448
|
Wed Nov 9 22:16:11 2016 |
CG, DK, TD, ML | NP1412 R24 R25 | 07.15 R24 started. BRIKEN run 33.
76~78Ni beam setting.
F5 C target out. F7 CH2 in. F11 C out.
|
34x | |
|
447
|
Wed Nov 9 11:07:14 2016 |
TD, CG, DK | NP1412 R22 R23 | DAQ start (R22) failed - merger remained in
'want first sync' state, no output to TapeServer
-> soft reset OK
|
6x | |
|
446
|
Wed Nov 9 09:50:50 2016 |
TD | NP1412 R20, R21 |
DAQ start (R20) failed - nnaida5 dropped
data transfer #1 link
|
   | |
|
433
|
Tue Nov 8 13:37:06 2016 |
TD, OH, DK | NP1412 R2 | 10:36 Run 2 Start
Degraders (5.4mm Al) in at start and
all removed once started.
|
6x | |
|
445
|
Wed Nov 9 08:47:03 2016 |
OH, TD | NP1412 R16, R17 and R18 | start 17:44
stop 17:49
AIDA filename R16
|
 | |
|
444
|
Wed Nov 9 07:16:59 2016 |
OH, TD | NP1412 R15 | Run 15
start 16:14
|
6x | |
|
443
|
Wed Nov 9 02:14:08 2016 |
OH, TD | NP1412 R14 | 11.13 Still waiting to get beam back got access
so took temp measurement.
T=25.6 DP=0.0 H=18.1
|
   | |
|
442
|
Wed Nov 9 00:49:03 2016 |
TD, OH | NP1412 R13 | 09.50 Run 13 Start
Thick C target (6mm) removed from F11.
All variable Al degraders put in place
|
 | |
|
441
|
Tue Nov 8 23:36:56 2016 |
DK, TD | NP1412 R12 | Takechi team changes the condition: F5
carbon; F7 empty; F11 carbon
F11 Plastic is 1.1kHz |
10x | |
|
440
|
Tue Nov 8 23:16:15 2016 |
DK, TD | NP1412 R11 | Recovered AIDA after power cycle (unknown
cause of crash from the end of R10)
Corresponding run in BRIKEN: 161109_0814_747576Ni_012 |
 | |
|
439
|
Tue Nov 8 22:04:21 2016 |
DK | NP1412 R10 | Put the variable Al degraders all back
in for safety (was 4.4 mm, now 5.4 mm)
Takechi team switches the condition: |
 | |
|
531
|
Wed Feb 1 16:54:40 2017 |
CG | NP1306 run summary | |
| |
|
229
|
Mon May 23 09:17:55 2016 |
Patrick Coleman-Smith | Multiplicity Trigger Specification | Please read and comment on the attached
specification. |
| |
|
902
|
Mon Oct 9 14:29:12 2023 |
TD | Monday 9 October contd. |
15.20 aida10 LK4 ( front f/p -> gnd ) fitted
- investigate impact aida10 asic #4 edge |
| |
|
901
|
Mon Oct 9 09:03:10 2023 |
TD | Monday 9 October | 09.55 Water pressure and temp OK
Power on
|
50x | |
|
558
|
Mon May 8 02:11:37 2017 |
OH, TD | Monday 8 May | 10.11 DAQ continues OK
Current file May2017/R1_58
|
11x | |
|
428
|
Mon Nov 7 02:13:05 2016 |
CG, OH, TD, DK | Monday 7 November | 11.10 DAQ found stopped. No storage mode so
can't tell when, but presumably at 06.30
during LN2 fill cycle.
|
10x | |
|
278
|
Sun Jun 5 17:09:49 2016 |
CG, DK, AE | Monday 6th June | 00.45 Run R1100 started on n-rich setting
(EURICA run_1100, BigRIPS run 1165)
|
20x | |
|
358
|
Mon Sep 5 06:54:02 2016 |
TD | Monday 5 September | 14.20 R17 continues
DSSSD bias/leakage current OK - see |
16x | |
|
765
|
Mon Nov 5 01:40:10 2018 |
CA, CB, TD, OH, PJW | Monday 5 November | 10.40 Lowered slow comparator threshold from
100 to 10
Good event statistics ok (attachment |
16x |
|