ID Date Authordown Subject Text Attachments
  567   Fri May 31 21:03:21 2024 CB, EMRun1422:03

Before this run we checked quickly 
beam with the target on but it does not make
 Screenshot_from_2024-05-31_22-05-57.pngScreenshot_from_2024-05-31_22-07-01.pngScreenshot_from_2024-05-31_22-07-49.png 
  500   Thu Feb 8 17:11:50 2024 CB, EHPulser walkthrough
17:30 File G22-88/R8

Pulser walkthrough

EGG
Ortec 448 Pulser

Amplitide 90,000-10,000
@ 10,000 step
Normalise 5.0
Attenuators
 4.png3.png 
  257   Wed Feb 23 16:57:35 2022 CB, CNOptimising motor motionOptimised motor motion during run R58

Moved 2 mm in (20.3 potentiometer)

29.47 potentiometer
  
  722   Fri Jun 6 16:49:59 2025 CB, AY, STBeam overlap results for 200keV and 250keVFor 200keV the optimal horizontal position
is -5mm.
For 250keV the optimal horizontal
 2025_06_06_17_46_56_Greenshot.png 
  752   Mon Jun 16 22:06:00 2025 CB, AR, EWRUN 90-9123:00 DAQ restored and data now being written
okay. Checks all okay, see screenshots below.
Histograms reset. 40 bars in bottle @ 23:45
 14x 
  573   Sun Jun 2 06:41:00 2024 CB, AGRun 21 - tests07:41

Switching to bunched beam to check
D vs H content.
 10x 
  574   Sun Jun 2 08:47:01 2024 CB, AGRun 22 - longer rung with 20 min storage09:47

12 seconds pre acc

200x cycles
 Screenshot_from_2024-06-02_09-47-53.pngScreenshot_from_2024-06-02_09-48-06.pngScreenshot_from_2024-06-02_11-21-59.pngScreenshot_from_2024-06-02_11-22-27.pngScreenshot_from_2024-06-02_13-02-31.png 
  569   Sat Jun 1 07:16:15 2024 CB, AB, EM, JMRun 19 - beam target overlapMorning shift

08:16 - as run 18, target off

9:00 Increased storage time to
 19x 
  488   Sat Feb 3 00:13:03 2024 CB TDRun1 end - R3 start
01.07 DAQ continues file G22-88/R1_46
      background alpha
 50x 
  490   Sun Feb 4 08:40:04 2024 CB TDRun3 - contd09.30 DAQ continues file G22-88/R3_17

      DSSSD bias OK - attachment 1
 22x 
  491   Mon Feb 5 05:45:26 2024 CB TDRun3 - end06.40 DAQ continues file G22-88/R3_42

      DSSSD bias OK - attachment 1
 47x 
  492   Mon Feb 5 12:48:50 2024 CB TDPulser walkthough - Run4
13.41 DAQ start - file G22-88/R4
 Screenshot_from_2024-02-05_14-04-33.pngScreenshot_from_2024-02-05_14-05-16.png 
  53   Thu Sep 2 21:04:26 2021 CB RSS ML + DR OGGate valves mounted + pump downMounted both gate valves and support. Gate

valves could not be installed one bolt 
 6x 
  66   Fri Sep 10 10:50:55 2021 CB RSS MLPressure after overnight pump downPressure found in 10-7 mbar range.

Decided to leak test anyway for safety.
 20210910_101131.jpg 
  67   Fri Sep 10 18:09:14 2021 CB RSS MLLeak test + baking system testLeak tested CARME via He leak tester + He

bottle. No leaks could be found. Some 
  
  64   Wed Sep 8 17:03:07 2021 CB RSS + OG NBSix feedthrough flanges mountedContinued to mount flanges as per previous
ELOG entry.
Peter also remarked that the wires look a
 23x 
  60   Tue Sep 7 11:37:05 2021 CB RSS + OGUpdate on strain relief screw issuesTested every strain relief. M3 screws get
stuck at different points in each hole. Only
one good hole out of 16
  
  62   Tue Sep 7 14:10:02 2021 CB RSS + OGStrain relief SS support re-drilledRe-drilled SS supports in order to fit M3
screws.
  
  63   Wed Sep 8 10:52:54 2021 CB RSS + OGFirst feedthrough flange mountedAssembled feedthrough flange with re-cut 
SS support bracket. M3 vented on the 
sides, M3x30 partly threaded on top. Top
 20210908_101743.jpg20210908_111958.jpg20210908_112002.jpg20210908_112006.jpg20210908_112010.jpg 
  65   Thu Sep 9 13:01:07 2021 CB RSS + OGAll feedthrough flanges mounted and motor rotatedMoved cables that touched neg pumps. See 
photos. Please bear in mind perspective.
Note avoiding touching chamber 
 20210909_111933.jpg20210909_112120.jpg20210909_112125.jpg20210909_133027.jpg 