (remotely)MIDAS DAQ no longer workingDAQ server crashed around 24:00

Rebooted server but could not could
not rescue remotely - could not contact raspberry
 Bad_Time_2022-02-24_04-34-12.pngBadTime_WRTime_2022-02-24_04-34-53.png 
  263   Wed Feb 23 22:29:50 2022 PE, EM, CB (remotely)check - 23:30Motor position ok

Data rate: 1030kbytes/s

T ok
  
  262   Wed Feb 23 21:27:29 2022 TD, CNcheck Motor position ok

Data rate: 1030kbytes/s

T ok
 11x 
  261   Wed Feb 23 20:52:56 2022 CN, TDSystem wide checks
Attachments 1-5 aida01-aida05 options
 11x 
  260   Wed Feb 23 20:06:43 2022 TD CNE141 kinematics
Assuming DSSSD is 1000um thick we can expect
to observe protons for E_lab=11MeV as follows
 E141_kinematics.txt 
  259   Wed Feb 23 19:22:55 2022 CN, TDcheck 

- Motor checked , OK

SW3
 10x 
  258   Wed Feb 23 18:58:12 2022 TD CNWednesday 23 February 15.00-23.00 shift

Assorted screenshots of the CARME, CRYRING
 6x 
  257   Wed Feb 23 16:57:35 2022 CB, CNOptimising motor motionOptimised motor motion during run R58

Moved 2 mm in (20.3 potentiometer)

29.47 potentiometer
  
  256   Wed Feb 23 10:56:06 2022 Laszlo, ThanassisCurrent status11:55
Temps OK
System Check OK
 10x 
  255   Wed Feb 23 09:50:19 2022 Laszlo, ThanassisMoving detector inWe are moving the detector in run 56   
  254   Wed Feb 23 08:58:30 2022 Laszlo, ThanassisCurrent status10:00
Temps OK
System Check OK
 10x 
  253   Wed Feb 23 07:58:38 2022 Laszlo, ThanassisCurrent status09:00
Temps OK
System Check OK
 10x 
  252   Wed Feb 23 06:58:19 2022 Laszlo, ThanassisCurrent status08:00
Temps OK
System Check OK
 11x 
  251   Wed Feb 23 06:00:25 2022 Jordan, GeorgeCurrent status07:00
Pressure Stable
Temps OK
 2022-02-23_07-06-36exRate.png2022-02-23_07-06-11exTotal.png2022-02-23_07-05-42xyTotal.png 
ELOG V3.1.4-unknown