Entry  Tue Sep 28 06:40:22 2021, RSS JM, CARME baking status -8 Screenshot_from_2021-09-28_07-38-53.pngScreenshot_from_2021-09-28_07-39-22.png

Current temperature ~120 C, increasing
See plot and screen attached.

Current pressure ~1.07E-6 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
http://web-docs.gsi.de/~lestinsk/vacplot.php
Entry  Mon Sep 27 21:33:50 2021, CB (remotely), CARME baking status -7 Temps.pngScreen.png
Current temperature ~87 C, increasing
See plot and screen attached.
Thermocouple on CARME foot side (1-4) may have come loose judging from sudden jump in temperature at 14:30?
Entry  Mon Sep 27 17:53:35 2021, JM RSS , Baking Jacket upgrade + NEG controllers connected 20210927_151650.jpg20210927_151706.jpg20210927_151721.jpg20210927_170139.jpg
Additional baking jacket sections for the turbo section arrived today. Baking was halted at ~11:00 to allow for the chamber to cool to install new sections.
New sections installed and baking restarted at 15:25. Jacket fits much better with gaps near the turbos and the motors now covered much better. Attached
are some photos. 
Entry  Mon Sep 27 11:09:48 2021, CB (remotely), Temperature vs Pressure plot Temps.pdf
Attached.
Entry  Mon Sep 27 06:42:45 2021, RSS JM, CARME baking status -6 Screenshot_from_2021-09-27_07-41-06.pngScreenshot_from_2021-09-27_07-41-39.png

Current temperature ~102 C. Was set in the manual mode since last evening 18:54.
See plot and screen attached.


Current pressure
3.62E-7 
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
http://web-docs.gsi.de/~lestinsk/vacplot.php
Entry  Sun Sep 26 17:20:13 2021, RSS JM CB (remotely), CARME baking status -5 Screenshot_from_2021-09-26_18-19-26.pngScreenshot_from_2021-09-26_18-18-23.png

Current temperature ~105 C
See plot and screen attached.


Current pressure 6.08E-7 
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
http://web-docs.gsi.de/~lestinsk/vacplot.php
Entry  Sun Sep 26 07:41:00 2021, CB (remotely), CARME baking status -4 Temps.pngScreen.png
Current temperature ~87C

See plot and screen attached.
Entry  Sat Sep 25 19:01:50 2021, CB (remotely), CARME baking status -3 Temps.PNG
Baking automatically stopped due to negative gradient in on thermocouple for 10 minutes straight. 
Not surprising giving we were baking at full power bu making little progress. We should have switched to manual
mode.
Entry  Sat Sep 25 07:23:06 2021, CB (remotely), CARME baking status -2 temp_plot.pngtemps.png
Current temperature ~90 C
However note setpoint is at 102 C. It appears we are baking at full power, but too many heat losses?
Temperature gradient still increasing. May just be a matter of time.
Entry  Fri Sep 24 15:36:34 2021, CB (remotely), CARME baking status Temp.pngTemps.png
Current temperature ~64 C

See plots attached
Entry  Fri Sep 24 09:44:58 2021, JM ML, Vacuum gauge readout 
The analog readout of the Combivac controller for the IE514 ion gauge has been set up, readings are plotted to http://web-docs.gsi.de/~lestinsk/vacplot.php.
Readings and plot should be updated every minute.
Entry  Fri Sep 24 08:47:36 2021, JM RSS CB(Remotely), Baking  
Baking halted on 23/9/21 16:16 as connection to TC08 module was lost. USB cable connection to TC08 module appears to have been damaged in shipment. USB
hub and cable replaced, connection re-established and baking restarted 17:27. 

Ramping of baking limited to 40C by the maximum difference between parts of the chamber being too high, this safety feature prevents high thermal
Entry  Fri Sep 24 07:04:57 2021, RSS JM, IE 514 pin arrangement and degas instructions IE514_pin_arrangement.JPGdegas_function.jpg
Fabre (German)       Color (English)

grau                        
grey
Entry  Thu Sep 23 14:19:27 2021, CB (remotely), Checking baking remotely - instructions Temp.png
1. Connect to pi on CRYRING local network 
ssh pi@192.168.207.127
Entry  Thu Sep 23 13:31:12 2021, JM RSS ML, IE514 Gauge and Bakeout 20210923_113239.jpg20210923_134339.jpg20210923_134355.jpg20210923_135954.jpg
CARME setup checked by vaccum group this morning. 

Both IE514 gauges de-gassed. To de-gas on the CM52 controller select the channel and hold the right arrow for two seconds. The reading will flash
indicating the de-gassing procedure, this lasts for 2 minutes before completing. Flashing automatically stops once procedure finishes. Attached for convinience
Entry  Wed Sep 22 14:44:51 2021, JM RSS ML, CARME leak test + bakeout tent 20210922_145646.jpg20210922_145933.jpg20210922_151728.jpg20210922_152052.jpg20210922_152113.jpg
On 21/9/21 CARME was connected to the leak tester. Leak testing showed no apparent leaks, extra time required to reach <1e-4 mbar during initial turbo
pumpdown might be due to outgassing from additional installed components on the chamber. Turbo pump restarted 

21/9/21 16:28    9.73e-7 mbar
Entry  Wed Sep 22 08:30:08 2021, CB (remotely), CARME pressure during first XHV test 
CARME pressure moved to

https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?e=hEoZt7
Entry  Mon Sep 20 11:45:45 2021, JM RSS ML, CARME installations 6x
Ion pump, RGA and additional gauge installed on the chamber.

Our gauge is the one mounted above the NEG feedthrough, Michael's gauge is mounted below the feedthrough. Ion pump too large to install on
the top of the vessel, sufficient room on flange immediately next to this top flange.  
    Reply  Tue Sep 21 08:20:39 2021, ML, CARME installations 
 




Quote:



Ion pump, RGA and additional gauge installed on the chamber.
Entry  Sun Sep 19 09:11:34 2021, CB (remotely), Baking RasPi status 
Accessed Pi remotely 

( 1. Without the Internet, the Pi has no way of knowing what time is it.
Entry  Fri Sep 17 16:42:25 2021, JM RSS ML + OG, CARME Realignment + Thermocouple installation 8x
Laser surveying team worked till 11. Chamber was too high by 3mm close to the jet target and 6mm by the turbo pump (towards the dipole). 

CARME lowered appropriate amount using bolts under CARME feet. Height checked using a laser on the centre point line of the middle flange turbo
end and mid point on the front of the chamber (see images). During lowering front foot swapped and valve supports moved slightly to give more clearance