60
|
Tue Sep 7 11:37:05 2021 |
CB RSS + OG | Update on strain relief screw issues |
Tested every strain relief. M3 screws get stuck at different points in each hole. Only one good hole out of 16
(2x8).
They were tested in Edinburgh - unclear if this is a result of baking at high temperatures, or bad screws, or
something else.
Easiest solution may be to re-machine holes and clean the connectors here in GSI.
Now investigating options. |
62
|
Tue Sep 7 14:10:02 2021 |
CB RSS + OG | Strain relief SS support re-drilled |
Re-drilled SS supports in order to fit M3 screws.
Used hand tool cleaned with alchool for 6 of the 8.
Had to use machine for another two with thread damaged.
All 8 will be sent for cleaning. Should be able to start mounting at least the 6 ones tomorrow.
Reason for lack of fit still not clear. They were tested in Edinburgh. Possibly result of high-temperature baking? |
63
|
Wed Sep 8 10:52:54 2021 |
CB RSS + OG | First feedthrough flange mounted |
Assembled feedthrough flange with re-cut
SS support bracket. M3 vented on the
sides, M3x30 partly threaded on top. Top
screws don't touch the
Macor (by design? See first attachment).
Macor affixed but has
some play - good for thermal dilation.
Mounted long wire harness (side flange) on
top. Unable to get one of the two
connectors fully in. Unable to get it out
as well. See last attach, it's a small gap.
Tested few pins with multimeter - all ok.
Decided to mount.
No issues mounting. Slowly and carefully
threaded wires harness in CARME taking
care not to hit negs.
Slightly concerned about weight of Macor
connector on wires, but no obvious
alternative.
Please have a look at attachments and
comment. Will keep mounting in the
afternoon. |
Attachment 1: 20210908_101743.jpg
|
|
Attachment 2: 20210908_111958.jpg
|
|
Attachment 3: 20210908_112002.jpg
|
|
Attachment 4: 20210908_112006.jpg
|
|
Attachment 5: 20210908_112010.jpg
|
|
65
|
Thu Sep 9 13:01:07 2021 |
CB RSS + OG | All feedthrough flanges mounted and motor rotated |
Moved cables that touched neg pumps. See
photos. Please bear in mind perspective.
Note avoiding touching chamber
bottom is not possible.
Re-installed motor to fix alignment
issues. All good. See attached.
Started pumping down. Reached 3E-1 mbar in
20 minutes (ok). Turbo on. After one hour
turbo stable at 0.85 A, pressure on Pirani
at 1.1E-2 (not reliable).
IE514 doesn't report pressure, i.e. > 1E-4
mbar.
Leak likely. Will try to pinpoint
tomorrow. We only changed 10 flangese. |
Attachment 1: 20210909_111933.jpg
|
|
Attachment 2: 20210909_112120.jpg
|
|
Attachment 3: 20210909_112125.jpg
|
|
Attachment 4: 20210909_133027.jpg
|
|
142
|
Wed Nov 3 16:39:01 2021 |
CB RSS + NP DR NK ML | Interaction chamber lifted in place |
Prepared to move interaction chamber in place. Ok CARME side, flange has M10 bolts. On interaction chamber side i.e. bellows it has M8 bolts.
DS designed this to have loose fit under assumption of M10 side actually being 3/8 holes i.e. 9.9 mm. However holes are 10.2 mm. Furthermore Grossmontage suggest loose fit will be damaged in baking in the long term.
Dismounted bellow ring from spare bellows. Re-drilled to M10 and cleaned. Remounted. Old bellow outer ring moved with spare bellows.
Lifted interaction chamber in place. Alignment started. Will finish tomorrow morning, followed by pump down and leak test. Last step before beginning final pump down should be mounting Be window on Friday. Need US for that. |
Attachment 1: 20211103_161553.jpg
|
|
Attachment 2: 20211103_161813.jpg
|
|
Attachment 3: 20211103_175457.jpg
|
|
48
|
Tue Aug 31 18:34:41 2021 |
CB RSS + DR OG | CARME on Al stand |
Lifted CARME off the floor and mounted feet on sides. It was found impossible to put four bolts for each foot
due to alignment conflict. Three bolts were mounted per foot instead.
