Entry  Sat Sep 12 08:38:52 2020, CB (remotely), Baking over the weekend 20200912_0839_ctrl.png20200912_0839_plot.png
Saturday 12 Sep 08:43

Remotely checked status of baking. See attached.
Entry  Sun Sep 13 08:06:25 2020, CB (remotely), Baking over the weekend -2 20201309_0806_ctrl.png20201309_0806_plot.png
Sun 13 Sep 08:06

Baking reached 93 C yesterday afternoon at 16:18 and paused as a result of a percieved temperature gradient in
Entry  Wed Sep 16 08:52:03 2020, CB (remotely), Baking status 16-17 September 20200916_0850_temps.png20200916_0850_ctrl.png20200916_1500_temps.png20200916_2022_temps.png20200917_0820_temps.png
16 September

08:50
Entry  Wed Sep 30 08:10:36 2020, CB (remotely), First bake of CARME with pumps 19x
(NOTE: Raspberry Pi internal clock appears to be on GMT, rather than GMT+1 due to daylight saving.)

Baking started on Mon 28 Sep. Due to WiFi connection authorisation expiring, no remote access was possible until
Entry  Thu Oct 22 22:15:00 2020, CB (remotely), Cooling down after first NEG activation 7x
Thu 22 October

22:15 Temperatures stables, slowly decreasing.
Entry  Sun Sep 19 09:11:34 2021, CB (remotely), Baking RasPi status 
Accessed Pi remotely 

( 1. Without the Internet, the Pi has no way of knowing what time is it.
Entry  Wed Sep 22 08:30:08 2021, CB (remotely), CARME pressure during first XHV test 
CARME pressure moved to

https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?e=hEoZt7
Entry  Thu Sep 23 14:19:27 2021, CB (remotely), Checking baking remotely - instructions Temp.png
1. Connect to pi on CRYRING local network 
ssh pi@192.168.207.127
Entry  Fri Sep 24 15:36:34 2021, CB (remotely), CARME baking status Temp.pngTemps.png
Current temperature ~64 C

See plots attached
Entry  Sat Sep 25 07:23:06 2021, CB (remotely), CARME baking status -2 temp_plot.pngtemps.png
Current temperature ~90 C
However note setpoint is at 102 C. It appears we are baking at full power, but too many heat losses?
Temperature gradient still increasing. May just be a matter of time.
Entry  Sat Sep 25 19:01:50 2021, CB (remotely), CARME baking status -3 Temps.PNG
Baking automatically stopped due to negative gradient in on thermocouple for 10 minutes straight. 
Not surprising giving we were baking at full power bu making little progress. We should have switched to manual
mode.
Entry  Sun Sep 26 07:41:00 2021, CB (remotely), CARME baking status -4 Temps.pngScreen.png
Current temperature ~87C

See plot and screen attached.
Entry  Mon Sep 27 11:09:48 2021, CB (remotely), Temperature vs Pressure plot Temps.pdf
Attached.
Entry  Mon Sep 27 21:33:50 2021, CB (remotely), CARME baking status -7 Temps.pngScreen.png
Current temperature ~87 C, increasing
See plot and screen attached.
Thermocouple on CARME foot side (1-4) may have come loose judging from sudden jump in temperature at 14:30?
Entry  Fri Oct 1 21:47:51 2021, CB (remotely), CARME baking status -16 screen.pngTemps.png
Current temperature ~132 C (on manual mode RE72-1: 132 C, RE72-2: 130 C)
See plot and screen attached.
Entry  Sun Nov 28 15:57:45 2021, CB (remotely), Nov 2021 temperatures 211128164424_temperatures.zip
Attached
Entry  Tue Dec 7 09:39:59 2021, CB (remotely), Gate valves closed 
Dry run complete.

YR09 section valves closed. Section isolated. Manual valve between electron target and CARME remain open.
Entry  Thu Apr 10 07:02:12 2025, CB (remotely), Current logging enabled - sort of 
There appear to be issues with Shahab's caenlogging program. It crashes occasionally, with an error indicating the number of columns in the terminal
is incorrect. We will have to ask Shahab.

For now
Entry  Tue Aug 31 18:56:35 2021, CB, CARME status 9x
(ELOG does not allow more pictures to be added to previous entry)
Entry  Sat Oct 9 09:47:33 2021, CB, To do list for next week Capture.PNG
0. Give split-funnels to OG or Grossmontage to clean. Mount back foot support for gate valves. Critical when we split.

1. Wait for vacuum division to come to install: IE514 cables to current CM52 module, ion pump cables + controls + turn on, RGA head + program
+ turn on