Mon Sep 14 12:07:40 2020, JM, CB (remotely), Baking status   
|
Mon 14 Sep 09:50
Jordan moved the TC08 picolog 2 away from the chamber and built a makeshit heatshield.
|
Sun Sep 13 08:06:25 2020, CB (remotely), Baking over the weekend -2 
|
Sun 13 Sep 08:06
Baking reached 93 C yesterday afternoon at 16:18 and paused as a result of a percieved temperature gradient in
|
Sat Sep 12 08:38:52 2020, CB (remotely), Baking over the weekend 
|
Saturday 12 Sep 08:43
Remotely checked status of baking. See attached.
|
Thu Sep 10 11:34:30 2020, TD, JM, Thursday 10 September  
|
All neg feed-throughs have now been fully installed, with ground tags
and power wires crimped and attached to the correct pins. Feed-throughs
are installed as seen in Image
|
Wed Sep 9 21:01:48 2020, JM, Neg Feedthroughs
|
4/6 of the neg feedthroughs installed. Continuity between the power pins, ground pin and the chamber has been checked, we observe 5-10 ohms between
the power pins similar to previous checks on the heaters. Also attached are the crimps for the ground tag and feedthrough connector pins. |
Fri Sep 4 15:48:25 2020, JM, Bakeout test completed 
|
Bakeout test completed. Maximum temperature reached within baking volume was 120 degrees, with baking stopped by the program due to detection of
negative temperature gradients. Negative temperature gradients due to a couple of thermocouples becoming unsecured and moving to cooler part of baking
volume. Attached documents show temperatures of thermocouples. The colour of plots are linked (all of chamber temperatures are blue etc). Temperature |
Wed Sep 2 17:01:49 2020, JM, Bakeout started and valve installation
|
Initial bakeout started which will run until friday, temperature had reached 44 degrees when I left the lab.
The bottom valve has now been installed on the main chamber |
Wed Aug 19 16:44:39 2020, JM, Neg Installs
|
Internal neg installs completed and electrically checked. |
Tue Aug 18 17:35:20 2020, TD, SAES UHV1400 pin assignment    
|
Using a digital multimeter confirmed continuity for SAES-supplied
power cable (Amphenol (circular) 6-pin plug to Han 05 plug) for
the following pins
|
Tue Aug 18 11:26:26 2020, JM, Week ending Friday 14/08/20
|
Week ending friday 14/08/20
CARME chamber securely mounted upon aluminium frame and support skis. Neg-ion pumps and right angled flanges installed. Neg pumps installed in
the wall detector section of the chamber. Neg pumps continuity checked and are electically isolated from the chamber. |
Mon Aug 17 08:16:16 2020, TD, CARME Elog
|
Test |