One of the mounting holes in CARME has been damaged and the thread has been ruined. Simple rethreading attempts
failed. Three good holes left - not an issue for now.
One of the shims between the feet and the chamber had to be modified in the workshop. Some feet were rather
difficult to mount, but in the end we succedeed.
CARME was then lifted on the Al frame and gently dropped. The crane remains in place overnight to prevent it
falling over given it is not anchored to the floor.
Front foot and back foot were also mounted.
Elbows at the back were mounted.
Currently considering whether to mount gate valves before or after lifting in place on YR09. Lift experts will
decide tomorrow what is the easiest procedure given constraints on the ring.
See other attachment and next entry for current status.
YR09 downstream will be cleared tomorrow morning. Lift will proceed tomorrow afternoon. |
Attachment 1: 20210831_144545.jpg
|
|
Attachment 2: 20210831_171442.jpg
|
|
Attachment 3: 20210831_171447.jpg
|
|
Attachment 4: 20210831_171449.jpg
|
|
Attachment 5: 20210831_171453.jpg
|
|
52
|
Thu Sep 2 10:41:16 2021 |
CB RSS + DR OG | CARME connected to the CRYRING |
Connected CARME to the CRYRING via tube
plus bellows. See attach.
Had to lift CARME slightly wrt yesterday
beam alignment to get a straight tube. |
Attachment 1: 20210902_114031.jpg
|
|
143
|
Fri Nov 5 12:27:11 2021 |
CB RSS + DR NP ML US | First pump down of YR09 |
Tightened all flanges.
Added Pirani gauge and third IE514 to interaction chamber.
Stated pump down. Around 100 mbar on Interaction chamber Pirani gauge very loud metallic noise is heard. Found bellows between CARME and interaction chamber completely pressed flat. CARME and interaction chamber now much closer. Vented immediately. No pictures. Bellows return to normal state.
Repeated slowly and carefully using theodolite laser on reference point on CARME. Found CARME does not move appreciably forward, thus motion must come from interaction chamber frame.
Mounted two feet between CARME and interaction chamber. Pumped down again. Interaction chamber now moves by few mm. No issues with bellows. Left pumping overnight (Thu 4 November)
Found at 1E-6 mbar this morning. Leak tested. Found four minor leaks. Fixed by tightening.
US + Kosmos installed Be window. Pumping down extremely slowly. 1 mbar per 2 second. Started turbo at 1 mbar. Pumping down overnight. No damage to window.
See attached new plastic free struts and motion of interaction chamber before after pumping. See skull nose. |
Attachment 1: 20211105_131748.jpg
|
|
Attachment 2: 20211105_135918.jpg
|
|
Attachment 3: 20211105_135929.jpg
|
|
Attachment 4: 20211105_140451.jpg
|
|
Attachment 5: 20211105_150616.jpg
|
|
141
|
Wed Nov 3 11:18:11 2021 |
CB RSS + DR NK ML | Leak closed |
Found CARME at 1.0E-6 mbar. Beginning leak test.
Found leaks in the same location as before. Roughly 1~3E-8 mbar l second vs. base leak of 1E-12
Tightened right hand half of bolts to 120 Nm. No changes but leak goes up to 1E-10 mbar l second when tightening bolts closer to leak location, without He being sprayed.
Tightened bolts closer to leak to 140. Leak goes down to 1E-9 mbar l second
Tightened four bolts closest to leak to 170 Nm. Leak disappeared (<1E-11 mbar). Tested repeatedly all around CARME including left hand side of 600 COF flange. No leaks.
Vented. Installing jet target in the afternoon.
|
Attachment 1: 20211103_110244.jpg
|
|
Attachment 2: 20211103_110414.jpg
|
|
51
|
Wed Sep 1 17:14:16 2021 |
CB RSS + DR ML | CARME mounted on the CRYRING |
Lifted CARME with Al support on the
CRYRING. No issues during transportation.
