  529   Tue Dec 6 06:38:46 2016 TD, Updated PatrickCAEN N1419 HV output common mode noise
There appears to be significant common mode
noise on the output of the
 9x 
  528   Tue Dec 6 02:30:35 2016 TDReport - low - significant variation in FEE64 boot times
Not something we were not aware of already
but /var/log/messages illustrate the issue.
  
  527   Tue Dec 6 02:20:29 2016 TDTuesday 6 December11.20 DSSSD bias & leakage currents OK - see
attachments 1 & 2
      FEE64 temperatures OK - see attachment
 100.png101.png102.pngAIDA_leakage_current(13).xlsx 
  525   Mon Dec 5 11:53:26 2016 TDMACB test
MACB configuration can be found at https://elog.ph.ed.ac.uk/AIDA/357
 42x 
  524   Mon Dec 5 10:51:08 2016 TDMonday 5 December19.50 DSSSD bias & leakage currents OK - see
attachments 1 & 2
      FEE64 temperatures HIGH - see attachment
 1.png2.png3.png4.pngAIDA_leakage_current(12).xlsx 
  523   Sun Dec 4 05:46:42 2016 TDSyncCheck RIBF03R1 & RIBF123R1 commissioning tests archived
The SyncCheck etc software used for the RIBF123R1
and RIBF03R1 commissioning
  
  522   Sun Dec 4 04:05:24 2016 TDReport - low - DAQ SETUP sometimes produces Javascript error
DAQ SETUP sometimes produces Javascript error
instead of a pop-up displaying
 10.png 
  521   Sun Dec 4 03:44:12 2016 TDSunday 4 December12.45 DSSSD bias & leakage currents OK - see
attachments 1 & 2
      FEE64 temperatures OK - see attachment
 16x 
  520   Sat Dec 3 10:49:36 2016 TDSaturday 3 December19.48 DSSSD bias & leakage currents OK - see
attachments 1 & 2
      FEE64 temperatures OK - see attachment
 1.png2.png3.png 
  519   Fri Dec 2 09:58:54 2016 DKSimple PID with LISE++I wrote this LISE++ file based on the Takechi
.lpp modified by AE for 77Ni, 78Ni, 76Ni.
 lise-41Al.pngSettingFallonDK.lppPIDintensity.png 
  518   Fri Dec 2 09:47:58 2016 DKF8 targetsF8 target measurements, for posterity.

Plastic: ~39 to 40 mm
  
  517   Fri Dec 2 09:47:45 2016 DKF8 targetsF8 targets, for posterity.

Plastic: 39~40 mm
  
  516   Fri Dec 2 08:23:28 2016 TDOffline analysis of R48_9Analysis of background, pulser off

S O R T    C O M P L E T E ..... Fri Dec
 100.png101.png102.png103.png 
  515   Fri Dec 2 06:41:25 2016 DKBenchmarks for compressionR45_17 as the test file, which was closed
at 9.02 AM Friday, December 2nd at the end
of the official parasitic
  
  514   Thu Dec 1 16:01:10 2016 CG, PVFriday 2 December00.07 BigRIPS data file 1135

01.07 BigRIPS data file 1136.
 14x 
  513   Thu Dec 1 10:58:54 2016 PV, TD, LiuImplantation profile in AIDA , after switch back to the previous ZDS setting (AIDA 43_63 to 43_71, bigrips run 1129)   51.png45.png31.png 
  512   Thu Dec 1 09:46:06 2016 TDOffline analysis of R43_59     Variable degrader setting is now #2 +
#3: 0.3 mm W + 1.0 mm W [+2 mm Al]
     Centre ZDS @ 40Mg
 9x 
  511   Thu Dec 1 08:13:06 2016 PV,Liu, TDImplantation profile in AIDA , after changing the ZDS setting to center at 41Al, AIDA 43_ 33 to 43Bigrips run 1127

AIDA run 43_ 33 to 43
 36.png24.png50.png 
  510   Thu Dec 1 02:25:41 2016 DKOffline analysis of R42_32Offline analysis of AIDA R42_32.

Degrader condition of F11 is with the same
 6x 
  509   Thu Dec 1 00:21:08 2016 DKOffline analysis of R42_7Checking that the implantation is still
reasonable after LN2 fill recovery. 

Degrader condition is 8. + 0.2
 r42_2110.pngr42_307.pngr42_2120.pngr42-301.pngr42-2000.png 