101
|
Tue May 5 16:40:23 2015 |
JA, TD, AE, CG & JLT | Wednesday 6 May 2015 | 00.00 Degrader changed to 4mm + some of variable
(need to confirm)
Extra 1mm removed.
|
| |
|
102
|
Thu May 7 01:32:39 2015 |
JA, TD, AE, CG & JLT | Thursday 7 May 2015 | 09.25 R69 continues
100Kr setting, degrader 4mm + 0.4mm
(variable) Al
|
| |
|
103
|
Fri May 8 01:05:18 2015 |
JA, TD, AE & CG | Friday 8 May 2015 | 08.50 FEE64 temperatures (attachment 1)
09.03 R70 ends OK
|
| |
|
73
|
Mon Apr 27 01:48:59 2015 |
JA, LHB, TD, VP, AE & CG | Monday 27 April 2015 | DSSSD #1 +100V, +3.8uA
DSSSD #2 +100V, +5.5uA
|
8x | |
|
78
|
Wed Apr 29 01:03:41 2015 |
JA, LHB, TD, AE, CG & VP | Wednesday 29 April 2015 | Overnight
Beam tuning, PID tests - beam stopped
in scintilator detector + 1" thick Pb bricks |
16x | |
|
87
|
Thu Apr 30 16:20:54 2015 |
JA, LHB, TD, AE, CG & VP | Friday 1 May 2015 | diode link threshold 0xca -> 0xb6
0x11 -> 0x2c
|
| |
|
71
|
Sat Apr 25 03:56:44 2015 |
JA, LHB, TD, AE & CG | Saturday 25 April 2015 |
1130: Rotated forward water inlet connection
to point towards rear of AIDA stand to remedy |
   | |
|
72
|
Sun Apr 26 02:28:59 2015 |
JA, LHB, TD, AE & CG | Sunday 26 April 2015 |
Upstream, 207Bi source
|
33x | |
|
76
|
Tue Apr 28 06:25:13 2015 |
JA, LHB, TD, AE & CG | Tuesday 28th April progress | 28/04/15
1420: Carried out ASIC optimisation
tests to find best shaping time. Chose system |
6x | |
|
46
|
Mon Feb 23 07:23:08 2015 |
J. Agramunt, H. Baba, A. Estrade | DAQ correlation test | The attached figure shows the configuration
used to test the synchronization of the DAQ
systems using a
|
   | |
|
280
|
Mon Jun 6 08:57:34 2016 |
GL,PW, YS, TD, ML | AIDA run 1112 - Sync problem | After starting run 1112, we noticed that
the merge program was waiting for a first
sync. It then turned out that all syncs had |
| |
|
865
|
Wed Mar 1 16:42:06 2023 |
Further results from Mezzanine bench tests | PJCS | Carried out some further work on failed
mezzanine modules.
Inspected them externally and removed |
 | |
|
536
|
Mon Mar 27 03:28:53 2017 |
DK, TD, JA | Clock settings at the waveform generator stage | Clock settings for this experiment are slightly
different than in the previous case.
|
| |
|
432
|
Tue Nov 8 13:06:18 2016 |
DK, TD, CG, OH | NP1412 Run 1 | AIDA run with Takechi experiment. 71~73
Ni beam setting
F5 carbon target is: |
| |
|
310
|
Sat Jun 11 17:24:11 2016 |
DK, TD | Sunday 12 June 2016 | Runs 41 and 42 are quite short. Run
41 was interrupted by the beam dropping (operators
called), and run 42 we are just trying to |
14x | |
|
440
|
Tue Nov 8 23:16:15 2016 |
DK, TD | NP1412 R11 | Recovered AIDA after power cycle (unknown
cause of crash from the end of R10)
Corresponding run in BRIKEN: 161109_0814_747576Ni_012 |
 | |
|
441
|
Tue Nov 8 23:36:56 2016 |
DK, TD | NP1412 R12 | Takechi team changes the condition: F5
carbon; F7 empty; F11 carbon
F11 Plastic is 1.1kHz |
10x | |
|
470
|
Sat Nov 26 06:57:36 2016 |
DK, TD | Offline analysis of R7_37 |
R7_37 3mm Pb + from 0 to 1.8mm W (+ up to
3mm Al, 1mm per W layer - 0.3mm W, 0.5mm |
   | |
|
542
|
Wed Mar 29 08:13:34 2017 |
DK, PV, JL, CG | Degrader, Pb wall opening | 16:21
Chris noticed that when the degraders that |
| |
|
324
|
Tue Jul 5 13:43:02 2016 |
DK, PV | Pulser Test Run after AIDA is moved | Needed to run startx and start the TcLHttpd
server on rpi
Following along here: https://elog.ph.ed.ac.uk/AIDA/242 |