268
|
Thu Feb 24 08:30:36 2022 |
JG, MS | AIDA5 calibration test failed - solved | UPDATE: THE PROBLEM IS SOLVED FOR NOW:
Doing the calib for the 5th time
eventually worked. |
 |
269
|
Thu Feb 24 09:43:16 2022 |
JG, MS | check | Beam is still beeing tuned. Target is off.
- Motor on manual |
13x |
468
|
Mon Jan 15 18:51:28 2024 |
JG, DR, TD | Monday 15 January |
Cooling water manifolds
|
|
469
|
Tue Jan 16 08:57:44 2024 |
JG, DR, TD | Tuesday 16 January | 10.00 Outflow manifold returned from workshop
with leaking attachment point welding re-worked.
|
8x |
697
|
Tue May 27 15:18:46 2025 |
JG, CN, JM | run 24 | Run 24 running
27/05/2025
We start a new run with real data |
7x |
331
|
Mon Feb 28 13:56:02 2022 |
JG, CB | Temperature cycle to 125K | 14:45
Rutherford rate was decreased significantly
for longer period. |
|
456
|
Wed Oct 18 16:47:36 2023 |
JG, CB | Power outage | Local power outage at the CRYRING today,
while JG was trying to activate the ion pumps.
Unlcear what caused it. |
|
323
|
Mon Feb 28 06:12:58 2022 |
JG, AK, US | Current status | 07:20
Temperature setpoint = 110 k
Rutherford rates shaky, peak max |
8x |
326
|
Mon Feb 28 08:36:35 2022 |
JG, AK, CB | Current status | 09:35
beam intensity at injection: 8.2e7
ions |
8x |
327
|
Mon Feb 28 09:31:48 2022 |
JG, AK, CB | Current status | 10:35
beam intensity at injection: 1e8
ions |
8x |
329
|
Mon Feb 28 11:57:22 2022 |
JG, AK, CB | Current status | 12:55
beam intensity at injection: 9e7
ions |
8x |
330
|
Mon Feb 28 13:16:39 2022 |
JG, AK, CB | Current status | 14:16
beam intensity at injection: 7e7
ions |
8x |
750
|
Mon Jun 16 11:12:22 2025 |
JG, AK, AR, EH | run 83 | 12:15 restarted measurement with target
- Run 83
same settings as for runs 76, 77 |
8x |
324
|
Mon Feb 28 07:31:25 2022 |
JG, AK | Current status | 08:30
Temperature setpoint = 110 k
Rutherford rates shaky, peak max |
8x |
715
|
Mon Jun 2 20:03:43 2025 |
JG, AG, CB, EW, EM | Run 45/46, 0.5 MeV/A | Run 45 started.
D+ beam deuterium target. D+ beam
energy is 0.5 MeV/u. (beam calc calculation |
13x |
713
|
Mon Jun 2 17:25:31 2025 |
JG, AG | Run 43 scraper tests | Same settings are Run 42 but bunched beam
and scrapers set to: 30 / - 30 mm.
|
|
714
|
Mon Jun 2 17:48:07 2025 |
JG, AG | Run 44 scraper tests | Same settings are Run 43 but with coasting
beam and scrapers set to: 30 / - 30
mm. |
 |
325
|
Mon Feb 28 07:35:51 2022 |
JG | current logger crashed | The current logger did crash in the evening
of 25.02. and stopped logging since then,
it seems. |
|
517
|
Thu Feb 15 13:18:30 2024 |
JG | MBS DAQ: target & ring values | We are running an MBS DAQ to record the
attached list of slow control values of the
ring and the target. In most cases this is |
|
682
|
Mon May 12 13:25:09 2025 |
JG | MBS DAQ - overview | An MBS DAQ is running to collect two types
of data:
|
|
|