AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  CARME, Page 29 of 38  ELOG logo
ID Date Authordown Subject Text Attachments
  289   Sat Feb 26 23:20:13 2022 David, Pierre-MichellUpdate statusIn this last hour we have been playing
with the cryostat temperature as dictated
by Nikos, in order to have the target working
 7x 
  290   Sun Feb 27 00:07:15 2022 David, Pierre-MichellNo beam, valve closedAt 00:37 we lost the beam due to a high
pressure burst in the tarjet which resulted
in a valve closed at YR09VV...
  
  291   Sun Feb 27 00:53:24 2022 David, Pierre-MichellCurrent statusWe have recovered the beam at 01:49, after
such a long time we had no target so we increased
from 80K to 120K at 01:52. 02:01 update 120K-->95K
 7x 
  292   Sun Feb 27 01:46:56 2022 David, Pierre-MichellCurrent statusSo far looks like with a temperature of
95K the target is maintained with a reasonable
density throughout long periods of time.
 2022-02-27_02-50-15exrate.png2022-02-27_02-49-47extot.png2022-02-27_02-49-28xytot.png 
  293   Sun Feb 27 02:38:52 2022 David, Pierre-MichellCurrent statusWe have decreased the temperatur> 95K
--> 90K. At 95K the target was stable,
but let's try to increase the density
 2022-02-27_03-43-36aida.png2022-02-27_03-42-55xyto.png2022-02-27_03-42-14exra.png2022-02-27_03-41-49extot.png 
  294   Sun Feb 27 03:49:36 2022 David, Pierre-MichellCurrent status04:06 85K -->120K : 04:13 120K -->95K

current ring 8e7 p/s

Merger, Tape server (WS3):
 2022-02-27_04-53-12xytot.png2022-02-27_04-52-51exrst.png2022-02-27_04-52-31extot.png 
  295   Sun Feb 27 04:54:46 2022 David, Pierre-MichellCurrent statusRing current 8e7 particles/s

Merger, Tape server (WS3):
1664 kB/s writing ok
 2022-02-27_05-56-59exra.png2022-02-27_05-56-31exto.png2022-02-27_05-56-13xytot.png 
  296   Sun Feb 27 05:45:53 2022 David, Pierre-MichellCurrent status6:05: 95K-->120K

6:12: 120K --> 95K

Ring current 8e7 particles/s
 2022-02-27_06-50-09exrat.png2022-02-27_06-48-23eytot.png2022-02-27_06-48-05extot.png2022-02-27_06-47-47xytot.png 
  357   Tue Mar 1 22:10:26 2022 David, GeorgeCurrent statusRing current 6.67e7 particles/s

pressure at S1: 2.3-2.8e-8

Merger, Tape server (WS3):
 2022-03-01_23-14-43aida.png2022-03-01_23-13-57exrate.png2022-03-01_23-13-40xyto.png2022-03-01_23-13-10extot.png 
  358   Tue Mar 1 23:30:04 2022 David, GeorgeCurrent status00:30
Pressure in S1 slightly decreased
from before but still high enough to measure
 2022-03-02_00-39-47xytotal.png2022-03-02_00-39-20exRate.png2022-03-02_00-38-44extotal.png 
  359   Tue Mar 1 23:43:15 2022 David, GeorgeBeam Intensity Drop00:38
Intensity in the ring dropped by 2
orders of magnitude to 5e5 on injection
  
  360   Wed Mar 2 01:24:48 2022 David, GeorgeIon Source Update02:25
Zoran was unable to ignite the ion
source.
  
  361   Wed Mar 2 03:40:40 2022 David, GeorgeTemperature Cycle04:40
Target density is hovering between
2.0e-8 and 2.3e-8, sometimes dipping below
  
  239   Tue Feb 22 17:32:38 2022 DavidCurrent statusMichael is modifying
the settings of the electron cooler -->
changed beam from bunched to coasting
 12x 
  241   Tue Feb 22 19:11:18 2022 DavidCurrent statusStill trying to recover previous pressures,
more details in the next entry.

Merger, Tape server (WS3)
 2022-02-22_20-16-26eyrate.png2022-02-22_20-15-34.eytotal.png 
  584   Tue Jun 4 00:04:39 2024 DR, EHRun 31Beam energy = 3 MeV

Horizontal beam position = 4.0
mm, vertical beam position = 0.0 mm.
  
  593   Thu Jun 6 05:44:45 2024 DR YL DB LB CB JMRun 38 - 15N Tests06:45

All system checks OK

Target density 3.4e11
 8x 
  585   Tue Jun 4 06:56:02 2024 DFF, PC, LB, JM,NP,ABRun 31 contd8:13

Since 6:40 the target density dramatically
dropped to 10^9 since then it has been unstable
 Screenshot_from_2024-06-04_10-53-58.pngScreenshot_from_2024-06-04_10-58-02.png 
  259   Wed Feb 23 19:22:55 2022 CN, TDcheck 

- Motor checked , OK

SW3
 10x 
  261   Wed Feb 23 20:52:56 2022 CN, TDSystem wide checks
Attachments 1-5 aida01-aida05 options
 11x 
ELOG V3.1.4-unknown