  446   Wed Nov 9 09:50:50 2016 TDNP1412 R20, R21
DAQ start (R20) failed - nnaida5 dropped
data transfer #1 link
 1.png2.png3.png4.png 
  445   Wed Nov 9 08:47:03 2016 OH, TDNP1412 R16, R17 and R18start 17:44
stop 17:49
AIDA filename R16
 r16bias1.pngr16bias2.png 
  444   Wed Nov 9 07:16:59 2016 OH, TDNP1412 R15Run 15

start 16:14
 6x 
  443   Wed Nov 9 02:14:08 2016 OH, TDNP1412 R1411.13 Still waiting to get beam back got access
so took temp measurement.
      T=25.6 DP=0.0 H=18.1
 bias1.pngbias2.pngR14bias1.pngR14bias2.png 
  442   Wed Nov 9 00:49:03 2016 TD, OHNP1412 R1309.50 Run 13 Start
      Thick C target (6mm) removed from F11.
All variable Al degraders put in place
 r13bias1.pngr13bias2.png 
  441   Tue Nov 8 23:36:56 2016 DK, TDNP1412 R12Takechi team changes the condition: F5
carbon; F7 empty; F11 carbon

  F11 Plastic is 1.1kHz
 10x 
  440   Tue Nov 8 23:16:15 2016 DK, TDNP1412 R11Recovered AIDA after power cycle (unknown
cause of crash from the end of R10)

Corresponding run in BRIKEN: 161109_0814_747576Ni_012
 R11_USB1.pngR11_USB2.png 
  439   Tue Nov 8 22:04:21 2016 DKNP1412 R10Put the variable Al degraders all back
in for safety (was 4.4 mm, now 5.4 mm)

Takechi team switches the condition:
 R10_USB1.pngR10_USB2.png 
  438   Tue Nov 8 21:01:40 2016 CG, DKNP1412 R906.02 R9 started with Takechi group C target
out and all variable degraders in.
      F5 C in. F7 empty. F11 empty.
  
  437   Tue Nov 8 18:52:32 2016 CG, DKNP1412 R7 R803.50 74-76Ni beam delivered to F11.
      F11 plastic rate ~1kHz.
      F5 C target in. F7 empty. F11 C target
 bias1.pngbias2.pngbias1.pngbias2.png 
  436   Tue Nov 8 15:10:16 2016 CG, TD, DK, OHNP1412 R5 R600.15 Setting changed to 71,72,73Ni. All variable
degraders in.
      Will remove while watching rates to
 bias1.pngbias2.png 
  435   Tue Nov 8 14:29:34 2016 TD, OH, DKNP1412 Run 423:28 Run 4 Start
      Thick 6mm C target in beam
      
  
  434   Tue Nov 8 14:22:16 2016 TD, OH, DKNP1412 R311:21 Run 3 Started
      Degrader moved upstream. AIDA moved
to centre of BRIKEN. Fixed degrader moved
  
  433   Tue Nov 8 13:37:06 2016 TD, OH, DKNP1412 R210:36 Run 2 Start
      Degraders (5.4mm Al) in at start and
all removed once started.
 6x 
  432   Tue Nov 8 13:06:18 2016 DK, TD, CG, OHNP1412 Run 1AIDA run with Takechi experiment. 71~73
Ni beam setting

F5 carbon target is:   
 14_JST_2016.png 
  431   Tue Nov 8 00:52:59 2016 OH, TDFEE Settings and Options filesUsed a program to sort through the settings
files located in /MIDAS/DB/EXPERIMENTS/AIDA/Settings_FIle_Name/nnaider1,2,3...
and /MIDAS/DB/EXPERIMENTS/AIDA/Options.
 FEE_Settings.xlsx 
  430   Tue Nov 8 00:12:56 2016 TDReport - medium - TapeServer changes volume name following request for existing filename
When you request a filename that already
exists and select OK to the prompt
 9.png 
  429   Mon Nov 7 23:15:14 2016 TD, CG, OHTuesday 8 November08.15 DAQ found stalled

      Soft reset OK
 12x 
  428   Mon Nov 7 02:13:05 2016 CG, OH, TD, DKMonday 7 November11.10 DAQ found stopped. No storage mode so
can't tell when, but presumably at 06.30
during LN2 fill cycle.
 10x 
  427   Sun Nov 6 05:16:22 2016 OHUpdateLeakage current spreadsheet has now been uploaded
to google docs for ease of access.
  