ID Date Author Subjectdown Text Attachments
  76   Thu Sep 23 13:31:12 2021 JM RSS MLIE514 Gauge and BakeoutCARME setup checked by vaccum group this
morning. 

Both IE514 gauges de-gassed. To
 20210923_113239.jpg20210923_134339.jpg20210923_134355.jpg20210923_135954.jpg 
  78   Fri Sep 24 07:04:57 2021 RSS JMIE 514 pin arrangement and degas instructionsFabre (German)      
Color (English)

grau                        
 IE514_pin_arrangement.JPGdegas_function.jpg 
  191   Thu Feb 10 09:12:41 2022 OH, CB, USHourly motor movementTo test effect of the motors on the leakage
current, they were cycled once per hour overnight
at approximately 50 minutes past the hour.
 220209_1014_leakage.png220210_1443_BiasFeeOn.png 
  189   Tue Feb 8 08:13:53 2022 OH, CB, DFHopefully effect of beam tuning on detectors09:00 Detector still biased to 60V and leakage
current has been mostly stable overnight.
      Only minor fluctuations observed -
 9x 
  114   Sat Oct 9 09:44:36 2021 CB RSSHeaters removed + motors testsRemoved thermocouples, heaters, RE72 modules
and leftover baking tent. Support octagon
removed except topmost part which requires
  
  153   Thu Nov 11 14:01:00 2021 AK, MLHeater channel layoutsSchematic layout of heaters and channel
assignment attached. Table kindly provided
by AK. I hope the conversion from excel to
 2020.11.05_Cryring-YR09-baking-layout.pdf 
  675   Thu Apr 17 08:51:29 2025 JMGrounding cont.09:00

Came in to see the bias for DSSD4
which has been fluctuating for the past few
 29x 
  192   Sat Feb 12 19:48:38 2022 JM, CBGrounding and movement tests> Initial grounding see final grounding
from elog 187. ASIC settings for all - LEC
slow comparator 0x64. Note on 11/02/22 1.8*L
 11x 
  181   Sat Jan 29 11:04:07 2022 JM, OHGrounding and PulserGrounding

Ground cables have been daisy chained
together from FEE to FEE. Ground cables are
 Silkscreen_Top.pdf 
  187   Fri Feb 4 12:49:54 2022 TD, JMGrounding Tests and current status
JM plans to install new crimped, 3mm dia
copper drain wires (a la AIDA@DESPEC) this
 10x 
  674   Wed Apr 16 08:20:05 2025 JMGrounding 09:00

Leakage currents this morning again
appear to have lowered during the night.
 14x 
  206   Thu Feb 17 16:26:27 2022 JM, CB, SDGauges OFF, Pulser Movement testsEdinburgh group ion gauge turned OFF ->
decrease in leakage current from 10.05 uA
to 6.5 uA
 7x 
  53   Thu Sep 2 21:04:26 2021 CB RSS ML + DR OGGate valves mounted + pump downMounted both gate valves and support. Gate

valves could not be installed one bolt 
 6x 
  166   Tue Dec 7 09:39:59 2021 CB (remotely)Gate valves closedDry run complete.

YR09 section valves closed. Section
isolated. Manual valve between electron target
  
  165   Tue Nov 30 10:49:43 2021 CB (remotely) GVGate valve openedGSI vacuum division IE514 gauge connected.

Gleb reports gate downstream opened.
Vacuum goes up and recovers as expected.
 vacplot24.png 
  561   Thu May 30 07:25:53 2024 Yuri, Phil, NikosGas targetThe cave is closed and beam is back

The d intensity is about half of
the intensity before the break
  
  131   Sat Oct 23 12:58:11 2021 JMGSI vacuum and bakeout testing summaryAttachment 1 shows the pump-down of the
CARME chamber at GSI before installation
of kapton cabling inside the chamber and
 GSI_fullpumpdown.pngGSI_pumping.pngBakeout-elog.pngfit-elog.pngActivation-elog.png 
  458   Fri Jan 5 12:29:10 2024 JM, CBFurther bias testsBiased detectors this morning to 150V,
the leakage current for all detectors appears
stable and is ~3.5 uA. We have also replaced
  
  36   Fri Dec 4 16:49:36 2020 TDFriday 4 December   7x 
  661   Fri Apr 4 10:17:16 2025 TDFriday 4 April
10.43 Reboot carme-gsi - unable to open a
working terminal
  