65
|
Fri Aug 16 15:09:05 2019 |
NH | Aida Waves (All FEEs) | Included waves for all 12 FEEs
FEES 1, 5, 9 all show this HF noise
on it, and are all located at the top of |
12x |
59
|
Fri Aug 9 12:33:14 2019 |
NH | Aida Test 9/8/19 - FEES 1-6 | The water issue has been resolved - merely
incorrect temperature guages (replaced).
Water is 20 C as required. |
|
54
|
Fri Jun 28 15:05:49 2019 |
NH | Aida 28/6/2019 - WATER OFF | The humidity sensor hasn't reported
humdities under 90% yet. In order to try
and help dry the pipes and turn AIDA the |
|
56
|
Mon Jul 8 16:02:52 2019 |
NH, PJCS | Aida 28/6/2019 - WATER OFF | It occurs to to wonder if there is now
water inside the modules. If the metal of
the cooling plates is damp on the outside |
|
380
|
Fri Sep 3 13:39:42 2021 |
OH | Additional noise tests performed at GSI | Contents of an email from NH to OH and TD
about tests performed on an additional bias
supply:
|
   |
112
|
Thu Dec 19 13:06:02 2019 |
TD, NH | AIDA@DESPEC To Do list | FAIR phase 0 DESPEC experiments are scheduled
March-May 2020 see
|
|
2
|
Thu Sep 6 15:25:19 2018 |
OH, TD | AIDA@DESPEC Setup Photos | |
|
92
|
Tue Nov 12 13:22:19 2019 |
OH, NH, CA | AIDA09 Replacement | ASIC 1 on FEE9 was not producing signals.
A new HDMI cable was installed but still |
|
717
|
Thu Jul 24 13:36:34 2025 |
CC, MP, NK | AIDA05 connected and disconnected compared to AIDA09 | HT cable shielded, HT
of upstream AIDA from iseg, HT of downstream
AIDA from CAEN. Both channel 0 and 1 of CAEN |
10x |
57
|
Wed Jul 10 10:46:05 2019 |
NH | AIDA/Water 10.07.2019 | S4 Conditions:
25.2 C, 35.3% RH, Td = 8.8 C
Water temperature: 20 C |
|
384
|
Tue Oct 19 16:17:49 2021 |
OH | AIDA-gsi server to centos 7 | Following advice of CU have updated the server
to centos 7.
|
|
4
|
Thu Sep 13 17:21:59 2018 |
TD | AIDA upstream window |
The upstream window of the AIDA detector
assembly consists of 2x 50um aluminized mylar |
|
206
|
Wed Mar 24 10:31:03 2021 |
TD | AIDA to do (or to understand) list |
In no particular order
|
|
677
|
Mon Dec 16 13:07:04 2024 |
JB, MP, CC | AIDA timing test | https://elog.gsi.de/despec/Implantation+Stack/9?suppress=1
- Day 1 ELOG
Day2: |
16x |
678
|
Tue Dec 17 12:45:36 2024 |
JB, MP, CC | AIDA timing test |
|
  |
683
|
Wed Jan 8 16:47:05 2025 |
JB, MP, CC | AIDA timing test |
|
|
684
|
Thu Jan 9 12:46:43 2025 |
JB, MP, CC | AIDA timing test |
|
   |
396
|
Wed Feb 16 10:32:52 2022 |
PJCS | AIDA software changes and some suggestions | The Pi console monitor program now outputs
a full date/time to file for each line of
report. |
|
681
|
Wed Jan 8 10:08:29 2025 |
JB, GB, SD, MP, CC, JG | AIDA noise test with platform in position | Yesterday we spent time essentially performing
a dry run to get AIDA DAQ and bPlast into
the time sorter, there were some issues with |
   |
702
|
Tue Apr 8 08:52:39 2025 |
TD | AIDA grounding |
AIDA DSSSDs and FEE64-DSSSD cabling are electrically
isolated (by design) from snout, mounting |
 |