Drilled new holes in the Al feet to fit
elephant feet. Unclear if the issue is
with the model, the frame or the feet
themselves. In any case this issue is
sorted.
CARME was designed to interface with the
CRYRING via the cross section with pumps
and sensors that we decided dismount. To
replace this section a length of xhv
tubing and a bellow will be employed.
Prepared today, to be mounted tomorrow.
Aligned CARME height with beam height.
This posed issues due to difficulty to
adjust bolts under the cross members used
to support the motors. See previous log
entry.
Bolts under those cross members are now
only finger tight. Unclear whether the
CARME section will drop slightly if
disconnected from main body. It's the
section housing the moving Dssds. May be
an issue for tightening it back. Will
investigate.
Gate valves and supports to be installed
tomorrow morning. |
Attachment 1: 20210901_162435.jpg
|
|
Attachment 2: 20210901_173059.jpg
|
|
Attachment 3: 20210901_174157.jpg
|
|
Attachment 4: 20210901_134635.jpg
|
|
Attachment 5: 20210901_173059.jpg
|
|
46
|
Tue Aug 31 07:09:54 2021 |
CB RSS (rem) JM | Preparation for mounting |
(30 August 2021)
The current state of YR09 is as per attach 1. CCC has been removed, but additional pumps and gauges remain. Some
will have to be mounted on CARME. Dismounting is scheduled for this Wed.
CB and RSS have been preparing for CARME to be mounted. JM supplied pictures of mounting process in DL. Attach 2-5.
2: Studs on carriages
3: CARME feet
4: Back foot
5: Elbows support
All components required have been located in the boxes except
- Cap hex bolts (M4 x 12?) to mount studs on carriages
- Plastic rails to remove cariages (a solution with bubble-wrap was found. Extra carriages are now in a box. Do
not turn it around.)
- Baking tray does not fit with carriages. Unclear how it did before. Will try to file down edges today.
- Bolts for CARME feet are of rather poor quality, and a host of different sizes. We may have to buy some, but
unclear what length.
- Studs are of different heights. That was not clear from previous pictures (attach 6)
- New and improved valve/elbow support (attach 7) is aligned worse than old one. Will keep using old one. Should
still work somehow. |
Attachment 1: 20210830_110920.jpg
|
|
Attachment 2: Al_frame.jpg
|
|
Attachment 3: 20200814_142437.jpg
|
|
Attachment 4: 20200902_153219.jpg
|
|
Attachment 5: 20210830_160613.jpg
|
|
Attachment 6: 20210830_115903.jpg
|
|
47
|
Tue Aug 31 11:55:11 2021 |
CB RSS | Last preparations for CARME lift |
Found strut bolts in the bag with
spherical washers. Mounted the struts and
the washers. See attach 1.
Vented CARME in preparation for lift.
Turbo off
Pressure starts increasing without
introducing leaks. Up to 10-4 mbar. IE 514
off.
Removed plastic cap from leak valve.
Pressure rate increases. Leaky valve?
Turbo motor speed reaches 0 Hz in 1h
Opened leak valve. Scroll off. Pressure to
10 mbar. Not increasing anymore. Turbo
leak aperture likely to small to vent
CARME volume.
Disconnected scroll. Carefully let air in
by tweaking flexible hose connection. Not
recommended again, but should be safe
given turbo fully stop and chamber nearly
vented.
Reached atmosphere in 10 minutes.
Now waiting for lifting support to mount
feet. |
Attachment 1: 16304077162843806956479048661374.jpg
|
|
Attachment 2: 16304077904321905824276870110392.jpg
|
|
50
|
Wed Sep 1 12:05:28 2021 |
CB RSS | Preparation for CARME on CRYRING YR09 |
Mounted additional cross member for motor
support. See attach 1
Washer required to make it fit on foot on
one side.
Holes in Al support are not matching elephant feet...! Will have to re-
drill them now.
