  52   Thu Aug 10 16:11:57 2023 TD, NS, ARNoise
Observe c. 2mV p to p noise with DSO ( Z_in
= 50 Ohm ) c. 60us period with HF structure.
 20230810_162959.JPGIMG_2906.jpeg20230810_164219.JPG 
  56   Fri Aug 11 10:02:08 2023 TD, NS, ARNoise
Check RAL108 +/-15V PSU
 20230811_104233.jpg20230811_104253.jpg 
  63   Tue Aug 15 10:17:39 2023 TD, NSRAL108 +/-15V PSU test at EAR2, n_TOF Monday 14 AugustOn the morning of Monday 14 August 2x RAL108
+/-15V PSUs were borrowed from the Edinburgh
equipment in the ISOLDE hall to check whether
 7x 
  64   Tue Aug 15 11:41:27 2023 TD, NSMonday 14 August - vacuum chamber pressure
08.35 Vacuum chamber pressure OK - see attachment
1
 20230814_083514.jpg 
  43   Thu Jul 27 11:53:52 2023 TDMSL type W1 detector data for 26Al(n,X) experiment EAR2, n_TOFMSL type W1(SS)-20

3186-9  20um Depletion voltage 3V Operating
  
  62   Mon Aug 14 11:00:13 2023 TDRAL108 +/-15V PSU test in ISOLDE hall
This morning 2x RAL108 +/-15V PSUs were borrowed
from the Edinburgh equipment in the ISOLDE
 13x 
  66   Sat Aug 19 14:14:26 2023 TDRAL108 +/-15V PSU test - JCMB 18.8.23PSU Calex

Setup and PSU details - attachments 1-3
 10x 
  67   Mon Aug 21 12:08:59 2023 TDRAL108 +/-15V PSU test - JCMB 21.8.23PSU Calex

Setup, PSU and ac mains filter - attachments
 13x 
  79   Sat Sep 14 09:30:40 2024 TDNeutron beam profile
Neutron beam profile - film exposure overnight
12/13.9.24
 20240914_101751.jpg 
  80   Mon Sep 16 12:36:45 2024 TD34-way IDC to 37-way D connector ribbon cables
The 2x sets of 34-way IDC to 37-way D connctor
ribbon cables used at GSI for the two-alpha
 20240916_121057_(1).jpg20240916_121052_(1).jpg20240916_121047_(1).jpg20240916_121003_(1).jpg 
  85   Fri Jul 11 09:16:18 2025 TDSilena 7710 Quad Bias Supply manual and internal configurationManual - see attachment 1

 Silena_7710_quad_bias_supply.pdf 
  87   Sat Jul 12 11:25:35 2025 Selin The Detector Bias-Leakage Current DataThis Excel sheet has the detector bias-leakage
current data and plot for both detectors.

Detector 2 has lower leakage current
 Ca-VoltageCurrent.xlsx 
  88   Sat Jul 12 11:34:31 2025 SelinDetector-Cable ConnectionsList of the detectors and the connections.  Detector-Cable.pdf 
  89   Wed Jul 16 08:51:06 2025 SelinRun221136 Lithium Uncalibrated DataPlots of Lithium #3 run (221136) from the
Ca41 campaign with the right voltage applied
(11.07.2025).
 Li_Strip1.pngLi_Strip1_Par.pngLi_ded_2d.png 
  90   Wed Jul 16 08:55:22 2025 SelinRun221141 Boron Uncalibrated DataPlots of Boron #1 run (221141) from
the Ca41 campaign with the right voltage
applied (11.07.2025).
 B_Strip1.pngB_ded_2d.pngB_Strip22.png 
  92   Wed Jul 16 11:45:39 2025 SelinBoron Spectra Update After Setting Change + Pulser RemovedUncalibrated amplitude spectra of Boron
(run221188) after the settings were changed,
the pulser was removed, and the threshold
 B_Strip2_ded.pngB_Strip19_ded.png 
  95   Mon Jul 21 10:30:01 2025 SelinThe 2D Energy Spectrum of Ca41The 2D energy spectrum of Ca41 (36 runs). The
expected alpha energies are 4.8 MeV (alpha_0)
and 2.7 MeV (alpha_1).
 Screenshot_from_2025-07-21_08-51-09.png 
  1   Mon Oct 12 11:27:02 2015 Sarah Lonsdale05/10/15 - Set up notes   8x 
  2   Mon Oct 12 11:50:52 2015 Sarah Lonsdale05/10/15 Pulser, Wiring information and DAQ initial set up   2015-10-05_15.19.54.jpg2015-10-05_15.20.24.jpg2015-10-05_15.22.39.jpg2015-10-05_15.22.46.jpg 
  3   Mon Oct 12 12:04:51 2015 Sarah Lonsdale05/10/15 Photo of detector distances and layoutFairly self explanatory, note that images
with time-stamps before 13.08.29 were taken