  CARME, Page 23 of 38  ELOG logo
ID Date Authordown Subject Text Attachments
  17   Mon Sep 21 09:51:57 2020 JMCARME StatusCooling of baking volume finished over
the weekend, attached are some plots of the
bakeout test. Bakeout2.png is the thermocouple
 Graphs.zip 
  18   Wed Sep 23 13:34:04 2020 JMTuesday 22 SeptemberTurbo-pump Issue approximately 13:00 22/9/20.

While moving the baking octagon
into position, the power connector became
  
  21   Fri Sep 25 12:58:33 2020 JMFriday 25/09/2010:00   Vessel P = 3.99e-8 mbar, 
RGA P = 1.4e-6 mbar 

10:54   Vessel P = 3.89e-8
 Photos.zip 
  23   Mon Sep 28 13:04:27 2020 JMBakingI have (fingers crossed) got the baking
stepping up nicely now. I have used some
of the outer shell to act as a shield and
 20200928_081831.jpg20200928_130239.jpg 
  26   Mon Oct 12 10:49:36 2020 JMFirst Bakeout of CARME with pumps (cont)12 October 

10:00 Bakeout temperatures stable.
Pressure on the backing line is 3e-7mbar
 temp6.png 
  27   Mon Oct 19 13:57:52 2020 JMNeg ActivationNeg and Neg-Ion pumps have been connected
up to the control modules. Controller on
the right is connected to the D-2000s. Middle
 Photos.zip20201019_154921.jpg 
  33   Tue Nov 10 12:25:29 2020 JMCable harnessesThe length of the wire needed was estimated
with the aid of a scale image of the detectors
in the CARME chamber and foam model pieces.
 20201102_155336.jpgFigure_1.png20201102_154648.jpgPhotos.zip 
  34   Tue Nov 24 12:24:01 2020 JMRGA scansRGA laptop passcode: tw%11&STA-
  

RGA scans set up and plotting data
 20201124_124107.jpg 
  37   Mon Dec 7 14:29:12 2020 JMCARME packing up   20201207_122353.jpg20201207_113905.jpg20201207_110714.jpg 
  131   Sat Oct 23 12:58:11 2021 JMGSI vacuum and bakeout testing summaryAttachment 1 shows the pump-down of the
CARME chamber at GSI before installation
of kapton cabling inside the chamber and
 GSI_fullpumpdown.pngGSI_pumping.pngBakeout-elog.pngfit-elog.pngActivation-elog.png 
  173   Sat Jan 15 11:28:10 2022 JMInventory 


Vaccum
DN250CF 1x gaskets
    
DN200CF 5x gaskets  
DN160CF 1x gaskets,
 20220115_162649.jpg20220115_162712.jpg 
  197   Tue Feb 15 21:28:14 2022 JMNoisy ChannelsAll fees and asics checked to find noisy
channels. Channels are listed along with
the noise peak height for the low energy
 2022-02-15_22-17-51-aida1-3*L.png2022-02-15_22-23-12-aida1-4-stat-log.png 
  201   Wed Feb 16 21:27:31 2022 JMCryring signals, Pulser tests, Waveforms On 15/2/22 it was noted that the leakage
current increases when the motors are moved
IN. This is contary to tests conducted on
 11x 
  202   Wed Feb 16 21:41:11 2022 JMRun 43 Alpha Background22:41

Check Leakage current: (see attachment
1) = 10.01 uA and falling
 8x 
  387   Mon Apr 24 21:24:26 2023 JMPreparation for CARME dismountCARME currently in vacuum, pressure ~3E-10
mbar. Chamber to be vented tomorrow afternoon
by vacuum division. We have active both pirani
 20230424_155635.jpg20230424_155607.jpg20230424_150526.jpg 
  388   Tue Apr 25 13:22:19 2023 JMCARME venting CARME venting using nitrogen gas bottle. 

Coolant pipes dismounted from the
chamber
 20230425_134119.jpg20230425_132944.jpg 
  413   Tue Jul 4 17:08:08 2023 JMLeak test and ventingThis morning the pressure achieved was
1.44E-7 mbar. Leak testing showed an overall
leak rate of 1.5E-10 mbar l/s, this is below
 20230704_135455.jpg20230704_174524.jpg 
  414   Wed Jul 5 19:27:13 2023 JMPump down and leak testCARME and the interaction chamber have
been pumping for ~26 hours, P=4.15e-7 mbar,
attached figures show the current pump down
 pumping_1.pngpumping-zoom.pngsignal-2023-07-05-15-13-30-512.jpg 
  415   Thu Jul 6 15:26:39 2023 JMLeak updateThe leak on the actuator arm bellows has
been attempted to be sealed using UHV vacuum
seal spray. The spray had the opposite to
 pumping.png 
  431   Thu Aug 10 07:51:43 2023 JMBaking tent and heater testing09/08/23

Attached is the current pumpdown
plot taken from grafana. 
 8x 