Sun Apr 26 02:28:59 2015, JA, LHB, TD, AE & CG, Sunday 26 April 2015 33x
|
Upstream, 207Bi source
|
Sat Apr 25 03:56:44 2015, JA, LHB, TD, AE & CG, Saturday 25 April 2015   
|
1130: Rotated forward water inlet connection to point towards rear of AIDA stand to remedy mechanical
conflict with EURICA support frame - see attachments. During drain and re-fill of Julabo FL1106
|
Fri Apr 24 08:11:04 2015, CG, AE & TD, Thursday 23 April 2015 contd
|
Image of interior of closed EURICA array with AIDA inserted. |
Thu Apr 23 10:27:59 2015, CG, AE, TD, Thursday 23rd April progress   
|
23/04/15
1800: Spent majority of the day moving AIDA forward and into EURICA.
So far everything seems to fit very well, we have just noticed a few points of possible |
Wed Apr 22 03:33:01 2015, TD, FEE64 Fast Discriminator OR o/p via MACB 
|
Illustration of the trigger timing of the AIDA FEE64 fast discriminator OR output via the
MACB front panel Trigger outputs.
|
Thu Apr 23 09:02:57 2015, TD, Patrick, FEE64 Fast Discriminator OR o/p via MACB
|
> Illustration of the trigger timing of the AIDA FEE64 fast discriminator OR output via the
> MACB front panel Trigger outputs.
>
|
Thu Apr 23 03:21:48 2015, TD, MSL type BB18(DS)-1000
|
MSL type BB18
Serial Thickness Depletion Date Note Location
|
Wed Apr 22 08:50:59 2015, CG, AE, TD, Wednesday 22nd April progress   
|
22/04/15
1230: Solved problem (empty spectra despite changing modules) with nnaida5 noted in previous progress update.
During Feb tests, nnaida5 was very noisy compared to other nnaida => switched it to medium |
Wed Apr 22 07:28:25 2015, AE (PM), Mechanical setup instructions: AIDA+EURICA at F11
|
Attached are Paul Morrall's instructions on how to move new AIDA support table into place, for a setup with
EURICA at F11 (March 2015). |
Tue Apr 21 09:39:00 2015, AE, LISE estimates for implantation setup [updated] 
|
[UPDATED 22/4: initial LISE file had incorrect thickness for MACi plastic]
Calculations for Al degrader thickness required to implant ions in AIDA DSSD stack.
|
Tue Apr 21 06:01:50 2015, CG, TD, Tuesday 21 April 2015 8x
|
21/04/15
1325: Recabled the MACB distribution tree as per PC-S instruction yesterday.
Now have nnaida5+6, 13+14 in MACB3 (nnaida5 in output 1) and nnaida3+4, 11+12 in MACB10 |
Mon Apr 20 06:53:24 2015, CG, TD, Progress 20th April + RPi procedure 7x
|
20/04/15
1200: Complete all points on first part of check list, except checking the PSU voltages.
System now in powered and has all network/HDMI cables attached. |
Mon Apr 20 09:07:59 2015, CG, TD, Patrick Coleman-Smith, Progress 20th April + RPi procedure + reply
|
Quote:
20/04/15 |
Mon Apr 20 09:38:15 2015, CG, TD, Patrick Coleman-Smith, Progress 20th April + RPi procedure + reply
|
Quote:
|
Mon Apr 20 09:45:38 2015, CG, TD, Patrick Coleman-Smith, Progress 20th April + RPi procedure + reply ++
|
Quote:
|
Mon Apr 20 07:39:49 2015, CG, TD, Rasberry Pi : USB ac mains switch + USB serial link to FEE64 console
|
It would appear that you cannot reliably startup the Raspberry Pi (nnrpi1)
connected to both the USB ac mains switch *and* the USB-serial link to FEE64
|
Sat Apr 18 09:30:11 2015, CG, To do list 19/04/15 - 21/04/15
|
To do (roughly in order):
Move shipped boxes down from Gabor's office to the experimental area. Check contents. Should include:
3x
3Tb HDD
NIM floating HV supply
2x Si detector boxes, containing MSL type BB18 detectors 3131-9 + 3131-11 and 3058-9 |
Mon Mar 9 16:51:26 2015, TD, AIDA adaptor PCB configuration - RIKEN - Feb 2015 6x
|
|
Mon Mar 9 16:45:35 2015, TD, Julabo FL11006 Recirculating Chiller: connection to 3ph ac mains 7x
|
3ph 100VAC/50Hz to Julabo FL11006 3ph 230VAC/50Hz via local transformer |
Mon Mar 9 13:59:32 2015, TD, New AIDA support frame for F11/F12 @ RIKEN
|
|
Mon Mar 9 09:02:03 2015, Patrick Coleman-Smith, Adding Filters to the AIDA PSU.
|
This guide is to help with the filter pcb assembly and installation into the AIDA power supply. |
Thu Mar 5 12:11:44 2015, TD, To Do list - March 2015
|
A draft 'to do' list in preparation for further AIDA tests at RIKEN from mid-April.
Please feel free to add your comments, suggestions, other items etc.
|
Wed Mar 4 17:38:06 2015, CG, Log book for Feb 2015 tests
|
04/03/15
Please find attached a scan of the log book for the Feb 2015 AIDA tests at RIKEN. |
Wed Feb 25 09:59:28 2015, CG, AE, Weds 25th Feb progress  
|
25/02/15
1200: Swapped out old green power switch for new one from UoE (having previously tested them both yesterday and found them to work fine).
With first switch connected and PuTTY session opened cannot get RPi to connect to |