ID Date Author Subject Text Attachments
  58   Mon Apr 20 07:39:49 2015 CG, TDRasberry Pi : USB ac mains switch + USB serial link to FEE64 console
It would appear that you cannot reliably
startup the Raspberry Pi (nnrpi1)
  
  57   Mon Apr 20 06:53:24 2015 CG, TDProgress 20th April + RPi procedure20/04/15
1200: Complete all points on first
part of check list, except checking the PSU
 7x 
  56   Sat Apr 18 09:30:11 2015 CGTo do list 19/04/15 - 21/04/15To do (roughly in order):

     Move shipped boxes
down from Gabor's office to the experimental
  
  55   Mon Mar 9 16:51:26 2015 TDAIDA adaptor PCB configuration - RIKEN - Feb 2015   6x 
  54   Mon Mar 9 16:45:35 2015 TDJulabo FL11006 Recirculating Chiller: connection to 3ph ac mains
3ph 100VAC/50Hz to Julabo FL11006 3ph 230VAC/50Hz
via local transformer
 7x 
  53   Mon Mar 9 13:59:32 2015 TDNew AIDA support frame for F11/F12 @ RIKEN   IMG_2798.JPG 
  52   Mon Mar 9 09:02:03 2015 Patrick Coleman-SmithAdding Filters to the AIDA PSU.  This guide is to help with the filter
pcb assembly and installation into the AIDA
power supply.
 Assembly_of_the_AIDA_PSU_filter_and_installation_guide.pdf 
  51   Thu Mar 5 12:11:44 2015 TDTo Do list - March 2015A draft 'to do' list in preparation for further
AIDA tests at RIKEN from mid-April.
  
  50   Wed Mar 4 17:38:06 2015 CGLog book for Feb 2015 tests04/03/15
Please find attached a scan of the
log book for the Feb 2015 AIDA tests at RIKEN. 
 AIDA_Feb2015_labBook_comp.pdf 
  49   Wed Feb 25 09:59:28 2015 CG, AEWeds 25th Feb progress25/02/15
1200: Swapped out old green power
switch for new one from UoE (having previously
 2015-02-25_14.25.40.jpg2015-02-25_14.38.43.jpg25Feb_Rly16error.png 
  48   Tue Feb 24 03:04:59 2015 CG, TDTues 24th Feb progress24/02/15
1200: Update the FEE firmware on
nnaida1-16 without problem.
 9x 
  47   Mon Feb 23 11:10:44 2015 TDOutline test plan - RIKEN - Feb 2015
With the exception of one AIDA FEE64 PSU
configuration test (5) and the upgrades
 RIKEN_test_-_Feb_2015.txt 
  46   Mon Feb 23 07:23:08 2015 J. Agramunt, H. Baba, A. EstradeDAQ correlation testThe attached figure shows the configuration
used to test the synchronization of the DAQ
systems using a
 DAQcorrelation_diagram.pdfDAQsoftware.pdfcorrelation_25Hz.pngcorrelation_random.png 
  45   Mon Feb 23 07:03:10 2015 TD, AE & CGMonday 23 February 201514.30 Saved nnaida1-16 ASIC + Waveform
configurations to directory (Data Base Key)
          
  
  44   Sun Feb 22 06:47:23 2015 CG, AE, TDSunday 22 February 201522/02/15
am    Testing various
grounding configurations for the connection
 Screenshot.png 
  43   Sat Feb 21 06:37:52 2015 CG, AE, TDSat 21st Feb progress21/02/15
1230: Developing the software to
check synchronisation between DAQs. Below
 6x 
  42   Fri Feb 20 10:48:09 2015 TDHow To Connect the FEE64 System Console Using PuTTY
Set permissions for the USB-serial device
using the command
  
  41   Fri Feb 20 10:04:29 2015 CG, AE, TDFri 20th progress20/02/15
1400: Measured leakage current as
function of bias V for the Caen 1419B high
 bias_voltage_vs_leakage_current_for_caen_n1419b_and_detector_bb18_2977-20(2).png2015-02-20_20.27.57.jpg 
  40   Thu Feb 19 08:21:33 2015 CG, AE, TDThrus 19th Feb progress19/02/15
1000: Check system gives same resolution
as yesterday, removing only the Cu braiding
 39x 
  39   Wed Feb 18 11:25:54 2015 Patrick Coleman-SmithInvestigations into removing HV noise With the system in T9 and a Keithley
Source Meter supplying HV to the detector.
The source meter supplies 200V and
  