Entry  Thu Aug 18 22:39:35 2016, NT Brewer, New preamps arrived at Oak Ridge and tested working. IMG_20160818_145801.jpg
Collaborators,

Attached is a phone photo of example signals from the new preamps with 3 3He tubes connected to a scope. Scope channels 1,2,3 (color y,c,m respectively)
are preamp channels 1,2,3 while 4 (green) is open. Trigger is on channel 3, at 500mV/div and other channels are at 500,200,and 20 mV/Div for channels 2,1,4
Entry  Thu Aug 18 23:32:59 2016, NT Brewer, New preamps arrived at Oak Ridge and tested working. IMG_20160818_145801.jpgIMG_20160803_160430.jpg
Collaborators,

Attached is a phone photo of example signals from the new preamps with 3 3He tubes connected to a scope. Scope channels 1,2,3 (color y,c,m respectively)
are preamp channels 1,2,3 while 4 (green) is open. Trigger is on channel 3, at 500mV/div and other channels are at 500,200,and 20 mV/Div for channels 2,1,4
Entry  Tue Nov 8 06:13:11 2016, Tain et al, New plastic detector in F11 PlasticsBehinMUSIC1.jpgPlasticsBehindMUSIC2.jpg
There is a new plastic scintillator
after the MUSIC chambers
Entry  Mon Nov 7 13:11:42 2016, Alvaro, Ale, Jose, Jorge, New directory and Config file 161107Conf_BrikenFull.xlsx
For second part of Takechi's run:

Directory: /data/1611Commissioning/161107Parasitic
Entry  Tue Nov 22 08:28:36 2016, A. Tarifeno-Saldivia et al, New directory and Config File 
A new directory in the IFICdaq computer has been created for the parasitic measurements during the Fallon Beam Time.

The path of the folder is:
Entry  Mon May 4 15:03:47 2015, J.Agramunt J.L.Tain K.Gabor , New detector placed under the beam line photo_2-2.JPGphoto_1-2.JPGphoto_3-2.JPG
 New detector placed under the beam line, below MUSIC chamber
This detector replace the USA tubes in the DACQ because we need the preamp to plug it.
 
Entry  Wed May 6 04:57:24 2015, J.L. Tain, J. Agramunt, G. Kiss, New degrader thickness 
The Al degrader thickness was reduced to 4.8mm
Entry  Sat Oct 21 17:11:03 2017, JA, ATD, JLT, New Gasific configuration file 171022_Conf_BrikenFullYSO.xlsx
Configuration file saved on 22-Oct-2017 at 00:59
after increasing all the threshold in all 3He tubes to about 100keV.
Also the threshold of Clover detectors was slightly increased.
Entry  Sun Oct 22 11:32:59 2017, JA,ATD, JLT, New Gasific Configuration file 171022_1846_Conf_BrikenFullYSO.xlsx
 
Entry  Sat Oct 21 17:05:21 2017, JA,ATD, JLT, New DACQ hardware configuration TubeAncillaryDACQDistribution-October2017.xlsx
Configuration of BRIKEN DACQ hardware:
Detector->VME->ADC->Channel
Entry  Tue Nov 6 21:51:54 2018, NT Brewer, New D4Off.conf for HV also on github 



V A V/s V/s 1/0









------ ---------------
--------- ----- ---- ------- ------- ------ ------ -------------









0
192.168.13.239 0 0 PA1 1450 0.0001 50 10 1









0 192.168.13.239 1
Entry  Fri Mar 31 16:56:16 2017, JLT, YS,Liu,PV,CG, New Configuration file 
New configuration file: 
170331_Conf_BrikenFull.xlsx
Entry  Wed Mar 29 17:15:21 2017, JLT, New Config file 
New configuration file:
170330_Conf_BrikenFull.xlsx
Entry  Fri Nov 25 21:50:42 2016, AT, New Conf File 
161125Conf_BrikenFull.xlsx
Entry  Mon Nov 7 09:04:10 2016, Phong,Liu,Ale,Jose, New AIDA plastic calibration 161107_1800_AIDAplasticCalib.pdf
To have a range of about 200 MeV

Ortec671 Gain from x20 to x5 (fine gain : x0.5)
Entry  Sat Jul 9 21:08:08 2016, J.L. Tain, Neutron moderator Moderator-Table.pdfTable.pdfModerator-Shielding.pdf
Drawings of the polyethylene neutron moderator and table assembly
Entry  Tue Jul 19 13:47:55 2016, A. Tarifeņo-Saldivia, Neutron efficiency - Scanning on Z preliminary result Preliminar_Zscaning_BRIKEN_PremLabel_vsmall.png
 We have carried out a scanning of the neutron efficiency with respect to the position along the Z-axis (AIDA and BEAM hole) of a 252Cf neutron
source. A preliminary analysis is presented based on data from the online. A plot with the comparison of the simulations and experimental data is attached. The
experimental results are in good agreement with the GEANT4 simulations of the studies for design of the neutron detector. The simulations for the
Entry  Fri Nov 4 13:16:42 2016, JLTain,ATolosa,JAgramunt, Neutron Background Screenshot_from_2016-11-04_22-26-10.pngScreenshot_from_2016-11-04_22-35-46.pngScreenshot_from_2016-11-04_22-35-29.pngScreenshot_from_2016-11-04_22-43-32.png
Beam tuning in BigRIPS

At 19:00 access to Exp. Area was closed and the tuning
Entry  Sat Apr 1 04:03:31 2017, ID JA DK GK, Na37 Ne36 run 056 
Date: 1/04/2017
Start:12:00
BRIKEN run: 56
Entry  Sat Apr 1 01:04:31 2017, ID DK JA, Na37 Ne36 Run 54 
Date: 1/04/2017
Start: 09:03
BRIKEN run: 54