ID |
Date |
Author |
Subject |
Text |
|
330
|
Mon Oct 16 05:52:14 2017 |
BRIKEN collaboration | START preparation | We start to check every thing for the coming
run
|
|
171
|
Sat Nov 26 06:30:30 2016 |
AT | Setup | Setup for parasitic experiments
Energy 41Al @ F11 is around 145MeV/u
|
|
321
|
Mon Jun 12 02:45:44 2017 |
Iris Dillmann AT | Setup detectors. Id of Ancillary@BRIKEN | Attachment 1: Setup detectors
Attachment 2: example of configuration file
(valid only for RIBF127). The Id of the ancillary |
|
145
|
Tue Nov 8 17:00:27 2016 |
NTB, CG, AT | Si Delta E | At least during the timeframe in between
~ 21:30 (11/08) - 23:30 (11/09) (161108_2323_717273Ni.root)
we see that the silicon dE have a very low |
|
123
|
Mon Nov 7 04:37:33 2016 |
Phong,Liu,... | Si de and AIDA plastic calibration | 60Co source placed close to the detectors:
ROOT files:
|
|
190
|
Tue Nov 29 00:30:42 2016 |
PV,SN | Sillicon dE bias voltage increased | We increase the bias voltage of the dE
detector from 20 V to 100 V
Leakage current: |
|
134
|
Tue Nov 8 02:49:19 2016 |
PV, Liu | Specification of the dE silicon detector | The specification and picture of the dE silicon
detector is shown in the attached photos.
The detector has an effective area of 134 |
|
358
|
Tue Oct 16 03:15:03 2018 |
ATD & JLT | Start of REP run preparation (RIBF148) | 16-Oct-2018
- Start DACQ computer: OK!
|
|
210
|
Wed Mar 29 13:31:37 2017 |
J Agramunt, R. Caballero, T. Davinson, C. Griffin, O. Hall, D. Kahl, G. Kiss, J. Liu, S. Nishimura, V. Phong, JL Tain | Start of parasitic | Start of parasitic Ca beam
(main experiment "New isotope search", Ahn
et al.)
|
|
348
|
Wed Oct 25 01:02:14 2017 |
RG | Status of the YSO array | The presently used detector has 48x48x5
mm3 YSO array with 1x1mm2 segments. They
are separated with ESR. We use H8500 |
|
12
|
Sun May 3 09:04:07 2015 |
J.L. Tain, J. Agramunt, G. Kiss | Summary of neutron measurements |
U: (Up: 2 RIKEN tubes at 40cm from AIDA)
D: (Down: 12 RIKEN tubes at 80cm from AIDA)
|
|
308
|
Fri May 26 09:07:46 2017 |
J. Agramunt | Synchronization Monitoring | We started the synchronization monitoring
programs to check that
it is OK as can be seen in the figure below
|
|
207
|
Wed Mar 29 03:02:02 2017 |
J. Agramunt | Synchronization test procedure (update) | To Launch the processes:
Open 4 terminals:
|
|
396
|
Fri Oct 26 03:31:33 2018 |
AT2 & JA | Test pulser effect on baseline | We have tested possible change of the baseline
in the digitizer due to the pulser connection.
NO EFFECT has been
|
6x |
20
|
Tue May 5 02:19:58 2015 |
j.Agramunt J.L.Tain K.Gabor | The Lower polyethylene pieces was swamped | The Lower polyethylene pieces was swamped.
In the photo beam comes from the
left. |
|
322
|
Mon Jun 12 22:28:02 2017 |
Oscar | The SUSHIRO app guide | It's here...it's rough...but it hopefully
gets the job done |
|
105
|
Thu Nov 3 14:02:49 2016 |
Nepal, J Ha, PV, Liu J | The degrader system has been set | We used the laser to align the degrader
(see attached photos)
According to the LISE calculation, |
|
203
|
Mon Mar 27 11:53:15 2017 |
PV,Liu | Turn on dE detector | We applied a bias voltage of 100 V to the
dE detector
Current read = 0.660 uA |
|
6
|
Wed Feb 25 07:38:42 2015 |
A. Estrade J. Agramunt | Usage of synchronization test programs | In order to access to the synchronization
test, we prepare two programs in the PC
briken1 ( 10.32.6.54). |
|
75
|
Tue Oct 11 15:58:01 2016 |
JL Tain et al | VETO Det | Check of Plastic and NaI veto detectors and
DACQ settings
|
|