Entry  Sun Sep 19 09:11:34 2021, CB (remotely), Baking RasPi status 
Accessed Pi remotely 

( 1. Without the Internet, the Pi has no way of knowing what time is it.
Entry  Fri Sep 17 16:42:25 2021, JM RSS ML + OG, CARME Realignment + Thermocouple installation 8x
Laser surveying team worked till 11. Chamber was too high by 3mm close to the jet target and 6mm by the turbo pump (towards the dipole). 

CARME lowered appropriate amount using bolts under CARME feet. Height checked using a laser on the centre point line of the middle flange turbo
end and mid point on the front of the chamber (see images). During lowering front foot swapped and valve supports moved slightly to give more clearance
Entry  Thu Sep 16 15:24:29 2021, JM RSS, CARME vented + thermocouple feedthrough 1.jpg2.jpg3.jpg
Chamber has been vented back to atmosphere. 

Motor was able to be pulled back to insert bloacking pin once at atmosphere.

Thermocouple feedthrough constructed with 4 thermocuples attached. Internal thermocouples each ~200mm in length with external thermocouples each
Entry  Sat Sep 11 16:01:44 2021, CB RSS, Preparations for shutdown turbo_pump.pnglog_scale.png
Found CARME pressure at 2E-7 mbar

Raspberry pi took pictures until 4 am and 
Entry  Fri Sep 10 18:09:14 2021, CB RSS ML, Leak test + baking system test 
Leak tested CARME via He leak tester + He 
bottle. No leaks could be found. Some 
indication of potential leak close to 
Entry  Fri Sep 10 10:50:55 2021, CB RSS ML, Pressure after overnight pump down 20210910_101131.jpg
Pressure found in 10-7 mbar range.

Decided to leak test anyway for safety.
Entry  Thu Sep 9 13:01:07 2021, CB RSS + OG, All feedthrough flanges mounted and motor rotated 20210909_111933.jpg20210909_112120.jpg20210909_112125.jpg20210909_133027.jpg
Moved cables that touched neg pumps. See 
photos. Please bear in mind perspective.
Note avoiding touching chamber 
Entry  Wed Sep 8 17:03:07 2021, CB RSS + OG NB, Six feedthrough flanges mounted 23x
Continued to mount flanges as per previous ELOG entry.
Peter also remarked that the wires look a bit loose inside the holes, although this is how they were during
dirty tests in Edinburgh.
Entry  Wed Sep 8 10:52:54 2021, CB RSS + OG, First feedthrough flange mounted 20210908_101743.jpg20210908_111958.jpg20210908_112002.jpg20210908_112006.jpg20210908_112010.jpg
Assembled feedthrough flange with re-cut 
SS support bracket. M3 vented on the 
sides, M3x30 partly threaded on top. Top 
Entry  Tue Sep 7 14:10:02 2021, CB RSS + OG, Strain relief SS support re-drilled 
Re-drilled SS supports in order to fit M3 screws.

Used hand tool cleaned with alchool for 6 of the 8.
Entry  Tue Sep 7 12:40:43 2021, CB ML + RH, CARME survey preparation 
Rudi and survey group representative came 
to CARME. 
Entry  Tue Sep 7 11:37:05 2021, CB RSS + OG, Update on strain relief screw issues 
Tested every strain relief. M3 screws get stuck at different points in each hole. Only one good hole out of 16
(2x8).
They were tested in Edinburgh - unclear if this is a result of baking at high temperatures, or bad screws, or
Entry  Mon Sep 6 14:13:17 2021, CB ML, Motors mounted - first attempt 20210906_113522.jpg20210906_113519.jpg20210906_115601.jpg20210906_152607.jpg20210906_143944.jpg
Mounted both  motors on CARME. Started 
with outside motor.
Entry  Sat Sep 4 15:54:50 2021, CB RSS, Motor mounting preparation 20210904_162517.jpg20210904_162520.jpg
Prepared the motors to be mounted and 
found all components required. No issues. 
May have to partly dismount again to fix 
Entry  Fri Sep 3 15:55:00 2021, CB RSS, Issues with cable clamps 20210903_154614.jpg20210903_162519.jpg
Attempted to mount cable clamps for strain 
relief on inner part of Allectra 
feedthroughs.
Entry  Fri Sep 3 14:14:40 2021, TD, Leybold IE514 manual & calibration data 20210903_141201.jpgIonivac_Sensors_IE414_IE514.pdf
 
Entry  Fri Sep 3 08:14:51 2021, CB RSS, Issues foreseeable splitting CARME 7x
In order to install the detector supports 
and eventually install the detectors 
themselves CARME must be split and 
Entry  Fri Sep 3 08:12:39 2021, CB RSS, Pressure after overnight pump down 20210903_085646.jpgIMG_4487.JPG
03.09.2021   09:00   5.27E-7 mbar     
03.09.2021   13:00   4.08E-7 mbar                   
Entry  Thu Sep 2 21:04:26 2021, CB RSS ML + DR OG, Gate valves mounted + pump down 6x
Mounted both gate valves and support. Gate 
valves could not be installed one bolt 
rotated from 90 degrees as per drawings 
Entry  Thu Sep 2 10:41:16 2021, CB RSS + DR OG, CARME connected to the CRYRING 20210902_114031.jpg
Connected CARME to the CRYRING via tube 
plus bellows. See attach.