AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  CARME, Page 11 of 38  ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry  Thu May 30 07:25:53 2024, Yuri, Phil, Nikos, Gas target 
The cave is closed and beam is back

The d intensity is about half of the intensity before the break

The gas target is prepared but the valvas cannot be opened. Anton is coming in at around 1 PM to open the gate valves.
Entry  Thu May 30 06:00:51 2024, Yuri Nikos ..., Open the cave 
Nikos needs to enter the cave to work on the target cooling.

 
Entry  Wed May 29 17:42:06 2024, TD, Offline analysis APR24/R2 (pulser walkthrough) 17x
ADC offsets using pulser walkthrough data from data file APR24/R2

ch = channel + ( module * 64 ) + ( range * 2048 )
Entry  Wed May 29 16:46:21 2024, NP, AB, PM, Run7 - Measurements only with ion beam. Screenshot_from_2024-05-29_21-49-57.pngScreenshot_from_2024-05-29_21-50-14.png
18:19 Start or run 7: In beam has been optimzed up to now by Zoran and Claude. ~7E7 particles at injection. From now on, only the injection beamline
is optimized by Operators.

Detectors IN (left arm pot =18.86 mm, right arm pot = 19.80 mm)
Entry  Wed May 29 09:49:35 2024, JM, CB, Threshold changes / D+ beam Screenshot_from_2024-05-29_11-00-20.pngScreenshot_from_2024-05-29_11-01-30.pngScreenshot_from_2024-05-29_11-01-47.pngScreenshot_from_2024-05-29_11-02-03.png
09:00

R4 alpha background continues, currently R4_12

Temps OK, system checks unchanged from previous status (OK, aida16 clock and ADC issue)
Entry  Wed May 29 08:10:32 2024, JM, Run4 - alpha background 
09:00

R4 alpha background continues, currently R4_12

Temps OK, system checks unchanged from previous status (OK, aida16 clock and ADC issue)
Entry  Tue May 28 15:25:21 2024, TD, JM, CB, Pulser tests Screenshot_from_2024-05-28_16-14-56.pngScreenshot_from_2024-05-28_16-15-43.pngScreenshot_from_2024-05-28_16-16-18.pngScreenshot_from_2024-05-28_16-20-05.pngScreenshot_from_2024-05-28_16-28-46.png
R3 started

Pulser ON. Approx 2 kHZ.

1.8*w waveforms attachments 1+2
Entry  Tue May 28 12:38:31 2024, TD, JM, CB, Run 2 - Alpha background run Screenshot_from_2024-05-28_13-35-03.pngScreenshot_from_2024-05-28_13-34-30.pngScreenshot_from_2024-05-28_13-33-19.pngScreenshot_from_2024-05-28_13-36-30.pngScreenshot_from_2024-05-28_13-37-16.png

13.35 FEE64 temperatures OK - attachment 1
Entry  Mon May 27 15:25:08 2024, JM, Startup 
27/05/24

The carme-gsi computer has been moved from the server room into the shifter control room.

Startup of the DAQ looks OK. Settings loaded 2024Apr24
Entry  Fri May 10 21:23:35 2024, TD, CB, JM, 20Ne7+ test beam 18x
22.00

Carsten Brandau stopping e-target experiment Unattended beam overnight. No operators watching.

10^5 (nominal) 20Ne7+ at 380keV/u beam available
Entry  Sun Apr 28 23:12:11 2024, TD, Monday 28 April 21x
00.09 DAQ continues data file R3_21

      DSSSD bias & leakage current OK - attachment 1
Entry  Sat Apr 27 23:16:02 2024, TD, Sunday 28 April 37x

00.12 DAQ continues data file R3_15
Entry  Fri Apr 26 23:41:16 2024, TD, Saturday 27 April 37x

00.34 DAQ continues data file R3_9
Entry  Fri Apr 26 07:05:01 2024, TD, Friday 26 April 19x

08.02 DAQ continues data file R1_14
Entry  Thu Apr 25 02:31:25 2024, TD, Thursday 25 April 39x

03.27 DAQ continues - file APR24/R1_7
Entry  Wed Apr 24 13:18:09 2024, TD, Examples of poor CARME cable management/routing 20240424_125858.jpg20240424_125929.jpg

Have observed some instances of poor CARME cable management/routing
Attachment 1 - SAES D-2000 ion pump HV cable (netal braid) transiting FEE64 cabling
Entry  Wed Apr 24 12:48:35 2024, TD, Wednesday 24 April 21x

      Replace AIDA ASIC mezzanine of aida01
Entry  Tue Apr 23 17:44:41 2024, TD, Tuesday 23 April 12x

18.43 ASIC settings 2024Feb08-15.59.09
Entry  Fri Apr 19 02:47:59 2024, TD, Friday 19 April 12x

03.45
Entry  Thu Apr 18 13:34:06 2024, TD, JG, Thursday 18 April 13x

14.30 
ELOG V3.1.4-unknown