Entry  Mon Feb 7 08:09:50 2022, OH, CB and PH, CARME Server setup and initial tests 
09:09 Arrived at GSI for comissioning beamtime.
      CARME currently in a stopped state, with all FEEs powered off.
      Upper detector is biased with 80V and has a leakage current of 9.92uA.
Entry  Fri Sep 17 16:42:25 2021, JM RSS ML + OG, CARME Realignment + Thermocouple installation 8x
Laser surveying team worked till 11. Chamber was too high by 3mm close to the jet target and 6mm by the turbo pump (towards the dipole). 

CARME lowered appropriate amount using bolts under CARME feet. Height checked using a laser on the centre point line of the middle flange turbo
end and mid point on the front of the chamber (see images). During lowering front foot swapped and valve supports moved slightly to give more clearance
Entry  Fri Oct 22 13:22:48 2021, TD, CARME FEE64 adaptor PCB 10x
 
Entry  Mon Aug 17 08:16:16 2020, TD, CARME Elog 

Test
Entry  Sat Feb 19 14:51:58 2022, JM, CB, Burst high energy noise 2022-02-19_15-50-50-aida1-4-stat-logscale.png2022-02-19_15-47-13-aida1-2*H.png2022-02-19_15-49-48-aida2-1*H.png2022-02-20_14-01-40-aida1-2*H.png2022-02-20_14-02-55-aida1-1*H.png
Noticed bursts of high energy noise on aida01 and aida02 during run 47 and 48.

Good events rate jumps from 10-20k range to 250k. ADC data items rate jumps from 0-1 to 2k. Data rate being written increases to ~2500 kb/s from
~20 kb/s
Entry  Tue Nov 9 15:03:29 2021, RSS + OG, Burnt cables issues 7x
Upper part of the frame was mounted. In order to do so, the valve was closed, turbo wire and hose were disconnected and then connected. Valve was opened
again. See pictures 1-2.

Bottom part of the tent was constructed with 3 heaters (from one of the controllers) at the front, 4 in the middle, and 4 at the back (4+4 from
Entry  Sun Jul 23 10:13:48 2023, RSS, TD, Building tent DBE0DA2E-2F69-469C-B645-3E33E3D82138.jpeg857185AC-3571-41E9-88AE-9F624445135B.jpegE69ED1D1-444E-478A-A3B4-481023B4024D.jpeg610048A3-25F5-459C-9EF1-83EFEFDE51C9.jpeg
11.15 Pirani 1.0e-03mbar IE514 2.72e-08mbar

16.35 Pirani 1.0e-03mbar IE514 2.61e-08mbar
Entry  Tue Jul 25 09:12:15 2023, RSS, Building tent BD01C0C8-5181-49B8-8751-AD4C99A459CC.jpeg7B3836F1-8A7E-491B-AFDC-46033BF84760.jpeg

10:10  IE514 2.0e-08mbar

Upstream part of the CARME is covered.
Entry  Wed Jul 26 08:28:09 2023, RSS, Building tent IMG_9897.jpgIMG_9899.jpgIMG_9901.jpgIMG_9902.jpg

09:26  IE514 1.96e-08mbar
Entry  Mon Feb 5 19:43:52 2024, CB, TD, ML, BuTIS reference for VETAR2 20240205_173029.jpg20240205_172957.jpgScreenshot_from_2024-02-05_16-43-18.png

16.40 CB/ML install fibre optic cable from patch panel beneath dipole downstream of YR09/CARME chamber to VETAR2 front panel fibre connector - see attachments
1 & 2.
Entry  Sat Oct 16 17:25:47 2021, RSS TD, Broken detectors IMG_5098.JPGIMG_5097.JPGIMG_5096.JPGIMG_5106.JPGIMG_5105.JPG
One of the detectors was damaged while mounting (see pictures 1-3).

Second detector was found already damaged when opened (see pictures 4-5).
Entry  Thu Feb 3 22:05:33 2022, JM, TD, OH(remotely), Bias update and grounding 
9:30 Bias remained stable overnight - 60V 2.95 uA.

10:00 No grounding attached initailly. Pulser ON, lots of noise across all ~250-300 kHz across biased detector. Waveforms and histograms saved
to /tmp. Pulser width for aida 6 ~300 channels. Aida 7,8 similar, aida 5 producing no ADC data. 
Entry  Sat Jan 13 14:25:05 2024, CB, JM, Bias tests with all FEEs connected Screenshot_2024-01-13_15-24-40.png20240113_150158.jpg
Connected all FEEs.

The two top fees corresponding to the bottom right detector are connected to damaged flexi rigid PCBs. The top one is missing an pin that should
not be connected to anything, while the bottom one has a slightly cracked connector and is missing the top left pin. Spares should be in Edinburgh.
Entry  Thu Jul 13 00:12:19 2023, JM, CB, Bellow replaced 20230705_164523.jpg
The left (inside ring) bellow for the motors rod was replaced.

Replacing the bellow involved;


One person holding the metal plate the detectors are mounted on (cabling remains plugged in) while the operation is performed. 
The
Entry  Fri Jun 14 14:52:02 2024, JM, Beam-Target Overlap Scan 20240614_153532.jpgBeam-overlap-updated.png
The orbit of the beam in the ring was re-configured so that the beam position is more central.

With the target density at ~6e11 at/cm2 this allowed a target overlap scan using the beam lifetime to be performed. 

Beam put into bunched mode to allow the number of particles to be observed on Grafana.
Entry  Sun Jun 9 09:45:27 2024, JM, CB, Beam-Target Overlap Beam-overlap.png
Target density this morning had stabalised at 7e11 at/cm2

This is sufficient to test the beam/target overlap using the lifetime of the beam in the ring.

Previous attempt at this method was done at 1.5e11 at/cm2 where lifetime from residual gas and target are essentially the same.
Entry  Fri Jun 6 16:49:59 2025, CB, AY, ST, Beam overlap results for 200keV and 250keV 2025_06_06_17_46_56_Greenshot.png
For 200keV the optimal horizontal position is -5mm.
For 250keV the optimal horizontal position is -2mm.

Both values are already given to the operators, so tomorrow we can just switch to 200keV and go on :)
Entry  Sat Feb 17 13:21:44 2024, JM, CB, Beam on target - motors tests Screenshot_from_2024-02-17_14-33-51.pngScreenshot_from_2024-02-17_14-36-27.pngScreenshot_from_2024-02-17_14-39-38.png
14:01

Run 36 started.

We put both detectors to the fully out position. Detectors then driven IN using the pnuematic motor only once the beam is ready and driven fully
Entry  Thu Feb 24 14:31:25 2022, JM, ML, CN, Beam Tuning Run 76 6x
15:30

1.5 MeV/u beam currently being tuned

Target is ON, setpoint = 135 K
Entry  Tue Feb 22 04:09:28 2022, JM, CB, LV, PM, AK, Beam ON, Target ON Run 54 - first event at 10MeV ! 11x
05:00

Beam ON ~2E6 pps, still fluctates between 2e6 and 6e6 (like a step function)

Target ON and open to the ring