Yr09 fully dismounted downstream |
Attachment 1: 20210901_125504.jpg
|
|
Attachment 2: 20210901_125517.jpg
|
|
54
|
Fri Sep 3 08:12:39 2021 |
CB RSS | Pressure after overnight pump down |
03.09.2021 09:00 5.27E-7 mbar
03.09.2021 13:00 4.08E-7 mbar
09;00 Will keep pumping down this morning. |
Attachment 1: 20210903_085646.jpg
|
|
Attachment 2: IMG_4487.JPG
|
|
55
|
Fri Sep 3 08:14:51 2021 |
CB RSS | Issues foreseeable splitting CARME |
In order to install the detector supports
and eventually install the detectors
themselves CARME must be split and
separated via rails.
However it does not look like we have
sufficient clearance on either side. See
pictures attached.
I suggest we mount the strain relievers
wires and motors, not split CARME, and
pump down + bake to give us time to figure
out what is different from the models and
how to fix it. Outgassing from detector
supports should be negligible wrt wires.
One possibility would be to install rail
extension on the back side of the Al frame
where the cross was meant to be supported,
temporarily remove the tube connecting
CARME to the YR09 valve and slide CARME
back. Will need to discuss with Peter. |
Attachment 1: 20210903_085801.jpg
|
|
Attachment 2: 20210903_085805.jpg
|
|
Attachment 3: 20210903_085811.jpg
|
|
Attachment 4: 20210903_085822.jpg
|
|
Attachment 5: 20210903_085958.jpg
|
|
Attachment 6: 20210903_090003.jpg
|
|
Attachment 7: 20210903_090024.jpg
|
|
57
|
Fri Sep 3 15:55:00 2021 |
CB RSS | Issues with cable clamps |
Attempted to mount cable clamps for strain
relief on inner part of Allectra
feedthroughs.
SS support mounted with M3 vented screws
OK
Cannot figure out which bolt type to use
to fix Macor on SS support.
M2 falls through
M3 screws in partly and gets stuck...
Will need to figure out how to get unstuck
No M2.5 bolts available.
In contact with Peter. Not clear what the
solution was
Will try again tomorrow or move to motors
first. |
Attachment 1: 20210903_154614.jpg
|
|
Attachment 2: 20210903_162519.jpg
|
|
58
|
Sat Sep 4 15:54:50 2021 |
CB RSS | Motor mounting preparation |
Prepared the motors to be mounted and
found all components required. No issues.
May have to partly dismount again to fix
bellows depending on ease of mounting.
Note extremely long screws mentioned in
previous Elog inventory are to be used for
the motors.
Attempted to swap Pirani gauge with ours
but realised it's CF and needs appropriate
port without risk of baking. That port
would be on the interaction chamber which
is not going to be mounted. Will probably
keep using ABD gauge for now.
Peter spotted mistake in mounting front
foot of CARME which is back to front.
Correct mount will gain us 2-3 cm but will
conflict with current CARME position fixed
by tube on the back. Will discuss options
with ML.
Motor mounting to take place on Mon with
local technical support. No activities
tomorrow unless a solution for the clamps
mentioned in previous entry is found (i.e.
what size bolts go on top). Peter will
check step file and we will consult with
local engineers on Mon pm. |
Attachment 1: 20210904_162517.jpg
|
|
Attachment 2: 20210904_162520.jpg
|
|
68
|
Sat Sep 11 16:01:44 2021 |
CB RSS | Preparations for shutdown |
Found CARME pressure at 2E-7 mbar
Raspberry pi took pictures until 4 am and
then lost contact with camera. Reasons
unclear. Plugging camera in / out solved
the issue. Will have to be investigated
if it happens again.
Left list of things to do with RSS. In
particular:
- Install xhv feedthrough and
thermocouples. Prepared on desk
- Install blocking pin in right hand motor
after pressure returns to atmosphere
- Cover bellows with aluminium to protect
from fibreglass when mounting tent
eventually
- Check all parts available for detector
supports with mounting sketch Peter sent (
RSS to recover sketch)
- Investigate baking program logging.
Unclear if logging is working - did we
disable it for some reason?
