83
|
Fri May 31 09:49:08 2019 |
A. Algora | Backgroun, beam on | Start: 17:49
Stop: 22:11
Root: 201905312211_background_AIDA_in.root |
|
82
|
Fri May 31 07:03:37 2019 |
A. Algora | Background, beam on, rates at F11PL and AIDAPL | Start: 15:04
Stop: partial (17:43), 201905311743_background_AIDA_in.root
(file corrupt again), system will be restarted |
|
81
|
Fri May 31 06:48:58 2019 |
A. Algora | T spectra for AIDA and F11 plastics | T spectra for AIDAPL and F11PLL and F11PLR
are defined from now on. The ancilliary card
was not saving the CFD values for all channels. |
|
80
|
Fri May 31 02:41:55 2019 |
A. Algora | Background, beam on | Start: 10:42
Stop: 11:49
Root: 201905311149_background_AIDA_in.root |
7x |
79
|
Thu May 30 12:08:01 2019 |
A. Algora | background, dacq restarted before the measurement | Start: 20:09
Stop: 10:17
Root: 201905311017_background_AIDA_in.root |
|
78
|
Thu May 30 08:57:34 2019 |
A. Algora | Background, no beam + beam, file not saved | Start: 16:57
Stop:
Comments: first part no beam, but |
|
77
|
Thu May 30 08:43:29 2019 |
A. Algora | Background no beam | Start: 16:43
Stop: 16:56
Root: 201905301656_background_AIDA_in.root |
|
76
|
Thu May 30 07:21:41 2019 |
A. Algora | Background with beam on | Start: 15:21
Stop: 16:41
Root: 201905301642_background_AIDA_in.root |
|
75
|
Thu May 30 06:46:10 2019 |
A. Algora | Background with beam | Again a new test with the beam on. At the
begining the beam was off and it can be noticed.
There is a lead wall after F11 |
|
74
|
Thu May 30 06:41:18 2019 |
A. Algora | Background with the beam | There was an small increase in the counting
rate of the detectors after the beam was
delivered. The rate at |
|
73
|
Thu May 30 02:44:56 2019 |
A. Algora | Background, just a test | Start: 11:01
Stop: 13:37
Root: 201905301337_background_AIDA_in.root |
|
72
|
Thu May 30 02:03:33 2019 |
A. Algora | Ref detector position changed, AIDA plastik HV changed | The position of the reference detector
in the ancilliary card was changed from channel
10 to channel 9. Remember that this is important |
|
71
|
Wed May 29 10:01:10 2019 |
A. Algora | Background, no lmd, AIDA in | Start: 18:02
Stop: 18:33, partial file (201905291833_background_AIDA_in.root),
Stop: 09:53 saved also next day (30/05) 201905300953_background_AIDA_in.root |
|
70
|
Wed May 29 09:49:25 2019 |
A. Algora | New configuration file | New configuration file after a few small
changes in thresholds. |
|
69
|
Wed May 29 09:08:11 2019 |
A. Algora | AIDA plastic setting changed | AIDA plastic changed.
HV was at 1000 V, it was changed
to 1300 V |
|
68
|
Wed May 29 08:29:26 2019 |
A. Algora | latest conf file | Latest configuration file from 28 of May |
|
67
|
Wed May 29 07:04:19 2019 |
A. Algora | F11 plastic connected | F11 plastic has been connected to our dacq
as it was in the earlier BRIKEN setting.
The detector cables were followed |
|
66
|
Wed May 29 02:07:20 2019 |
A. Algora | Irradiation for 24Na | Irradiation of two pieces of aluminium
of 80 mm x 40 mm x 10 mm will be performed
at the second BigRips dipole. |
|
65
|
Tue May 28 07:49:51 2019 |
A. Algora | Background, no lmd | Start: 15:50
Stop: 10:09 (next day)
Root: 201905291009_background_AIDA_in.root |
|
64
|
Tue May 28 06:13:27 2019 |
A. Algora | Background, Aida in | Start: 14:13
Stop: 15:47
Lmd: Background_AIDA_in_201905281413_231.dlt |
|