AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  AIDA, Page 5 of 46  ELOG logo
  ID Date Authordown Subject Text Attachments
  284   Mon Jun 6 14:24:07 2016 TD, ML & YSR1118 (AIDA)22.14 R1118 starts

      aidas1 has been rebooted
 10x 
  286   Mon Jun 6 15:57:51 2016 TD, ML & YSR1121 (AIDA)
R1120 stalled shortly after DAQ GO
      'unable to connect' etc
 43.png44.png 
  299   Fri Jun 10 02:25:45 2016 TD, ML & YSDAQ State of Play - Friday 10 June 2016
10.25 Screenshots showing DAQ state of play
during NP1512
 6x 
  300   Fri Jun 10 02:52:02 2016 TD, ML & YSFriday 10 June 201610.50 SyncCheck ... EURICA server refusing
connection
 16x 
  923   Fri Nov 17 15:53:03 2023 TD, JB, JGFriday 17 November contd.
AIDA ASIC settuings 2023Nov16-18.55.20
     low comparator p+n FEE64s 0xa, n+n 0xf
 25x 
  920   Thu Nov 16 09:09:58 2023 TD, JB, CC, VPAIDA tests 16/11/2023Viewing AIDA status on Thursday morning 16/11/2023.

 48x 
  921   Thu Nov 16 17:43:25 2023 TD, JB, CC, VPAIDA test 16/11/2023 cont.Screenshot uploads as I hit the 50 image
upload limit.
 Screenshot_from_2023-11-16_16-37-22.pngScreenshot_from_2023-11-16_16-36-25.pngScreenshot_from_2023-11-16_16-35-51.pngScreenshot_from_2023-11-16_16-35-30.png 
  276   Sun Jun 5 01:32:44 2016 TD, DK, GL, AE, PJWFirst RIB implantation: Run 67We restarted the merger (Stop, Setup &
Configure, Go, Pause) and then we could restart
the DAQ as normal.  Rate is ~500 Hz. 
  
  471   Sat Nov 26 07:11:34 2016 TD, DK, AESaturday 26 November, Part II16.11 The cyclotron and BigRIPS condition
are now restored and we have good beam

     Count
  
  473   Sat Nov 26 07:45:48 2016 TD, DK, AEOffline analysis of R7_45R7_45 3mm Pb + 0.5mm W (+1mm Al) only (at
start of run) changing to 1.5mm W (+2mm Al)
 103.png110.png111.png 
  483   Sun Nov 27 06:35:47 2016 TD, DK, AESunday 27 November - part 214.15 BigRIPS run number is now 1029

15.22 BigRIPS run number is now 1030
 14x 
  538   Tue Mar 28 01:28:12 2017 TD, CG, OH, DKTuesday 28 March
09.13 DAQ run R3 ends OK (final file R3_9)
      
 15x 
  429   Mon Nov 7 23:15:14 2016 TD, CG, OHTuesday 8 November08.15 DAQ found stalled

      Soft reset OK
 12x 
  419   Thu Nov 3 17:42:37 2016 TD, CG, DKFriday 4 November
00.40-02.30 Discussion with PJCS
 
 32x 
  421   Fri Nov 4 04:35:03 2016 TD, CG, DKFriday 4 November part 213.35 Swapped HDMI cables from master MACB
to MACB #3 & #7
      for HDMI cables from MACB #7 ports
 36x 
  447   Wed Nov 9 11:07:14 2016 TD, CG, DKNP1412 R22 R23DAQ start (R22) failed - merger remained in
'want first sync' state, no output to TapeServer
-> soft reset OK
 6x 
  245   Sun May 29 10:11:07 2016 TD, CG & reply by PJCSSaturday 8 May 2016 - reply about 'H' and "X"> 15.20 DAQ histogramming & data transfer
#1 enabled
>       Merger configured, started, input
  
  145   Wed Jan 27 14:54:48 2016 TD, CGWednesday 27 January 2016MSL type BB18(DS)-1000 serial 2998-22
Bias +200V, I_L +8.110uA, ambient temperature
+20.2 deg C
 11.png14.png 
  232   Tue May 24 06:39:17 2016 TD, CGper FEE64 waveforms
Attachments 1-30 per FEE64 ASIC #1 waveforms
 30x 
  235   Wed May 25 02:10:51 2016 TD, CGWednesday 25 May 201610.05 Recirculating chiller on
      FEE power on
      Detector bias on - ambient temp +23
 50.png51.png60.png 