Valve on scroll closed. Scroll off. Turbo
off. Pressure sensors off. Raspberry pi
off.
Activities to resume on 16 September.
Attached are the pumping down plots
start point: 10.09.2021 19:00
end point: 11.09.2021 16:00
10.09.2021 19:00 1.09e-6
10.09.2021 20:00 7.57e-7
10.09.2021 21:00 6.17e-7
10.09.2021 22:00 5.36e-7
10.09.2021 23:00 4.82e-7
11.09.2021 00:00 4.42e-7
11.09.2021 01:00 4.10e-7
11.09.2021 02:00 3.84e-7
11.09.2021 03:00 3.62e-7
11.09.2021 04:00 3.43e-7
11.09.2021 15:00 2.29e-7
11.09.2021 16:00 2.31e-7 |
Attachment 1: turbo_pump.png
|
|
Attachment 2: log_scale.png
|
|
108
|
Tue Oct 5 17:30:01 2021 |
CB RSS | NEG activation tests |
Found D2000 #1 activated and at 250C (25W)
to prevent getting dirty when other NEGs
are activated. See previous entries.
Attempted activation of D2000 #2 using T
390C , rise time 30 m, hold time 90 m
After 30 m temperature inside chamber
increased by 5C. 390 C corresponds to 75
W.
Attempted activation of D2000 #3 while #2
is holding temperature. Same parameters as
above except T 400.
After 30 min, temperature in chamber up by
10 more C to 110.
Attempted activation of #4 as above.
Set #2 then #3 then #4 to 250 C after hold
time is over to protect them. All D2000
activated. Max temperature on Kapton
bundle 110 C.
Attempted activation of 2xUHV1400 linked
to top C4, channel 2.
No thermocouple available. Used power 200
W (2x100) rise time 30 m and hold time 90
min. Upon reaching 200 W no effect on
chamber interior temperature. Increased to
300 W. Temperatures increased to 120C max
roughly. Acceptable.
Had to decrease hold time to 60 m to avoid
remaining in cave alone for too long.
Likely okay with 300 W (450 C?). Left on
150W (400C?) to protect from subsequent
activations tomorrow.
Because cables are unlabeled it's not
clear how far the activated UHV1400 are
from the detectors. If close, this recipe
works. If far, we may have to use lower
power for other modules. |
Attachment 1: 20211005_131259.jpg
|
|
Attachment 2: 20211005_171403.jpg
|
|
Attachment 3: 20211005_161317.jpg
|
|
110
|
Wed Oct 6 09:47:30 2021 |
CB RSS | Neg activation tests -2 |
Attempted activating 2xUHV1400 connected to top C4, channel #3 with P 300 W (450 C?), t rise 30 min, t hold 90
min as yesterday
Power reach 300 W, hold. Temperature increased by 5C. OK.
Activated top C4, channel #4 using same set of parameters. Internal temperature increases significantly, up to
140C and still increasing.
Decreased power on channel #2 to 100 W (down from 200 W yesterday). Should correspond to 350 C or so.
Temperature still increasing.
Decreased power on channels #3 and #4 to 250 W (425 C?). Temperature stops increasing. Around 155C on kapton
bundle. OK for kapton, detectors would have broken.
Baking code detected temperature on internals >150 C and stopped baking for safety. Temperatures do not change -
heating provided by NEGs more than enough to maintain current status.
Decreased power on channel #2 to 50W (250 C?). Temperature on internals decreases slightly. No major effect.
This is likely because the UHV1400 corresponding to #2 are far from the detectors, while #3 and #4 are closer.
Decided to complete activation of #3 and #4 using 250 W. Set both to 50C after completion. Temperature of
internals decreases quickly.
Re-activated baking code when temperature on all internals <150 C. Setpoint 85C on RE72-1 and 95 on -2.
Now waiting for internals to cool down. Will activate remaining 3 sets (2+2+3 UHV1400) later today with P 200 W
(400 C?) t rise 30 min, t hold 90 min.
We know the set of 3 UHV1400 is definitely close to the kapton bundle. P 300 W (100x3) for that set. |