  455   Tue Oct 17 08:43:47 2023 CBNEG activation -209:40 - Found temperature and pressure
stablised, but too high to comfortably activate
NEGs closest to detectors. Detector temperature
 Screenshot_2023-10-17_09-45-23.pngScreenshot_2023-10-17_11-04-09.pngScreenshot_2023-10-17_14-56-55.pngScreenshot_2023-10-17_17-58-24.pngScreenshot_2023-10-17_17-58-51.png 
  495   Tue Feb 6 09:39:54 2024 CBDetector bias tests10:30 Found ADC#4 on aida 1 and 4 are suddenly
noisy. See attach 1-2. Checkloaded multiple
times - no effect.
 13x 
  9   Sat Sep 12 08:38:52 2020 CB (remotely)Baking over the weekendSaturday 12 Sep 08:43

Remotely checked status of baking. See attached.
 20200912_0839_ctrl.png20200912_0839_plot.png 
  10   Sun Sep 13 08:06:25 2020 CB (remotely)Baking over the weekend -2Sun 13 Sep 08:06

Baking reached 93 C yesterday afternoon at
 20201309_0806_ctrl.png20201309_0806_plot.png 
  13   Wed Sep 16 08:52:03 2020 CB (remotely)Baking status 16-17 September16 September

08:50
 20200916_0850_temps.png20200916_0850_ctrl.png20200916_1500_temps.png20200916_2022_temps.png20200917_0820_temps.png 
  24   Wed Sep 30 08:10:36 2020 CB (remotely)First bake of CARME with pumps(NOTE: Raspberry Pi internal clock appears
to be on GMT, rather than GMT+1 due to daylight
saving.)
 19x 
  29   Thu Oct 22 22:15:00 2020 CB (remotely)Cooling down after first NEG activationThu 22 October

22:15 Temperatures stables, slowly decreasing.
 7x 
  71   Sun Sep 19 09:11:34 2021 CB (remotely)Baking RasPi statusAccessed Pi remotely 

( 1. Without the Internet, the Pi has no
  
  74   Wed Sep 22 08:30:08 2021 CB (remotely)CARME pressure during first XHV testCARME pressure moved to

https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?e=hEoZt7
  
  77   Thu Sep 23 14:19:27 2021 CB (remotely)Checking baking remotely - instructions1. Connect to pi on CRYRING local network

ssh pi@192.168.207.127
 Temp.png 
  81   Fri Sep 24 15:36:34 2021 CB (remotely)CARME baking statusCurrent temperature ~64 C

See plots attached
 Temp.pngTemps.png 
  82   Sat Sep 25 07:23:06 2021 CB (remotely)CARME baking status -2Current temperature ~90 C
However note setpoint is at 102 C. It appears
we are baking at full power, but too many
 temp_plot.pngtemps.png 
  83   Sat Sep 25 19:01:50 2021 CB (remotely)CARME baking status -3Baking automatically stopped due to negative
gradient in on thermocouple for 10 minutes
straight. 
 Temps.PNG 
  84   Sun Sep 26 07:41:00 2021 CB (remotely)CARME baking status -4Current temperature ~87C

See plot and screen attached.
 Temps.pngScreen.png 
  87   Mon Sep 27 11:09:48 2021 CB (remotely)Temperature vs Pressure plotAttached.  Temps.pdf 
  89   Mon Sep 27 21:33:50 2021 CB (remotely)CARME baking status -7Current temperature ~87 C, increasing
See plot and screen attached.
Thermocouple on CARME foot side (1-4) may
 Temps.pngScreen.png 
  100   Fri Oct 1 21:47:51 2021 CB (remotely)CARME baking status -16Current temperature ~132 C (on manual mode
RE72-1: 132 C, RE72-2: 130 C)
See plot and screen attached.
 screen.pngTemps.png 
  164   Sun Nov 28 15:57:45 2021 CB (remotely)Nov 2021 temperaturesAttached  211128164424_temperatures.zip 
  166   Tue Dec 7 09:39:59 2021 CB (remotely)Gate valves closedDry run complete.

YR09 section valves closed. Section
isolated. Manual valve between electron target
  
  165   Tue Nov 30 10:49:43 2021 CB (remotely) GVGate valve openedGSI vacuum division IE514 gauge connected.

Gleb reports gate downstream opened.
Vacuum goes up and recovers as expected.
 vacplot24.png 