  CARME, Page 36 of 38  ELOG logo
Entry  Thu Sep 2 21:04:26 2021, CB RSS ML + DR OG, Gate valves mounted + pump down 6x
Mounted both gate valves and support. Gate 
valves could not be installed one bolt 
rotated from 90 degrees as per drawings 
Entry  Thu Sep 2 10:41:16 2021, CB RSS + DR OG, CARME connected to the CRYRING 20210902_114031.jpg
Connected CARME to the CRYRING via tube 
plus bellows. See attach.
Entry  Wed Sep 1 17:14:16 2021, CB RSS + DR ML, CARME mounted on the CRYRING 20210901_162435.jpg20210901_173059.jpg20210901_174157.jpg20210901_134635.jpg20210901_173059.jpg
Lifted CARME with Al support on the 
CRYRING. No issues during transportation. 
Entry  Wed Sep 1 12:05:28 2021, CB RSS, Preparation for CARME on CRYRING YR09 20210901_125504.jpg20210901_125517.jpg
Mounted additional cross member for motor 
support. See attach 1
Entry  Tue Aug 31 18:56:35 2021, CB, CARME status 9x
(ELOG does not allow more pictures to be added to previous entry)
Entry  Tue Aug 31 18:34:41 2021, CB RSS + DR OG, CARME on Al stand 20210831_144545.jpg20210831_171442.jpg20210831_171447.jpg20210831_171449.jpg20210831_171453.jpg
Lifted CARME off the floor and mounted feet on sides. It was found impossible to put four bolts for each foot
due to alignment conflict. Three bolts were mounted per foot instead.
Entry  Tue Aug 31 11:55:11 2021, CB RSS, Last preparations for CARME lift 16304077162843806956479048661374.jpg16304077904321905824276870110392.jpg
Found strut bolts in the bag with 
spherical washers. Mounted the struts and 
the washers. See attach 1.
Entry  Tue Aug 31 07:09:54 2021, CB RSS (rem) JM, Preparation for mounting 6x
(30 August 2021)

The current state of YR09 is as per attach 1. CCC has been removed, but additional pumps and gauges remain. Some
Entry  Wed Aug 25 07:02:41 2021, RSS TD, 25-31 August 19x

Pirani  IE514
mbar    mbar


25/8/21 08:00 0.0030 1.86e-8

----------------------------------------------------

26/8/21   09:00  0.0030   1.77e-8

----------------------------------------------------
Entry  Wed Aug 18 11:58:49 2021, NTD RSS, Misc fittings and fasteners plus gasket inventory 22x
Attachments 1-3 fasteners, fittings found amongst earlier shipments. I assume that the STFC DL cleaned items are for the internal detector mount assembly.

Entry  Wed Aug 18 07:07:26 2021, RSS TD, 18-24 August 25x

Pirani  IE514
mbar    mbar


18/8/21 08:00 0.0034 3.90e-8
18/8/21 17:00 0.0032 3.72e-8


 

-------------------------------------------------------------

19/8/21  08:00  0.0032  3.38e-8
Entry  Fri Aug 13 07:28:37 2021, RSS TD, Friday 13-17 August  23x
Pirani  IE514
mbar    mbar
Entry  Thu Aug 12 09:16:42 2021, TD RSS, Thursday 12 August 13x

Attachment 1 - IE414/514 feedthrough wiring diagram
Entry  Wed Aug 11 12:30:40 2021, TD RSS, Wednesday 11 August  8x

Attachments 1 & 2 - 2x SAES D-2000 re-fitted to side ports
                    all 4x SAES D-2000 now re-fitted to chamber
Entry  Tue Aug 10 12:22:56 2021, TD RSS, Tuesday 10 August  20210810_115555.jpg20210810_115607.jpg20210810_115617.jpg

Attachments 1-3 - 2 of 4 SAES D2000 installed at same ports used for STFC DL XHV tests
Entry  Mon Aug 9 12:36:00 2021, TD, RSS, ABD, Monday 9 August 7x

Attachments 1-5 - CARME shipment in CRYRING hall
                  XHV chambers nearest to YR09
Entry  Mon Dec 7 14:29:12 2020, JM, CARME packing up 20201207_122353.jpg20201207_113905.jpg20201207_110714.jpg
 
Entry  Fri Dec 4 16:49:36 2020, TD, Friday 4 December 7x
 
Entry  Wed Nov 25 10:39:37 2020, TD, Wednesday 25 November 7x

10.39
Entry  Tue Nov 24 12:24:01 2020, JM, RGA scans 20201124_124107.jpg
RGA laptop passcode: tw%11&STA-   

RGA scans set up and plotting data as of 11:44

RGA is set to the multiplier mode (4.44e-8mbar) with an accuracy setting of 8, these are for the most sensitive scans. RGA is set to scan masses