ID Date Author Subject Text Attachments
  768   Fri Jan 16 13:59:08 2026 JM[How to] Startup CARME via x2goThe startup procedure is the same as the
regular startup as described in elog https://elog.ph.ed.ac.uk/CARME/666
with some important differences
  
  767   Fri Jan 16 13:54:08 2026 JMBackground run - R6/712:00

Background run started via x2go
- Run 6
  
  766   Wed Jan 14 09:06:01 2026 EW, JMJan26 - electronic testsR3 pulser walkthrough completed.

Pulser amplitudes from 90,000 to
10,000 in steps of 10,000
 7x 
  765   Tue Jan 13 12:59:37 2026 JM, EWCARME startup - Jan26 tests13/01/26

Arrived at GSI.

Biased DSSDs. Noticed higher leakage
 12x 
  764   Thu Dec 18 16:30:49 2025 CB, ML, JMAttempting to start CARME backgroundML flicked switch on CAEN bias module to
Enable, and restored remote control.

Attempted to bias the DSSDs. Leakage
 Capture.PNG 