  159   Tue Jul 7 08:04:57 2020 NHPower failure in MesshuetteLast week there was a power failure in Messhuette
(FRS control room) - AIDA-3 and MBS were
affected.
  
  160   Tue Jul 7 08:50:27 2020 NHnnrpi2 does not bootMIDAS was not working properly on nnrpi2 -
power cycled. Now system does not boot properly,
it gets stuck trying to login claiming "PAM
  
  161   Tue Oct 6 15:48:06 2020 NHnnrpi kernel updateFYI:

The SD card on nnrpi2 was full again causing
  
  162   Tue Nov 24 13:10:42 2020 NHWaveforms with frame groundedAIDA Frame is now grounded to platform (will
add photo later)
 waves_odd.pngwaves_even.png20201124_164416.jpg20201124_164413.jpg 
  163   Mon Feb 1 15:19:07 2021 NHAIDA Status Feb 202101.02.2021 - Four new sets of PSU, HDMI &
Ethernet cables were ran from the DESPEC
rack to the AIDA frame, in preparation for
  
  164   Sat Feb 6 10:45:55 2021 NHAIDA Status Feb 2021> 01.02.2021 - Four new sets of PSU, HDMI
& Ethernet cables were ran from the DESPEC
rack to the AIDA frame, in preparation for
 pregrd050222_E.pngpregrd050221_O.pngpostgrd050221_O.pngpostgrd050221_E.png 
  165   Fri Feb 12 17:31:04 2021 NHBackground runA background run has been started to check
the AIDA channels.
It is in /TapeData/BGFEB21
  
  166   Mon Feb 22 18:18:47 2021 NHAIDA Rates/Situation The ground cable (LEMO00) in aida07 was disconnected,
it has been reinserted and the waveforms
now look good.
 8x 
  167   Sat Feb 27 12:47:57 2021 NHAIDA Rates/Situation Updated figures as of 27 Feb 2021 - S4 is
now closed for experiments but may open on
Wednesday.
 10x 
  170   Thu Mar 4 11:03:04 2021 NHS452 Operating NotesPlease note the following "quirks" currently
present in S452 that are important
  
  208   Tue Mar 30 13:21:50 2021 NHnnrpi1 (tty logs)We had issues with all TTYs reading out on
nnrpi1, I have moved them from an apparently
faulty USB hub to a new one.
  
  212   Fri Apr 9 16:40:36 2021 NHnnrpi1 Updatennrpi1 is now back in S4 with a new SD card
and new raspberry pi.
The freezing originally continued (it was
  
  216   Mon Apr 12 18:36:31 2021 NH[HowTo] AIDA & MBSSome instructions on AIDA and MBS and troubleshooting
are available here
https://sf.gsi.de/lib/c9ba0b4c-26bc-43d0-9b49-213fc594610f/file/AIDA%20and%20MBS%20Tips%20and%20Troubleshooting.pdf
 AIDA_and_MBS_Tips_and_Troubleshooting.pdf 
  222   Thu Apr 15 12:23:22 2021 NHFast Discriminator MasksIt is possible to get good rates with the
fast discriminators with a few hot channels
mask in aida03 and aida10
 Image_Pasted_at_2021-4-14_18-57.png 
  227   Fri Apr 16 02:15:12 2021 NHImplants/PunchthroughRate with beam < 1000 Hz still

Not Uranium but some fragments possibly produced
 53_AM.png 
  276   Sat Apr 24 10:21:06 2021 NHSaturday 24.04.2021I have restarted some more of the consoles
that disappeared since the aidas-gsi issue
last night
 AnyDesk_2021-04-24_11-27-49.pngAnyDesk_2021-04-24_11-28-50.png 
  285   Wed Apr 28 10:06:11 2021 NHWednesday 28 April11.05 All system wide checks OK *except*
WR
 elog_temps.pngelog_gswr.pngelog_tse.pngelog_hv.pngAIDA_FEE.png.jpeg 
  292   Tue May 4 14:05:48 2021 NHMACB CablesDuring the installation of the 4 new HDMI
cables for aidas13-16 the HDMI cables between
the MACB Root and the MACB leaves were looped
 macb_front.jpgmacb_side.jpg 
  293   Tue May 4 14:26:50 2021 NHFEE64 Adapter wiring diagram and layoutA figure showing the FEE64 numbers (a previous
diagram had 2/6 and 4/8 on the wrong side
of the DSSD) and the wiring of pulser/HV
 AIDA_Adapter_Configuration(1).png 
  299   Fri May 7 13:11:22 2021 NHFriday 7th May14:11 - Alpha has been running most of morning

Just saw rates in tape spike to 6 MB/s...
 elog_locks.pngelog_temps.pngelog_rates.pngelog_rates1.pngaida13.txt 