ID |
Date |
Author |
Subject |
Text |
 |
376
|
Sun Oct 21 08:58:23 2018 |
AT & AT | background, high threshold, NO pulser | 18/10/21 START: 16:58
18/10/21 STOP: 19:09
Background measurements. Checking noise!
|
|
374
|
Sun Oct 21 03:19:54 2018 |
AT & AT | background, high threshold |
18/10/20 START: 20:30 approx
18/10/21 STOP: 11:20
|
|
375
|
Sun Oct 21 06:04:43 2018 |
AT & AT | background, high threshold | 18/10/21 START: 14:10
18/10/21 STOP: 16:41
Background measurements. Checking noise!
|
|
368
|
Fri Oct 19 00:28:48 2018 |
AT2, JLT, SN | background measurement, no clovers |
18/10/19 START: 08:31
18/10/19 STOP: 10:50
|
 |
60
|
Fri Jul 29 09:52:28 2016 |
Keishi Matsui | accuracy of Cf-252's intensity in RIKEN | According to the reply from Japan
Radioisotope Association, the accuracy of
the Cf-252's intensity is +0%/-15%. |
|
357
|
Fri Dec 1 07:29:47 2017 |
Vi Ho Phong | [Hardware][Configuration] Return the PB-5 Pulse generator (Pulser 2) and the 428F Linear Fan in-out modules and replace with a new Linear Fan in-out module | The PB-5 Pulse generator labeled "Pulser 2"
and the 428F Linear Fan in-out labeled "Clover
G7" from BRIKEN NIM crate have to be returned |
7x |
5
|
Tue Feb 24 09:34:54 2015 |
J. Agramunt, H. Baba, A. Estrade | [DAQ] DAQ correlation test |
We have performed a successful test of the
integration of independent DAQ systems based |
   |
328
|
Thu Jun 15 03:40:17 2017 |
BRIKEN collaboration | Z-scaning 252Cf Jun17 | A scaning with 252Cf along the Z-axis of
the neutron detector is carried out. The
setup is similar to the scaning carried out |
|
355
|
Thu Nov 16 02:32:23 2017 |
BRIKEN collaboration | YSO thresholds | YSO Tests
Thresholds & calibrations
|
|
320
|
Mon Jun 12 02:38:27 2017 |
JA AA AIM AT AT | VME crate & new configuration | Sun Jun 4 2017 11:16:45 VME crate #1 crashed
New configuration file of BRIKEN
|
|
75
|
Tue Oct 11 15:58:01 2016 |
JL Tain et al | VETO Det | Check of Plastic and NaI veto detectors and
DACQ settings
|
  |
83
|
Thu Oct 13 23:39:58 2016 |
JL Tain et al | VETO Det | Energy calibration of plastic and NaI detectors
|
    |
6
|
Wed Feb 25 07:38:42 2015 |
A. Estrade J. Agramunt | Usage of synchronization test programs | In order to access to the synchronization
test, we prepare two programs in the PC
briken1 ( 10.32.6.54). |
 |
203
|
Mon Mar 27 11:53:15 2017 |
PV,Liu | Turn on dE detector | We applied a bias voltage of 100 V to the
dE detector
Current read = 0.660 uA |
   |
105
|
Thu Nov 3 14:02:49 2016 |
Nepal, J Ha, PV, Liu J | The degrader system has been set | We used the laser to align the degrader
(see attached photos)
According to the LISE calculation, |
 |
322
|
Mon Jun 12 22:28:02 2017 |
Oscar | The SUSHIRO app guide | It's here...it's rough...but it hopefully
gets the job done |
|
20
|
Tue May 5 02:19:58 2015 |
j.Agramunt J.L.Tain K.Gabor | The Lower polyethylene pieces was swamped | The Lower polyethylene pieces was swamped.
In the photo beam comes from the
left. |
|
396
|
Fri Oct 26 03:31:33 2018 |
AT2 & JA | Test pulser effect on baseline | We have tested possible change of the baseline
in the digitizer due to the pulser connection.
NO EFFECT has been
|
6x |
207
|
Wed Mar 29 03:02:02 2017 |
J. Agramunt | Synchronization test procedure (update) | To Launch the processes:
Open 4 terminals:
|
|
308
|
Fri May 26 09:07:46 2017 |
J. Agramunt | Synchronization Monitoring | We started the synchronization monitoring
programs to check that
it is OK as can be seen in the figure below
|
 |