Entry  Sat Nov 12 01:45:00 2016, TD, Saturday 12 November 6x
10.45 DSSSD bias & leakage currents OK - see attachments 1 & 2
      FEE64 temperatures OK - see attachment 3
Entry  Fri Nov 11 00:50:00 2016, TD, Friday 11 November 11x
10.00 DAQ continues (R33) in no storage mode

      DSSSD bias & leakage currents OK - see attachments 1 & 2
Entry  Thu Nov 10 12:02:24 2016, TD, OH, CG, Thursday 10 November 30.png31.png32.png34.png

21.17 DAQ starts (R30)
Entry  Thu Nov 10 11:57:35 2016, TD, Data directory NP1412 renamed as RIBF123R1 

Data directory NP1412 renamed as RIBF123R1
Entry  Thu Nov 10 09:56:20 2016, TD, OH, ML, NP1412 R26 R27 8x
start 18.55 10.11.16
stop 
AIDA filename R26_0
Entry  Wed Nov 9 22:16:11 2016, CG, DK, TD, ML, NP1412 R24 R25 34x
07.15 R24 started. BRIKEN run 33.
      76~78Ni beam setting.
      F5 C target out. F7 CH2 in. F11 C out.
Entry  Wed Nov 9 11:07:14 2016, TD, CG, DK, NP1412 R22 R23 6x
DAQ start (R22) failed - merger remained in 'want first sync' state, no output to TapeServer -> soft reset OK

start 20.07
Entry  Wed Nov 9 09:50:50 2016, TD, NP1412 R20, R21 1.png2.png3.png4.png

DAQ start (R20) failed - nnaida5 dropped data transfer #1 link
Entry  Wed Nov 9 08:47:03 2016, OH, TD, NP1412 R16, R17 and R18 r16bias1.pngr16bias2.png
start 17:44
stop 17:49
AIDA filename R16
Entry  Wed Nov 9 07:16:59 2016, OH, TD, NP1412 R15 6x
Run 15

start 16:14
Entry  Wed Nov 9 02:14:08 2016, OH, TD, NP1412 R14 bias1.pngbias2.pngR14bias1.pngR14bias2.png
11.13 Still waiting to get beam back got access so took temp measurement.
      T=25.6 DP=0.0 H=18.1
      Biases and leakages good. Attachments 1 and 2
Entry  Wed Nov 9 00:49:03 2016, TD, OH, NP1412 R13 r13bias1.pngr13bias2.png
09.50 Run 13 Start
      Thick C target (6mm) removed from F11. All variable Al degraders put in place
      AIDA settings file: 2016Nov07-23.03.06
Entry  Tue Nov 8 23:36:56 2016, DK, TD, NP1412 R12 10x
Takechi team changes the condition: F5 carbon; F7 empty; F11 carbon

  F11 Plastic is 1.1kHz

BRIKEN: 161109_0828_747576Ni_013.dlt
Entry  Tue Nov 8 23:16:15 2016, DK, TD, NP1412 R11 R11_USB1.pngR11_USB2.png
Recovered AIDA after power cycle (unknown cause of crash from the end of R10)

Corresponding run in BRIKEN: 161109_0814_747576Ni_012

 
Entry  Tue Nov 8 22:04:21 2016, DK, NP1412 R10 R10_USB1.pngR10_USB2.png
Put the variable Al degraders all back in for safety (was 4.4 mm, now 5.4 mm)

Takechi team switches the condition: F5 empty; F7 CH2; F11 empty

 
Entry  Tue Nov 8 21:01:40 2016, CG, DK, NP1412 R9 
06.02 R9 started with Takechi group C target out and all variable degraders in.
      F5 C in. F7 empty. F11 empty.
      F11 plastic rate 1.1kHz.
Entry  Tue Nov 8 18:52:32 2016, CG, DK, NP1412 R7 R8 bias1.pngbias2.pngbias1.pngbias2.png
03.50 74-76Ni beam delivered to F11.
      F11 plastic rate ~1kHz.
      F5 C target in. F7 empty. F11 C target in.
Entry  Tue Nov 8 15:10:16 2016, CG, TD, DK, OH, NP1412 R5 R6 bias1.pngbias2.png
00.15 Setting changed to 71,72,73Ni. All variable degraders in.
      Will remove while watching rates to settle on degrader setting.
      F5 CH2 in. F7 CH2 out. F11 C target in.
Entry  Tue Nov 8 14:29:34 2016, TD, OH, DK, NP1412 Run 4 
23:28 Run 4 Start
      Thick 6mm C target in beam
      
Entry  Tue Nov 8 14:22:16 2016, TD, OH, DK, NP1412 R3 
11:21 Run 3 Started
      Degrader moved upstream. AIDA moved to centre of BRIKEN. Fixed degrader moved upstream from centre of BRIKEN.
11:25 Run 3 Stopped