  13   Sat Feb 28 09:20:14 2026 TDMIDAS DAQ configuration
MIDAS DAQ configuration files
 8x 
  14   Sat Feb 28 12:09:56 2026 TDOffline analysis data file R52
Offline data analysis of data file R52 
c. 1h 2.25MeV neutrons from 10uA p+ + 410ug/cm2
 8x 
  8   Fri Feb 27 12:41:34 2026 SB, TD, FGIFriday 27 February 2026
BNC PB-5 settings
Amplitude 5.0V
 11x 
  10   Fri Feb 27 14:38:28 2026 SB, TD, FGIR51
start: 14:31:03 (w23 is set to GMT)
stop: 14:38:09
 9.png 
  11   Fri Feb 27 15:17:59 2026 SB, TD, FGIR52Start: 15:06:06 GMT
Stop: 16:13:45
Blocks: 875
  
  12   Sat Feb 28 08:59:14 2026 SB, TD, FGIR53
start: 16:14:44 27.2.26
stop: 08:38:26 2.3.26
 6x 
  2   Thu Jan 29 16:16:46 2026 Francisco García InfantesSetUp StatusHere is a brief status update on the chamber
setup.

At the moment, we have all the
 Preamp_Modules.jpegChamber_In.jpegFrom_Chamber.jpegVoltage_Cable.jpeg 
  3   Fri Jan 30 15:45:48 2026 Francisco Garci­a InfantesDAQ and cables statusConcerning the electronic
stuff. We will need:
 VME_V430_crate.jpegCAMAC_Crate.jpegJonction_Box.jpegNIM_bin.jpegVME_V430_crate.jpeg 
  5   Tue Feb 10 09:03:26 2026 Francisco Garci­a InfantesContents of shipment boxesBOX
A

  
  6   Tue Feb 10 09:31:47 2026 Francisco Garci­a InfantesDetector Voltage vs CurrentAnalysis
of how the current changes with increasing
voltage for both detectors.
 Voltage_vs_Current.png 
  19   Mon Mar 2 11:11:18 2026 FGI, TD, SB, CLWSecond configuration.After the first weekend, we change the
setup configuration. We removed the shadow
cone, and we placed the chamber closer to
 DSSSD1_Voltage_New.jpegDSSSD2_Voltage_New.jpeg 
  22   Mon Mar 2 13:50:20 2026 FGI, TD, SB, CLWCablingThe cables are plug in this way.

Cable 0 connected to Preamp A,
Positive output. (n+n side, toward the sample)
  
  25   Tue Mar 3 15:28:37 2026 FGI, SB, CLWRun 59Before this run, we change the target for
the neutron source. We are using a Triton
target of ~200 ug/cm².
  
  27   Thu Mar 5 09:21:10 2026 FGI, SBRun 60NaCl #5 sample in beam

Starting time: 15:29:51

Stop time : 08:19:57
  
  28   Thu Mar 5 09:22:58 2026 FGI, SBRun 61Boron-10 #3 sample in beam

Starting time: 08:49:16

Stop time : 15:07:34
  
  29   Thu Mar 5 09:24:21 2026 FGI, SBRun62Gold + Mylar sample in beam

Starting time: 15:32:00

Stop time : 08:13:55
  
  30   Thu Mar 5 09:25:45 2026 FGI, SBRun 63LiF #8 sample in beam

Starting time: 08:34:15

Stop time : 14:53:02
  
  31   Fri Mar 6 08:55:16 2026 FGI, SBRun 64LiF #7 sample in beam

Starting time: 15:11:10

Stop time : 08:14:22
  
  32   Fri Mar 6 08:56:26 2026 FGI, SBRun 65Am-241 calibration source. Towards DSSSD
#2 (PreAmp B) upstream detector

Starting time: 08:41:21
 Am_241_Source.jpeg 
  15   Mon Mar 2 09:43:05 2026 FG,SB,CLW,TDRun 54
start: 09:36:05 2.3.26
stop: 09:43:49
2.3.26
blocks: 14

Cu rod taken
out, run in neutron beam with NaCl target.
  