Entry  Thu Sep 23 13:31:12 2021, JM RSS ML, IE514 Gauge and Bakeout 20210923_113239.jpg20210923_134339.jpg20210923_134355.jpg20210923_135954.jpg
CARME setup checked by vaccum group this morning. 

Both IE514 gauges de-gassed. To de-gas on the CM52 controller select the channel and hold the right arrow for two seconds. The reading will flash
indicating the de-gassing procedure, this lasts for 2 minutes before completing. Flashing automatically stops once procedure finishes. Attached for convinience
Entry  Fri Sep 24 07:04:57 2021, RSS JM, IE 514 pin arrangement and degas instructions IE514_pin_arrangement.JPGdegas_function.jpg
Fabre (German)       Color (English)

grau                        
grey
Entry  Thu Feb 10 09:12:41 2022, OH, CB, US, Hourly motor movement 220209_1014_leakage.png220210_1443_BiasFeeOn.png
To test effect of the motors on the leakage current, they were cycled once per hour overnight at approximately 50 minutes past the hour. - attachment 1
Leakgage current was seen to decrease slowly overnight before flattening out.
Entry  Tue Feb 8 08:13:53 2022, OH, CB, DF, Hopefully effect of beam tuning on detectors 9x
09:00 Detector still biased to 60V and leakage current has been mostly stable overnight.
      Only minor fluctuations observed - attachment 1
Entry  Sat Oct 9 09:44:36 2021, CB RSS, Heaters removed + motors tests 
Removed thermocouples, heaters, RE72 modules and leftover baking tent. Support octagon removed except topmost part which requires disconnecting pneumatic
hoses going to top gate valve. To be done on Monday with ML assistance.

Attempted to move servo motors once more - did not work. The motors appear stuck but it is not clear how or where. Removed screws on flanged
    Reply  Thu Nov 11 14:01:00 2021, AK, ML, Heater channel layouts 2020.11.05_Cryring-YR09-baking-layout.pdf
Schematic layout of heaters and channel assignment attached. Table kindly provided by AK. I hope the conversion from excel to pdf didn't swallow
any important information.
Entry  Thu Apr 17 08:51:29 2025, JM, Grounding cont. 29x
09:00

Came in to see the bias for DSSD4 which has been fluctuating for the past few days had tripped during the night. From the gnuplot it looks like
it was fluctuating all night and just after midnight it went above 20uA and tripped.
Entry  Sat Feb 12 19:48:38 2022, JM, CB, Grounding and movement tests 11x
> Initial grounding see final grounding from elog 187. ASIC settings for all - LEC slow comparator 0x64. Note on 11/02/22 1.8*L widths with same settings
were aida1-4: 300,240,250,260

ADC data items <10k
Entry  Sat Jan 29 11:04:07 2022, JM, OH, Grounding and Pulser Silkscreen_Top.pdf
Grounding

Ground cables have been daisy chained together from FEE to FEE. Ground cables are screwed into a feee bolt hole on the FEE body using an M3 bolt. 

LEMO cables have been connected in a similar way between the grounds on the adaptor boards for each FEE. Short LEMO cables go between J6 on pairs
Entry  Fri Feb 4 12:49:54 2022, TD, JM, Grounding Tests and current status  10x

JM plans to install new crimped, 3mm dia copper drain wires (a la AIDA@DESPEC) this afternoon. 
Entry  Wed Apr 16 08:20:05 2025, JM, Grounding  14x
09:00

Leakage currents this morning again appear to have lowered during the night. Current plot shows a day/night variation but I think the minimum
is decreasing ever so slightly.
Entry  Thu Feb 17 16:26:27 2022, JM, CB, SD, Gauges OFF, Pulser Movement tests 7x
Edinburgh group ion gauge turned OFF -> decrease in leakage current from 10.05 uA to 6.5 uA

GSI vacuum group ion gauge turned OFF -> decrease in leakage current from 6.5 uA to 3.63 uA

GSI large ion pump turned ON -> no effect on leakage current
Entry  Thu Sep 2 21:04:26 2021, CB RSS ML + DR OG, Gate valves mounted + pump down 6x
Mounted both gate valves and support. Gate 
valves could not be installed one bolt 
rotated from 90 degrees as per drawings 
Entry  Tue Dec 7 09:39:59 2021, CB (remotely), Gate valves closed 
Dry run complete.

YR09 section valves closed. Section isolated. Manual valve between electron target and CARME remain open.
Entry  Tue Nov 30 10:49:43 2021, CB (remotely) GV, Gate valve opened vacplot24.png
GSI vacuum division IE514 gauge connected.

Gleb reports gate downstream opened. Vacuum goes up and recovers as expected.
Entry  Thu May 30 07:25:53 2024, Yuri, Phil, Nikos, Gas target 
The cave is closed and beam is back

The d intensity is about half of the intensity before the break

The gas target is prepared but the valvas cannot be opened. Anton is coming in at around 1 PM to open the gate valves.
Entry  Sat Oct 23 12:58:11 2021, JM, GSI vacuum and bakeout testing summary GSI_fullpumpdown.pngGSI_pumping.pngBakeout-elog.pngfit-elog.pngActivation-elog.png
Attachment 1 shows the pump-down of the CARME chamber at GSI before installation of kapton cabling inside the chamber and mounting of the chamber on
the ring. Discontinuity in the plot is from switching between the pirani gauge and IE514 gauge. The pumping of the chamber in the turbo regime follows
the power law where P ~ 1/(nt) due to outgassing from the chamber being dominated by water outgassing which has an n ~1 dependence (for first order
Entry  Fri Jan 5 12:29:10 2024, JM, CB, Further bias tests 
Biased detectors this morning to 150V, the leakage current for all detectors appears stable and is ~3.5 uA. We have also replaced the CAEN bias module
so that all channels are now functional. Detectors are connected as follows;

CHN0 -> Top left
Entry  Fri Dec 4 16:49:36 2020, TD, Friday 4 December 7x
 
Entry  Fri Apr 4 10:17:16 2025, TD, Friday 4 April 

10.43 Reboot carme-gsi - unable to open a working terminal