  86   Mon Sep 27 06:42:45 2021 RSS JMCARME baking status -6
Current temperature ~102 C. Was set
in the manual mode since last evening 18:54.
See
plot and screen attached.


Current
 Screenshot_from_2021-09-27_07-41-06.pngScreenshot_from_2021-09-27_07-41-39.png 
  90   Tue Sep 28 06:40:22 2021 RSS JMCARME baking status -8
Current temperature ~120 C, increasing
See
plot and screen attached.

Current pressure
~1.07E-6 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-28_07-38-53.pngScreenshot_from_2021-09-28_07-39-22.png 
  91   Tue Sep 28 12:18:54 2021 RSS JMCARME baking status -9
Current temperature ~130 C, was set
to 130 C on manual mode around 10:00 am
See
plot and screen attached.

Current pressure
 Screenshot_from_2021-09-28_13-17-51_1.pngScreenshot_from_2021-09-28_13-18-18.png 
  92   Tue Sep 28 18:53:13 2021 RSS JMCARME baking status -10
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~9.98E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-28_19-54-16.pngScreenshot_from_2021-09-28_19-51-19.png 
  93   Wed Sep 29 06:49:41 2021 RSS JMCARME baking status -11
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~6.08E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-29_07-48-03.pngScreenshot_from_2021-09-29_07-48-36.png 
  96   Wed Sep 29 15:34:07 2021 RSS JMCARME baking status -12
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~4.51E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-29_16-32-50.pngScreenshot_from_2021-09-29_16-31-48.png 
  97   Thu Sep 30 06:29:39 2021 RSS JMCARME baking status -13
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~4.07E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-30_07-29-02.pngScreenshot_from_2021-09-30_07-28-09.png 
  98   Thu Sep 30 18:16:52 2021 RSS JMCARME baking status -14
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-09-30_19-18-44.pngScreenshot_from_2021-09-30_19-18-08.png 
  99   Fri Oct 1 07:17:46 2021 RSS JMCARME baking status -15
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-10-01_08-17-02.pngScreenshot_from_2021-10-01_08-16-41.png 
  156   Wed Nov 17 07:12:22 2021 RSS CB + ML (remotely)CARME baking with tape continues 17 NovCARME baking with heating tape continues

Left overnight at -

Ch1-3: 140 degrees
 7x 
  160   Mon Nov 22 08:06:01 2021 RSS CB + MLNEG activation starts08:20 Temperature of channels 1-3 and 5-6
were reduced to 120 degrees. Immediately
after, the conditioning of the NEGs was stopped
 IMG_5674.JPGCARMEtemps.pngvacplot.png 
  640   Sun Jun 16 13:29:05 2024 RSS CBRun 78Target clogged?   
  145   Mon Nov 8 17:19:02 2021 RSS + OGNeg and ion cables connectedNeg and ion pump cables were labeled and
connected.

Kapton tape wrapped around the
 IMG_5480.JPGIMG_5483.JPGIMG_5488.JPG 
  146   Tue Nov 9 15:03:29 2021 RSS + OGBurnt cables issuesUpper part of the frame was mounted. In
order to do so, the valve was closed, turbo
wire and hose were disconnected and then
 7x 
  151   Thu Nov 11 11:44:58 2021 RSS + ML OG + CB (remotely)CARME baking startedWith the help of OG, the baking tent was
built. MG started baking around 11:30 am
with a rate of 0.2 K/minute.
 IMG_5535.JPGIMG_5537.JPGIMG_5531.JPGIMG_5534.JPGIMG_5539.JPG 
  149   Wed Nov 10 18:24:12 2021 RSSThermocouple labelling1. Detector

2. Chamber back

3. Strain relief
 labeling.JPG.svgLabelling.svgIMG_5512.JPG 
  428   Tue Jul 25 09:12:15 2023 RSSBuilding tent
10:10  IE514 2.0e-08mbar

Upstream
part of the CARME is covered.
 BD01C0C8-5181-49B8-8751-AD4C99A459CC.jpeg7B3836F1-8A7E-491B-AFDC-46033BF84760.jpeg 
  429   Wed Jul 26 08:28:09 2023 RSSBuilding tent
09:26  IE514 1.96e-08mbar
 IMG_9897.jpgIMG_9899.jpgIMG_9901.jpgIMG_9902.jpg 
  430   Thu Jul 27 09:43:56 2023 RSSThermocouples connected -2
10:30  IE514 1.80e-08mbar

Most
of the CARME is covered by the baking tent.
The tent needs to be closed and a bit covered
 IMG_9920.jpgIMG_9919.jpg 
  639   Sun Jun 16 06:02:31 2024 RSSRun 77Run 77 started at 06:48

Cooler voltage setpoint 247.0 V.

 