ID Datedown Author Subject Text Attachments
  68   Sat Sep 11 16:01:44 2021 CB RSSPreparations for shutdownFound CARME pressure at 2E-7 mbar

Raspberry pi took pictures until 4 am and
 turbo_pump.pnglog_scale.png 
  67   Fri Sep 10 18:09:14 2021 CB RSS MLLeak test + baking system testLeak tested CARME via He leak tester + He

bottle. No leaks could be found. Some 
  
  66   Fri Sep 10 10:50:55 2021 CB RSS MLPressure after overnight pump downPressure found in 10-7 mbar range.

Decided to leak test anyway for safety.
 20210910_101131.jpg 
  65   Thu Sep 9 13:01:07 2021 CB RSS + OGAll feedthrough flanges mounted and motor rotatedMoved cables that touched neg pumps. See 
photos. Please bear in mind perspective.
Note avoiding touching chamber 
 20210909_111933.jpg20210909_112120.jpg20210909_112125.jpg20210909_133027.jpg 
  64   Wed Sep 8 17:03:07 2021 CB RSS + OG NBSix feedthrough flanges mountedContinued to mount flanges as per previous
ELOG entry.
Peter also remarked that the wires look a
 23x 
  63   Wed Sep 8 10:52:54 2021 CB RSS + OGFirst feedthrough flange mountedAssembled feedthrough flange with re-cut 
SS support bracket. M3 vented on the 
sides, M3x30 partly threaded on top. Top
 20210908_101743.jpg20210908_111958.jpg20210908_112002.jpg20210908_112006.jpg20210908_112010.jpg 
  62   Tue Sep 7 14:10:02 2021 CB RSS + OGStrain relief SS support re-drilledRe-drilled SS supports in order to fit M3
screws.
  
  61   Tue Sep 7 12:40:43 2021 CB ML + RHCARME survey preparationRudi and survey group representative came

to CARME. 
  
  60   Tue Sep 7 11:37:05 2021 CB RSS + OGUpdate on strain relief screw issuesTested every strain relief. M3 screws get
stuck at different points in each hole. Only
one good hole out of 16
  
  59   Mon Sep 6 14:13:17 2021 CB MLMotors mounted - first attemptMounted both  motors on CARME. Started 
with outside motor.
 20210906_113522.jpg20210906_113519.jpg20210906_115601.jpg20210906_152607.jpg20210906_143944.jpg 
  58   Sat Sep 4 15:54:50 2021 CB RSSMotor mounting preparationPrepared the motors to be mounted and 
found all components required. No issues.
 20210904_162517.jpg20210904_162520.jpg 
  57   Fri Sep 3 15:55:00 2021 CB RSSIssues with cable clampsAttempted to mount cable clamps for strain

relief on inner part of Allectra 
 20210903_154614.jpg20210903_162519.jpg 
  56   Fri Sep 3 14:14:40 2021 TDLeybold IE514 manual & calibration data   20210903_141201.jpgIonivac_Sensors_IE414_IE514.pdf 
  55   Fri Sep 3 08:14:51 2021 CB RSSIssues foreseeable splitting CARMEIn order to install the detector supports

and eventually install the detectors 
 7x 
  54   Fri Sep 3 08:12:39 2021 CB RSSPressure after overnight pump down03.09.2021   09:00   5.27E-7 mbar     
03.09.2021   13:00   4.08E-7 mbar       
           
 20210903_085646.jpgIMG_4487.JPG 
  53   Thu Sep 2 21:04:26 2021 CB RSS ML + DR OGGate valves mounted + pump downMounted both gate valves and support. Gate

valves could not be installed one bolt 
 6x 
  52   Thu Sep 2 10:41:16 2021 CB RSS + DR OGCARME connected to the CRYRINGConnected CARME to the CRYRING via tube 
plus bellows. See attach.
 20210902_114031.jpg 
  51   Wed Sep 1 17:14:16 2021 CB RSS + DR MLCARME mounted on the CRYRINGLifted CARME with Al support on the 
CRYRING. No issues during transportation.
 20210901_162435.jpg20210901_173059.jpg20210901_174157.jpg20210901_134635.jpg20210901_173059.jpg 
  50   Wed Sep 1 12:05:28 2021 CB RSSPreparation for CARME on CRYRING YR09Mounted additional cross member for motor

support. See attach 1
 20210901_125504.jpg20210901_125517.jpg 
  49   Tue Aug 31 18:56:35 2021 CBCARME status(ELOG does not allow more pictures to be added
to previous entry)
 9x 